VOLUME THREE CAPITAL IMPROVEMENT PLAN City of Scottsdale • FY 2019/20 Budget McCormick-Stillman Railroad Park, winner of the 2019 ELGL Knope Best Park & Open Space competition Photo: Sam Mitchell Photography Adopted FY 2019/20 Budget City of Scottsdale, Arizona Volume Three Capital Improvement Plan City Council W.J. “Jim” Lane, Mayor Linda Milhaven, Vice Mayor Suzanne Klapp Virginia Korte Kathy Littlefield Guy Phillips Solange Whitehead Administrative Staff Jim Thompson, City Manager Jeff Nichols, City Treasurer Bill Murphy, Assistant City Manager Brent Stockwell, Assistant City Manager Judy Doyle, Budget Director TABLE OF CONTENTS FY 2019/20 Adopted Budget – Volume Three Capital Improvement Plan Table of Contents Overview Volume Content ................................................. 1 Definition of CIP Projects ................................... 2 Recurring Capital Maintenance Projects ........... 3 CIP Review Process ........................................... 3 Funding Source of Funds ................................................. 7 Use of Funds .................................................... 11 Funds Summary & Five-Year Financial Forecast .......................................................... 18 Program Descriptions, Locations, Project Types, Funding Sources & Operating Impacts Community Facilities Program Description ........................................ 57 Library/Library Improvements ......................... 59 Neighborhood & Community ........................... 61 Parks/Parks Improvements ............................. 68 Drainage/Flood Control Program Description ........................................ 75 Drainage/Flood Control ................................... 76 Project Lists Preservation Capital Improvement Plan – Project List Alphabetical ................................................... 23 By Division ...................................................... 31 By Program .................................................... 40 Program Description ........................................ 81 Preservation/Preservation Improvements....... 82 Operating Impacts CIP Operating Impacts .................................... 49 Public Safety Program Description ........................................ 87 Fire Protection ................................................. 88 Police ............................................................... 93 TABLE OF CONTENTS Service Facilities Water Management Program Description ........................................ 99 Municipal Facilities/Improvements ............... 101 Technology Improvements ............................ 107 Program Description ..................................... 171 Transportation Program Description ..................................... 119 Aviation/Aviation Improvements .................. 123 Streets/Streets Improvements ..................... 134 Traffic/Traffic Reduction .............................. 156 Transit/Transit Improvements ...................... 159 Wastewater Improvements........................... 174 Water Improvements .................................... 183 Appendix Budget Adoption Ordinance .......................... 211 Property Tax Levy Ordinance ........................ 229 Acronyms ....................................................... 231 Glossary ......................................................... 235 Table of Contents OVERVIEW | Volume Content The City of Scottsdale’s FY 2019/20 budget is comprised of three volumes: Volume Three – Capital Improvement Plan authorizes and provides the basis for control of expenditures for the acquisition of significant city assets and construction of all capital facilities. A five-year Capital Improvement Plan (CIP) is developed and updated annually, including anticipated funding sources. Under state law, budget appropriations lapse at the end of the fiscal year. As part of the annual budget development process the city must re-budget the appropriations until the project is complete and capitalized. The CIP is prioritized based on City Council’s mission and broad goals, the city’s General Plan, Citizen Boards and Commissions recommendations, the comprehensive financial policies, including debt and capital management policies, long range financial forecasts and growth and development assumptions. The Overview section of Volume Three describes the guidelines used to define a capital project, recurring capital maintenance projects in further detail, and the city’s capital improvement plan review process, which includes review teams and prioritization criteria. The CIP prioritization criteria described are the measures used by the city’s two separate CIP review teams (Construction and Technology) to rate the various proposed construction related and technology related capital projects. The CIP review process also includes the involvement of senior management and the City Council Capital Improvement Plan Subcommittee. The overview section concludes with a summary of operating impacts for capital projects. The Funding section is a summary of the various sources of funds and how those funds are used to pay for CIP projects. The funding section concludes with the Financial Summary and Five-Year Financial Forecast. The Project Lists section includes three lists: • Alphabetical by Project Name – summarizes all capital projects in alphabetical order • By Division – summarizes all capital projects by city division • By Program – summarizes all capital projects by major program The project lists reflect each project’s adopted FY 2019/20 budget with the forecasted funding through FY 2023/24. The forecasted funding, which includes FY 2020/21 through FY 2023/24 was not adopted by City Council as part of the FY 2019/20 budget. This information serves as part of the city’s long-term capital plan process and will be revisited and updated in future budget reviews. The CIP Operating Impacts section includes a four-year summary of the projected operating costs associated with capital projects. The operating impacts for projects completed prior to or during FY 2019/20 are calculated and included in the adopted Operating Budget. Volume Three also includes detailed information arranged by major program on each of the city’s capital projects, including Community Facilities, Drainage/Flood Control, Preservation, Public Safety, Service Facilities, Transportation and Water Management. The detailed information includes location, project description, funding source(s) and project number, if applicable. Volume Three concludes with the Appendix, which includes the City Council’s ordinances reflecting the adoption of the city’s FY 2019/20 budget and property tax levy including state budget forms, a list of Acronyms and a Glossary of terms. Volume One – Budget Summary Includes the city’s annual report, City Council’s strategic goals, demographic information, transmittal letters, executive summary, an explanation of the city’s budget development process, a total budget overview, total appropriation, fund overviews, fund summaries and Five-Year Financial Forecasts as well as information on the sources, uses, transfers, and ending fund balances for each of the city’s funds. Volume Two – Division Operating Budget Provides detailed information on each of the city's divisions, including descriptions, prior year highlights, priorities, staffing, and a summary of the operating budgets by expenditure category and the applicable funding sources. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three -1- Table of Contents Definition of CIP Projects Relatively High Monetary Value Includes Long Life (Five Years or More) Results in the Creation of a "Capital Asset" or the revitalization of an existing "Capital Asset" Construction of new facilities Remodeling or expansion of existing facilities Purchase, improvement and/or development of land Operating equipment and machinery for new and expanded facilities Planning and engineering costs related to specific capital improvements Street construction, reconstruction, resurfacing or renovation In general, automotive and other rolling stock, personal computers, and other equipment not attached to or part of new facilities are not included as a CIP project. The exception to this is when the aggregate dollar amount of all the items are of a significant enough value that they are grouped together and considered a single capital project. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three -2- Table of Contents Overview OVERVIEW | Capital Improvement Plan Capital Improvement Plan Recurring Capital Maintenance Projects Recurring capital maintenance projects reflect the recurring capital expenditure needs required to preserve or replace existing city assets due to wear and tear. These projects include budget appropriation for the first year of the five-year plan and a forecast for the following four years. These projects are reviewed and evaluated as part of the annual budget development process. The desired goal is to close out the projects within one year. The first year’s appropriation may be carried forward into the next fiscal year if and when the project requires more time for completion. The recurring capital maintenance projects are assigned a project number with the prefix “Y”. CIP Review Process - The City of Scottsdale uses two cross-divisional CIP Review Teams; one for review of construction related projects and the other for review of technology related projects. The Construction Review Team consists of individuals from a variety of divisions and professional disciplines to review project submissions and ensure that: Projects are scoped properly (a building has Americans with Disabilities Act (ADA) access, includes telephones, computers, etc.) Infrastructure components are coordinated (a waterline is installed at the same time as a roadway improvement at a specific location) Long-term operating impacts are included in estimates (staffing, utility and maintenance costs are considered) Timeframes for construction activity and cash flow requirements are realistic Projects are coordinated geographically (i.e., not more than one north/south major thoroughfare is restricted at a time) Project costs are reviewed to determine the adequacy of the budget and appropriate funding sources City of Scottsdale FY 2019/20 Adopted Budget - Volume Three -3- Table of Contents Overview OVERVIEW | Capital Improvement Plan Capital Improvement Plan The Technology Review Team includes individuals from a variety of divisions to review technology project submissions and ensure that: Projects meet city’s current hardware, software and security standards Network bandwidth requirements are needed to support the application if technology will be accessed from remote locations Long-term operating impacts are included in estimates (training, maintenance and support) Funding for ongoing maintenance of hardware, operating system, application and database, if applicable, is identified Parties responsible for day-to-day support are identified Identify systems that require after hours technical support Funding is included to cover ongoing monthly communication costs associated with the system, if applicable Backups and data retention have been considered Disaster recovery and security considerations have been considered While these illustrations are not exhaustive, they provide excellent examples of the value added through project review by cross-divisional teams. Each division is required to submit new funding requests to the City Treasurer’s Office, who then compiles the information for the applicable CIP review team. If the review teams have questions concerning a request, the divisions are asked to provide input and feedback to assist the review team in prioritizing the projects against all city needs. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three -4- Table of Contents Overview OVERVIEW | Capital Improvement Plan Capital Improvement Plan The CIP review teams prioritize the projects based on City Council’s broad goals, division priorities, anticipated funding sources, and the International City/County Management Association (ICMA) Project Prioritization Matrix. The ICMA Prioritization Criteria were obtained from Capital Projects: New Strategies for Planning, Management, and Finance, Copyright 1989, pp 85-87, and adjusted for the City of Scottsdale. Eight Prioritization Criteria used by Scottsdale for Capital Projects Mayor & City Council's Strategic Goals and Priorities Distributional Effects Mandated Emergency / Negative Impact of Not Investing Master Plan Economic Vitality Annual Operating Cost Matching Funds City of Scottsdale FY 2019/20 Adopted Budget - Volume Three -5- Table of Contents Overview OVERVIEW | Capital Improvement Plan Capital Improvement Plan Capital Management Review Committee The Construction and Technology Review Teams forward their prioritization results to the Capital Management Review Committee (CMRC) for the next phase of review. This group includes senior management members who provide an enterprise-wide view for synergy and priority while balancing project requests against known City Council objectives. CIP Subcommittee and City Council After their review is completed, members of the CMRC Team present the recommended five-year CIP to the Council Capital Improvement Plan (CIP) Subcommittee so they may apply a policy perspective while considering citywide needs. The CIP Subcommittee makes funding recommendations to the full City Council. The funding recommendations and the five-year CIP plan are discussed at study sessions and public hearings prior to budget adoption. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three -6- Table of Contents Capital Improvement Plan - Source of Funds FUNDING | Source of Funds The Capital Improvement Plan (CIP) uses funding from prior year carryovers. Prior year carryovers are “blended” funding from various funding sources. For FY 2019/20 – 2023/24 the funding includes carryovers from the Bond 2015 General Obligation (G.O.) Bonds carryovers, and new funding from the Municipal Property Corporation (MPC) Bonds for Water, Stormwater and Stadium projects. These provide the bond-funded portion of the plan, which is approximately nine percent of the CIP funding in FY 2019/20 – 2023/24. Approximately 27 percent of Scottsdale’s FY 2019/20 – 2023/24 CIP is funded with Enterprise and Preservation funding, and approximately 64 percent is funded by “pay-as-you-go” revenues, which include dedicated sales tax revenues and contributions from fund balance transfers. The three percentages listed indicate that the FY 2019/20 – 2023/24 CIP follows Financial Policy No. 24, which states that pay-as-you-go Capital Improvement Plan financing should account for a minimum of 25 percent of all capital improvement projects, excluding Preservation and Enterprise for each five-year planning period. Pay-as-you-go financing is defined as all sources of revenue other than city debt issuance. The pie chart at the end of this section represents funding source percentages for FY 2019/20 – 2023/24. Funding sources for the CIP are presented on a cash flow basis. These revenue sources are presented in the period that the revenue is expected to be collected. Funding sources include estimated balances on hand at the beginning of the period as well as revenue expected to be received during the period or in future periods, i.e. bond issuances. Because revenue is presented on a cash basis, pay-as-you-go funding sources do not equal budgeted expenditures in each period, which sometimes creates a fund deficit for project expenditures in subsequent years. All potential capital funding resources are evaluated to ensure equity of funding for the CIP. The measure of whether equity is achieved is if the beneficiaries of a project or service pay for it. For example, general tax revenues and/or G.O. Bonds appropriately pay for projects that benefit the general public. User fees, development fees, and/or contributions pay for projects that benefit specific users. Other factors considered when funding the capital plan are whether the financing method provides funding when needed and the financial costs associated with the funding source. The following summarizes the funding sources for the CIP. Revenues Bond Proceeds General Obligation (G.O.) Bonds are bonds secured by the full faith and credit of the issuer. G.O. Bonds issued by local units of government are secured by a pledge of the issuer’s property taxing power (secondary portion). They are usually issued to pay for general capital improvements such as fire stations and pavement replacement. Municipal Property Corporation (MPC) Bonds Water, Stormwater and Stadium represents bonds issued by the Municipal Property Corporation (MPC), a non-profit corporation established to issue bonds to fund city capital improvements. The debt incurred by the corporation is a city obligation and does not require voter approval. Examples of pledged revenue streams are Water Rates, Stormwater Fees and Tourism Development Funds to finance the repayment of MPC debt. Charges for Services/Other Intergovernmental Funds represents amounts paid by other organizations for capital projects through intergovernmental agreements (IGAs) and include the Maricopa County Flood Control District (MCFCD), the Salt River Pima-Maricopa Indian Community (SRPMIC) and the Maricopa Association of Governments (MAG). MAG administers the Proposition 400 revenues received from the 2004 voter approved 20-year extension of a half-cent transportation sales tax in Maricopa County that was first approved in 1985 to fund freeway construction. Other Contributions represent amounts paid by other organizations for capital projects including developers, the San Francisco Giants and the Stadium Concessionaire. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three -7- Table of Contents Capital Improvement Plan - Source of Funds FUNDING | Source of Funds Other Revenue Grant Funds represent revenues received from federal or state sources. Most grants require a matching funding source with the percentage of the match dependent on grant requirements. The funding is restricted in use to the improvements requested and approved in the grant application. Utilities & Enterprises Utilities & Enterprises funding represents revenues from several sources (groundwater treatment, reclaimed water distribution, etc.) that are aggregated for reporting purposes. Interest Earnings Interest Earnings represents interest earnings on cash balances on hand in the various funds under the Capital Improvement Program. Building Permit Fees & Charges In-Lieu Fees represent compensatory fees paid in lieu of parking and stormwater requirements established by the city. Transfers In Enterprises Funds Water and Water Reclamation Rates are utility bill revenues received from the sale of domestic water and the fees collected for the disposal of sanitary sewer waste from customers within the city. Water and water reclamation operating revenues in excess of operating expenditures are transferred to the CIP to fund water and water reclamation capital improvement projects. Aviation Fees represent fee revenues received from users of the city’s municipal airport and related facilities. Fees paid include transient landing fees, tie down fees, hangar fees, etc. Solid Waste Rates represent utility bill revenues received for the collection and disposal of solid waste from residential and commercial customers. Internal Service Funds Internal Service Funds represent revenues received for services provided to internal customers. In this instance the revenue represents self-insurance funds. Fleet Fund represents revenues from the city’s Fleet Rates and per Financial Policy No. 12 is restricted to use for improvements to facilities providing maintenance services to the city’s rolling stock, the replacement of rolling stock, and the administration of the program. General Fund General Fund represents the transfer of cash from the General Fund to fund the “pay-as-you-go” (PAYGO) contributions from general revenues for capital projects that do not have a dedicated funding source. The General Fund transfer of cash to the CIP is considered and approved by the City Council each fiscal year and complies with the city’s Financial Policy No. 17 that states it will be at a minimum (1) 25 percent of construction privilege (sales) tax revenues; (2) 100 percent of net interest income in excess of $1.0 million; and (3) two-thirds of the 1.1 percent sales tax collected on food for home consumption. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three -8- Table of Contents Capital Improvement Plan - Source of Funds FUNDING | Source of Funds Special Revenue Fund Preservation Sales Tax Fund represents revenues received from the 1995 voter approved 0.2 percent sales tax on local retail and other sales dedicated to the purpose of acquiring land for the McDowell Sonoran Preserve and revenues received from the 2004 voter approved 0.15 percent sales tax on local retail and other sales dedicated to purpose of acquiring land and constructing essential preserve related necessities such as proposed trailheads for the McDowell Sonoran Preserve. Special Programs funding represents revenues from dedicated funding sources and donations earmarked for specific purposes (i.e., Court Enhancement Fund (CEF)). Tourism Development Fund represents revenues received from the voter approved transient lodging (bed) tax of five percent on hotel and motel room rentals in addition to sales tax. Tourism development revenue is transferred to the CIP when City Council approves using it as a funding source for specific capital projects. Transportation Sales Tax (0.10%) represents revenues received from the 2018 voter approved 0.1 percent sales tax on local retail and other sales for a period of ten years. Per the city’s Financial Policy No. 26A this revenue is restricted to fund transportation improvements. Transportation Sales Tax (0.20%) represents revenues received from the 1989 voter approved 0.2 percent sales tax on local retail and other sales. Per the city’s Financial Policy No. 26, no more than 50 percent of the privilege (sales) tax revenue for transportation improvements will be allocated to transportation improvement operating expenses. Stadium Capital Improvement Fund Stadium Capital Improvement Fund represents contributions received from the San Francisco Giants and the Scottsdale Charros equivalent to forty cents per ticket sold to Spring Training games to fund ongoing capital improvements to the stadium facilities. (Subsequent to the FY 2019/20 CIP budget adoption on June 11, 2019 City Council authorized the transfer of the Stadium Capital Improvement Fund to the Operating Budget). Stormwater Fees Stormwater Fees represent the $2.95 monthly increase to the Stormwater Fees paid by utility customers. Prior Year Carryovers Prior Year Carryovers are committed funds from prior years that are re-budgeted until they are expended, uncommitted or until the projects are completed. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three -9- Table of Contents Capital Improvement Plan - Source of Funds FUNDING | Source of Funds City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 10 - Table of Contents Overview Capital Improvement Plan - Use of Funds Use of Funds Funds FUNDING | Use The Capital Improvement Plan (CIP) is comprised of seven major programs: The Use of Funds pie chart represents the percentages for each major program. Expenditures are presented on a budget basis rather than a cash flow basis. Governmental budgeting procedures require adequate budget to pay for the entire contract to be available and appropriated in the period in which a contract is entered into by the city. However, actual cash flows (expenditures) under the contract generally take place over more than one year and match cash flow funding receipts. The following summarizes the seven major programs that comprise the total Capital Improvement Plan. Community Facilities focuses on enhancing and protecting a diverse, family-oriented community where neighborhoods are well maintained. These recreational needs are met by providing library improvements, recreation facilities, parks, park improvements, multiuse paths, neighborhood enhancements, youth sports lighting, aquatic centers, library facilities and senior centers. Approximately 9.8 percent of the CIP has been identified to address the needs of this program. Drainage/Flood Control focuses on enhancing and protecting a diverse, family-oriented community where neighborhoods are well maintained by preventing property damage from flooding. This program achieves these goals through flood plain mapping, meeting regulatory requirements, and identifying and correcting hazards to reduce future flood damage potential. This is accomplished using detention basins, culvert and channel projects, and a program of neighborhood drainage improvements. Approximately 4.0 percent of the CIP has been identified to address the drainage and flood control needs of the city. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 11 - Table of Contents Overview Capital Improvement Plan - Use of Funds Use of Funds Funds FUNDING | Use Preservation focuses on preserving the character and environment of Scottsdale. This goal is met by land acquisition activities for the McDowell Sonoran Preserve for the purpose of maintaining scenic views, preserving native plants and wildlife, and providing public access to the McDowell Mountains and Sonoran Desert. The 1998 election expanded the recommended study boundary from the original 12,876 acres to 34,400 acres. The 2004 election provided an additional revenue stream (0.15 percent sales tax rate increase) as well as the bonding capacity ($500.0 million) that continues to provide authority to carry on preservation efforts. Approximately 8.0 percent of the CIP has been identified to address this program. Public Safety focuses on enhancing and protecting a diverse, family-oriented community where neighborhoods are safe. This goal is met by providing fire and police stations, training facilities and automation and communication systems related to fire and police operations. Approximately 2.6 percent of the CIP has been identified to address the public safety needs of the city. Service Facilities focuses on coordinating land use and infrastructure planning within the context of financial demands and available resources. These programs achieve this goal through the renovation of current facilities and technology needs necessary for the efficient and effective operations of the city. Approximately 2.8 percent of the CIP has been identified to address this program. Transportation focuses on providing for the safe, efficient, and affordable movement of people and goods. This program meets this goal by attempting to offer real transportation choices in a way that meets the needs of the community and include aviation, streets, traffic and transit projects. In 1989 voters authorized a 0.2 percent sales tax on local retail and other sales to fund transportation improvements. In 2004 voters approved a 20-year extension of a half-cent transportation sales tax in Maricopa County that was first approved in 1985 to fund freeway construction. Additionally, in 2018 voters authorized a 0.1 percent sales tax on retail and other sales for ten years to fund transportation improvement projects. This program looks for the best use of these funding sources and addresses the multi-modal concept. Approximately 28.5 percent of the CIP has been identified to address the transportation needs of the city. Water Management focuses on coordinating land use and infrastructure planning within the context of financial demands and available resources. This program achieves this goal by delivering safe, reliable water and providing wastewater services. This program also reflects the city’s commitment to federal and state regulations. Approximately 44.3 percent of the CIP has been identified to address the water and water reclamation needs of the city. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 12 - Table of Contents Overview Capital Improvement Plan - Use of Funds Use of Funds Funds FUNDING | Use City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 13 - Table of Contents Overview Capital Improvement Plan - Use of Funds Use of Funds Funds FUNDING | Use City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 14 - Table of Contents Overview Capital Improvement Plan - Use of Funds Use of Funds Funds FUNDING | Use City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 15 - Table of Contents Overview Capital Improvement Plan - Use of Funds Use of Funds Funds FUNDING | Use FY 2019/20 Highlights of the Capital Improvement Program City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 16 - FY 2019/20 Adopted Budget City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 17 - Table of Contents Capital Improvement Plan CAPITAL IMPROVEMENT PLAN& Five | Financial Summary Financial Summary Year Financial Forecast Beginning Fund Balance (a) Revenues Bond Proceeds Charges for Service/Other Other Revenue Utilities & Enterprises Interest Earnings Building Permit Fees & Charges Subtotal Transfers In Aviation Fund Contributions Fleet Fund General Fund Grants Fund MPC Bonds Preservation Sales Tax Fund Risk Management Fund Solid Waste Fund Special Programs Fund Stadium Capital Improvement Fund Stormwater Fee Fund Tourism Development Fund Transportation Sales Tax (0.10%) Fund Transportation Sales Tax (0.20%) Fund Water & Water Reclamation Funds Subtotal Total Sources Actual 2017/18 278,043,411 Adopted 2018/19 183,714,000 Forecast 2018/19 301,758,330 Adopted 2019/20 266,595,297 28,770,429 7,334,950 10,876,095 8,926,292 3,402,503 70,001 59,380,271 23,535,466 9,011,628 6,150,000 3,323,949 5,000 42,026,043 13,527,253 6,590,949 5,950,000 3,263,949 65,000 29,397,151 47,162,600 38,709,557 6,620,745 6,150,000 5,237,047 340,000 104,219,949 215,540 4,644,341 1,483,400 9,552,950 147,200 10,649,271 7,300 312,300 541,000 67,400 2,170,000 10,940,689 46,768,083 87,283,934 5,427,726 51,089 1,483,400 10,522,253 44,986 12,791,485 7,300 312,300 532,495 67,400 2,170,000 5,000,000 4,030,023 12,596,077 35,063,283 90,099,817 2,365,142 1,571,538 12,358,833 3,791 83,699 2,362,363 2,317 10,531 302,525 65,755 6,279,500 19,569,769 62,409,689 105,235,850 2,120,204 11,788,637 6,463 4,450,872 581,841 496,444 2,762,000 67,400 2,504,808 12,053,356 14,446,752 35,144,698 88,788,617 164,616,121 129,309,977 119,496,968 193,008,566 421,255,298 459,603,863 Total Fund Balance and Sources 442,659,531 313,023,977 (a) Prior year unexpended sources and uses of funds are estimated and included in the Beginning Fund Balance. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 18 - Table of Contents Capital Improvement Plan CAPITAL IMPROVEMENT PLAN& Five | Financial Summary Financial Summary Year Financial Forecast Actual 2017/18 Adopted 2018/19 Forecast 2018/19 Adopted 2019/20 Subtotal Less: Estimated Capital Improvement Expenditures 5,253,075 3,674,316 2,362,363 6,426,910 7,752,319 51,603,544 45,814,157 122,886,685 - 22,356,002 8,719,392 51,368,957 18,543,875 18,754,610 182,199,432 262,016,995 563,959,262 (223,224,400) 16,882,000 3,944,500 12,841,500 6,066,600 6,679,200 63,432,526 28,014,100 137,860,426 - 64,938,834 25,540,216 52,708,015 17,395,309 18,377,191 188,233,083 292,497,878 659,690,525 (190,071,000) Subtotal: Unexpended at Year End - 340,734,862 - 469,619,525 4,787 1 231,185 119,034 8,192 115,073 249,756 17,286,489 18,014,517 16,617,500 16,617,500 182,075 16,617,500 16,799,575 6,920,000 1,200,000 900,000 9,020,000 140,901,202 239,841,900 154,660,001 199,091,000 - 250,000 5,000,000 8,350,200 2,000,000 3,000,000 3,000,000 4,069,850 141,905 - 250,000 1,000,000 25,000,000 8,350,100 2,000,000 3,000,000 3,000,000 301,758,330 301,758,330 73,182,077 73,182,077 258,171,787 266,595,297 260,512,863 260,512,863 Expenditures Community Facilities Drainage / Flood Control Preservation Public Safety Service Facilities Transportation Water Management Prior Year Unexpended Transfers Out G.O. Bonds Fund General Fund Grants Fund In Lieu Fees Fund MPC Bonds MPC Bonds - Water Reclamation Special Programs Fund Tourism Development Fund Transportation Sales Tax (0.20%) Fund Water & Water Reclamation Funds Subtotal Total Uses (a) Ending Fund Balance Aviation Funds Contingency CIP Stormwater Utility Bill Fee Contingency General Fund Contingency Grants Contingency Sewer Rates Contingency Transportation 0.2% Sales Tax Contingency Water Rates Contingency Reserved: Reserved Fund Balance Total Ending Fund Balance (a) Contingencies are unfunded and allow for the expenditure of unanticipated revenue that are not included in the beginning or ending fund balance. City Council approval is required before use of capital contingencies. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 19 - Table of Contents Capital Improvement Plan CAPITAL IMPROVEMENTFinancial PLANSummary | Five-Year Forecast & Five Financial Year Financial Forecast Adopted 2019/20 266,595,297 Forecast 2020/21 260,512,863 Forecast 2021/22 294,163,263 Forecast 2022/23 365,192,963 Forecast 2023/24 408,339,663 47,162,600 38,709,557 6,620,745 6,150,000 5,237,047 340,000 104,219,949 52,297,500 978,200 6,150,000 5,163,600 65,000 64,654,300 25,000,000 20,285,800 5,267,700 6,150,000 5,028,200 65,000 61,796,700 16,698,600 1,844,200 6,150,000 5,025,900 65,000 29,783,700 157,980,400 6,150,000 5,342,100 65,000 169,537,500 2,365,142 775,100 144,600 565,100 89,900 2,120,204 11,788,637 6,463 4,450,872 581,841 496,444 2,762,000 67,400 2,504,808 12,053,356 14,446,752 35,144,698 88,788,617 769,700 11,622,500 5,200 450,000 3,500 15,500 40,000 67,400 2,504,800 11,955,200 11,581,300 34,506,900 74,297,100 72,000 11,636,400 26,100 450,000 18,900 82,100 40,000 67,400 2,504,800 11,889,700 11,688,700 34,898,300 73,519,000 27,800 11,787,100 9,900 6,600 209,100 40,000 67,400 2,504,800 12,032,200 11,684,500 35,163,500 74,098,000 51,400 12,013,300 18,400 12,300 53,900 20,000 67,400 2,504,800 12,189,600 11,908,300 40,550,900 79,480,200 Total Sources 193,008,566 138,951,400 135,315,700 103,881,700 249,017,700 Total Fund Balance and Sources 459,603,863 399,464,263 429,478,963 469,074,663 657,357,363 Beginning Fund Balance (a) Revenues Bond Proceeds Charges for Service/Other Other Revenue Utilities & Enterprises Interest Earnings Building Permit Fees & Charges Subtotal Transfers In Aviation Fund Contributions Fleet Fund General Fund Grants Fund MPC Bonds Preservation Sales Tax Fund Risk Management Fund Solid Waste Fund Special Programs Fund Stadium Capital Improvement Fund Stormwater Fee Fund Tourism Development Fund Transportation Sales Tax (0.10%) Fund Transportation Sales Tax (0.20%) Fund Water & Water Reclamation Funds Subtotal (a) Prior year unexpended sources and uses of funds are estimated and included in the Beginning Fund Balance. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 20 - Table of Contents Capital Improvement Plan CAPITAL IMPROVEMENTFinancial PLANSummary | Five-Year Forecast & Five Financial Year Financial Forecast Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Subtotal Less: Estimated Capital Improvement Expenditures 64,938,834 25,540,216 52,708,015 17,395,309 18,377,191 188,233,083 292,497,878 659,690,525 (190,071,000) 3,824,373 680,000 4,904,626 3,847,650 41,328,268 28,207,900 469,619,525 552,412,342 (104,401,000) 7,095,380 450,000 3,025,354 9,059,579 19,713,869 28,371,200 448,011,342 515,726,724 (63,386,000) 2,177,416 450,000 1,377,047 10,134,950 31,845,300 32,524,200 452,340,724 530,849,637 (59,835,000) 1,582,179 30,975,811 1,440,347 6,944,920 175,346,875 33,570,200 471,014,637 720,874,969 (181,339,700) Subtotal: Unexpended at Year End 469,619,525 448,011,342 452,340,724 471,014,637 539,535,269 6,920,000 1,200,000 900,000 9,020,000 900,000 900,000 900,000 900,000 900,000 900,000 900,000 900,000 199,091,000 105,301,000 64,286,000 60,735,000 182,239,700 250,000 1,000,000 25,000,000 8,350,100 2,000,000 3,000,000 3,000,000 250,000 1,000,000 5,000,000 8,350,100 2,000,000 3,000,000 3,000,000 250,000 1,000,000 5,000,000 8,350,100 2,000,000 3,000,000 3,000,000 250,000 1,000,000 5,000,000 8,350,100 2,000,000 3,000,000 3,000,000 250,000 1,000,000 5,000,000 8,350,100 2,000,000 3,000,000 3,000,000 260,512,863 260,512,863 294,163,263 294,163,263 365,192,963 365,192,963 408,339,663 408,339,663 475,117,663 475,117,663 Expenditures Community Facilities Drainage / Flood Control Preservation Public Safety Service Facilities Transportation Water Management (a) Prior Year Unexpended Transfers Out G.O. Bonds Fund General Fund Grants Fund In Lieu Fees Fund MPC Bonds MPC Bonds - Water Reclamation Special Programs Fund Tourism Development Fund Transportation Sales Tax (0.20%) Fund Water & Water Reclamation Funds Subtotal Total Uses Ending Fund Balance(b) Aviation Funds Contingency CIP Stormwater Utility Bill Fee Contingency General Fund Contingency Grants Contingency Sewer Rates Contingency Transportation 0.2% Sales Tax Contingency Water Rates Contingency Reserved: Reserved Fund Balance Total Ending Fund Balance (a) Prior year unexpended uses are based on annual cashflow estimates. (b) Contingencies are unfunded and allow for the expenditure of unanticipated revenue that are not included in the beginning or ending fund balance. City Council approval is required before use of capital contingencies. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 21 - FY 2019/20 Adopted Budget City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 22 - Table of Contents 'ETMXEP-QTVSZIQIRX4PERF]4VSNIGX2EQI Capital Improvement Plan CAPITAL IMPROVEMENT PLAN - PROJECT LIST Alphabetical Financial Summary & Five Year|Financial Forecast -RXLSYWERHWSJHSPPEVW 8LI4VSNIGX0MWXsection includes three lists. These lists summarize all capital projects in 1) alphabetical order, 2) city division and  TVSKVEQ8LIPMWXWVIJPIGXIEGLTVSNIGX’s adopted FY 2019/20 budget with the forecasted funding through FY 2023/24. The JSVIGEWXIHJYRHMRK[LMGLMRGPYHIW*=XLVSYKL*=[EWRSXEHSTXIHF]XLI'MX]'SYRGMPEWTEVXSJXLI*= 2019/20 budget adoption. This information serves as part of the city’WPSRKXIVQGETMXEPTPERRMRKTVSGIWWERH[MPPFIVIZMWMXIH ERHYTHEXIHMRJYXYVIFYHKIXVIZMI[W*SPPS[MRKXLIXLVIITVSNIGXPMWXWMWXLI3TIVEXMRK-QTEGXWWIGXMSRXLEXMRGPYHIWEJSYV]IEV WYQQEV]SJXLITVSNIGXIHSTIVEXMRKGSWXWEWWSGMEXIH[MXLGETMXEPTVSNIGXW8LISTIVEXMRKMQTEGXWJSVTVSNIGXWGSQTPIXIHTVMSVXS SVHYVMRK*=EVIGEPGYPEXIHERHMRGPYHIHMRXLI%HSTXIH3TIVEXMRK&YHKIX2I\XEVITVSNIGXHIWGVMTXMSRW[LMGLMRGPYHI HIXEMPIHMRJSVQEXMSREVVERKIHF]QENSVTVSKVEQSRIEGLSJXLIGMX]’WGETMXEPTVSNIGXWMRGPYHMRK'SQQYRMX]*EGMPMXMIW Preservation, Drainage/Flood Control, Public Safety, Service Facilities, Transportation and Water Management. The detailed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ity of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 23 - Table of Contents 'ETMXEP-QTVSZIQIRX4PERF]4VSNIGX2EQI Capital Improvement Plan CAPITAL IMPROVEMENT PLAN - PROJECT LIST Alphabetical Financial Summary & Five Year|Financial Forecast -RXLSYWERHWSJHSPPEVW 4VSNIGX  &MOI[E]W4VSKVEQ =+ &SSWXIV7XEXMSR6ITPEGIQIRX ;) &SSWXIV7XEXMSR9TKVEHIW ;& &47()8VERWQMWWMSR'ETEGMX])\TERWMSR 8)14* 'EQTYW'IRXVEP%VM^SRE4VSNIGX(VEMREKI 4EZMRK -QTVSZIQIRXW ;EXIV  ;& 'EVIJVII,MKL[E]'EZI'VIIO6SEHXS7GSXXWHEPI6SEH 8)14 'IMPMRK-QTVSZIQIRXWEX%MVTSVX347&YMPHMRK %+ 'IRXVEP%VIE8VEMP'SRWXVYGXMSR (& 'LETEVVEP;EXIV8VIEXQIRX4PERX4VIXVIEXQIRX ;& '-4'SRXMRKIRG] >& '-4'SRXMRKIRG]JSV*YXYVI+VERXW >& 'MX]'SYVX'YWXSQIV7IVZMGI'SYRXIVWERH0SFF] 6IQSHIP &) 'MZMG'IRXIV0MFVEV]7GSXXWHEPI,IVMXEKI'SRRIGXMSR 4* 'MZMG'IRXIV0MFVEV]7XSV]8MQI6SSQ)\TERWMSR 4* 'PSWIH'MVGYMX8IPIZMWMSR ''8:  7IGYVMX]'EQIVE 7]WXIQ ERH%GGIWW'SRXVSP6ITPEGIQIRX .( 'PYWXIV%VWIRMG8VIEXQIRX ;+ 'SYVXLSYWI-QTVSZIQIRXW%VGLMXIGXYVEP7IVZMGIW &*  'VMQI0EFSVEXSV])UYMTQIRX6ITPEGIQIRX =+  'VMQI0EFSVEXSV])UYMTQIRX6ITPEGIQIRX =* 'VSWWVSEHW)EWX*PSSH'SRXVSP4LEWI- *& 'VSWWVSEHW)EWX7I[IV :* 'VSWWVSEHW)EWX;EXIV ;* (EXE'IRXIV6IWMPMIRG]4PER .( (IIT;IPP6IGLEVKI6IGSZIV]4VSNIGXW ;* (IPXE%TVSR-QTVSZIQIRXW4LEWI-- %+ (IWMKR'SRWXVYGX2SVXL+IRIVEP%ZMEXMSR&S\,ERKEVW %* (S[RXS[R)RXIVXEMRQIRX(MWXVMGX7XVIIX 4IHIWXVMER 0MKLXMRK () (S[RXS[R1EMR7XVIIX7XVIIXWGETI 4IHIWXVMER -QTVSZIQIRXW () (S[RXS[R7TPEWL4EH 4) (S[RXS[R7XSVQ[EXIV4YQT7XEXMSR6ILEFMPMXEXMSR :( %HSTXIH  *SVIGEWX  *SVIGEWX  *SVIGEWX  *SVIGEWX                                                                                                                                                                             6IGYVVMRK'ETMXEP1EMRXIRERGI4VSNIGXW City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 24 - 8SXEP 4EKI                                        Table of Contents 'ETMXEP-QTVSZIQIRX4PERF]4VSNIGX2EQI Capital Improvement Plan CAPITAL IMPROVEMENT PLAN - PROJECT LIST Alphabetical Financial Summary & Five Year|Financial Forecast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ity of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 25 -                               Table of Contents 'ETMXEP-QTVSZIQIRX4PERF]4VSNIGX2EQI Capital Improvement Plan CAPITAL IMPROVEMENT PLAN - PROJECT LIST Alphabetical Financial Summary & Five Year|Financial Forecast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ity of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 26 - *SVIGEWX  8SXEP 4EKI                Table of Contents 'ETMXEP-QTVSZIQIRX4PERF]4VSNIGX2EQI Capital Improvement Plan CAPITAL IMPROVEMENT PLAN - PROJECT LIST Alphabetical Financial Summary & Five Year|Financial Forecast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ity of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 27 -       Table of Contents 'ETMXEP-QTVSZIQIRX4PERF]4VSNIGX2EQI Capital Improvement Plan CAPITAL IMPROVEMENT PLAN - PROJECT LIST Alphabetical Financial Summary & Five Year|Financial Forecast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ity of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 28 - Five-Year Capital Improvement Plan FY 2018/19 - 2022/23 Sorted by Alphabetical (In thousands of dollars) Project Zone 8 Jomax Road Transmission Line (TEMP2098) Zone 8-D Jomax Road Transmission Line (TEMP2097) *Recurring Capital Maintenance Projects. FY2018/19 FY2019/20 FY2020/21 FY2021/22 FY2022/23 Adopted Forecast Forecast Forecast Forecast 725.0 - 927.0 - - - Total Page # 725.0 186 927.0 187 Table of Contents 'ETMXEP-QTVSZIQIRX4PERF]4VSNIGX2EQI Capital Improvement Plan CAPITAL IMPROVEMENT PLAN - PROJECT LIST Alphabetical Financial Summary & Five Year|Financial Forecast -RXLSYWERHWSJHSPPEVW 4VSNIGX 7SPMH;EWXI9TKVEHIWERH-QTVSZIQIRXW4VSKVEQ &+ 7SPMH;EWXI:ILMGPI1SRMXSVMRK7]WXIQ .& 7SYXL%VIE%GGIWW'SRXVSP 4& 7SYXL%VIE8VEMP'SRWXVYGXMSR 4& 763+6IKMSREP;EWXI[EXIV*EGMPMXMIW :* 7XEXI0ERH2IEV0IKIRH8VEMPW- ;* 7XEXI0ERH2IEV0IKIRH8VEMPW-- ;* 7XSVQ[EXIV*II'SRXMRKIRG] >+ 7XVIIX3TIVEXMSRW;SVOERH%WWIX1EREKIQIRX7]WXIQ .&  7XVIIXPMKLX6ITPEGIQIRX =8)14 8IGLRSPSK]1EWXIV4PER-HIRXMJMIH;EWXI[EXIV4VSNIGXW :) 8IGLRSPSK]1EWXIV4PER-HIRXMJMIH;EXIV4VSNIGXW ;) 8LSQEW+VSYRH[EXIV8VIEXQIRX*EGMPMX] ;' 8LSQEW6SEHXL7XVIIXXSVH7XVIIX 7+ 82)'1SRYQIRX7MKR (* 84'7XEHMYQ'SYVWI1MH[E]+VMPP-QTVSZIQIRXW 4+  8VEJJMG7MKREP'SRWXVYGXMSR =*  8VEJJMG7MKREP'SRWXVYGXMSR =+  8VEMP-QTVSZIQIRX4VSKVEQ =+ 8VERWMX6SYXI-QTVSZIQIRXW 8' 8VERWMX7XST-QTVSZIQIRXW 8' 8VERWTSVXEXMSR*YRH'SRXMRKIRG] >* 9XMPMX]&MPPMRK1EREKIQIRX7]WXIQ 8)14* ;EWXI[EXIV*YRH'SRXMRKIRG] >) ;EWXI[EXIV-QTEGX*IIW :' ;EWXI[EXIV7]WXIQ-QTVSZIQIRXW :* ;EWXI[EXIV7]WXIQ3ZIVWM^MRK :* ;EWXI[EXIV8IGLRSPSK]1EWXIV4PER :& ;EWXI[EXIV8VIEXQIRX*EGMPMX]-QTVSZIQIRXW :( ;EXIVERH7I[IV7]WXIQ3TXMQM^EXMSR ;& ;EXIV'EQTYW:EHSWI;IPP'SRWXVYGXMSR 8)14* ;EXIV'EQTYW:EHSWI;IPP6ILEFMPMXEXMSR ;& ;EXIV(MWXVMFYXMSR7]WXIQ-QTVSZIQIRXW ;& ;EXIV*YRH'SRXMRKIRG] >) ;EXIV-QTEGX*IIW ;' %HSTXIH  *SVIGEWX  *SVIGEWX  *SVIGEWX  *SVIGEWX  8SXEP 4EKI                                                                                                                                                                                                                                 6IGYVVMRK'ETMXEP1EMRXIRERGI4VSNIGXW City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 29 -                      Table of Contents 'ETMXEP-QTVSZIQIRX4PERF]4VSNIGX2EQI Capital Improvement Plan CAPITAL IMPROVEMENT PLAN - PROJECT LIST Alphabetical Financial Summary & Five Year|Financial Forecast -RXLSYWERHWSJHSPPEVW 4VSNIGX ;EXIV1IXIV6ITPEGIQIRX4VSKVEQ ;& ;EXIV4EVXMGMTEXMSR4VSKVEQ ;& ;EXIV5YEPMX]0EF)UYMTQIRX6ITPEGIQIRX ;+ ;EXIV6IGPEQEXMSR4EVXMGMTEXMSR4VSKVEQ :& ;EXIV6IGPEQEXMSR7IGYVMX])RLERGIQIRXW :& ;EXIV6IWSYVGIW-QTEGX*IIW ;' ;EXIV7]WXIQ3ZIVWM^MRK ;* ;EXIV7]WXIQ7IGYVMX])RLERGIQIRX4VSNIGXW ;) ;EXIV8IGLRSPSK]1EWXIV4PER ;& ;EXIV8VIEXQIRX*EGMPMX]-QTVSZIQIRXW ;( ;EXIV8VIEXQIRX4PERX1IQFVERIW ;& ;IPP7MXI-R'VSWWVSEHW)EWX2SVXLSJXLI%VM^SRE 7XEXI6SYXI ;* ;IPP7MXIW ;& ;IPP7MXIW6ILEFMPMXEXMSR ;& ;IWX;SVPH-QTVSZIQIRXW ;& ;IWX;SVPH0SX,)PIGXVMGEP-QTVSZIQIRXW () ;IWX;SVPH4YVGLEWISJ4SVXEFPI6:4IHIWXEPW () ;IWX;SVPH8IRX6IQSZEP (( ;IWX;SVPH8VEMP'SRRIGXMSRW 8' ;MPHPMJI,E^EVH1EREKIQIRX4PER 8)14* >SRI;EXIV7]WXIQ-QTVSZIQIRXW4LEWI ;* >SRI;EXIV7]WXIQ-QTVSZIQIRXW ;' >SRI;;EXIV7]WXIQ-QTVSZIQIRXW ;( >SRI.SQE\6SEH8VERWQMWWMSR0MRI ;+ >SRI(.SQE\6SEH8VERWQMWWMSR0MRI ;+ %HSTXIH  *SVIGEWX  *SVIGEWX  *SVIGEWX  *SVIGEWX                                                                                                                                                                                 6IGYVVMRK'ETMXEP1EMRXIRERGI4VSNIGXW City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 30 - 8SXEP 4EKI Table of Contents 'ETMXEP-QTVSZIQIRX4PERF](MZMWMSR Capital Improvement Plan CAPITAL IMPROVEMENT PLAN PROJECT | by Division Financial- Summary & FiveLIST Year Financial Forecast -RXLSYWERHWSJHSPPEVW 4VSNIGX %HQMRMWXVEXMZI7IVZMGIW (EXE'IRXIV6IWMPMIRG]4PER .(  -82IX[SVO-RJVEWXVYGXYVI =+  -82IX[SVO-RJVEWXVYGXYVI =*  -87IVZIV-RJVEWXVYGXYVI =*  -87IVZIV-RJVEWXVYGXYVI =+ ' )(%MVTSVX %MVTSVX*YXYVI+VERXW'SRXMRKIRG] >& %MVTSVX1EWXIV4PER9THEXI 8)14 %MVTSVX1SRYQIRX7MKR %+ %MVTSVX4EZIQIRX4VIWIVZEXMSR4VSKVEQ %& %MVTSVX7IGYVMX]*IRGMRK-QTVSZIQIRXW %+ %MVTSVX8IVQMREP%VIE6IHIZIPSTQIRX4VSNIGX %& %TVSR6IGSRWXVYGXMSR(IPXE%TVSR %' %ZMEXMSR1EXGL'SRXMRKIRG] >& 'IMPMRK-QTVSZIQIRXWEX%MVTSVX347&YMPHMRK %+ (IPXE%TVSR-QTVSZIQIRXW4LEWI-- %+ (IWMKR'SRWXVYGX2SVXL+IRIVEP%ZMEXMSR&S\,ERKEVW %* )RZMVSRQIRXEP%WWIWWQIRXJSV0ERH%GUYMWMXMSR 8)14%&* )\MX8E\M[E]W&&ERH& 8)14* /MPS6EQT6ILEFMPMXEXMSR %+ 0ERH%GUYMWMXMSR%GVIW 8)14* 4IVMQIXIV7IVZMGI6SEH6ILEFMPMXEXMSR %+ 6IGSRWXVYGX8E\M[E]%ERH)\MXW %& 6ILEFMPMXEXI6YR[E] %& 6ILEFMPMXEXI8E\M[E]' %+ 6YR[E]6ILEFMPMXEXMSR6IGSRWXVYGXMSR 'SRWXVYGXMSR 8)14 6YR[E]6ILEFMPMXEXMSR6IGSRWXVYGXMSR(IWMKR %+ 6YR[E]+YEVH0MKLXW %) ;MPHPMJI,E^EVH1EREKIQIRX4PER 8)14* ' )()GSRSQMG(IZIPSTQIRX )\TERWMSRSJ)\MWXMRK4EVOMRK+EVEKIW (* ' )(4PERRMRK (IZIPSTQIRX 'VSWWVSEHW)EWX*PSSH'SRXVSP4LEWI- *& +VERMXI6IIJ;EXIVWLIH *& %HSTXIH  *SVIGEWX  *SVIGEWX  *SVIGEWX  *SVIGEWX  8SXEP 4EKI                                                                                                                                                                                                                          6IGYVVMRK'ETMXEP1EMRXIRERGI4VSNIGXW City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 31 - Table of Contents 'ETMXEP-QTVSZIQIRX4PERF](MZMWMSR Capital Improvement Plan CAPITAL IMPROVEMENT PLAN PROJECT | by Division Financial- Summary & FiveLIST Year Financial Forecast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ity of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 32 - 8SXEP 4EKI               Table of Contents 'ETMXEP-QTVSZIQIRX4PERF](MZMWMSR Capital Improvement Plan CAPITAL IMPROVEMENT PLAN PROJECT | by Division Financial- Summary & FiveLIST Year Financial Forecast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ity of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 33 -                    Table of Contents 'ETMXEP-QTVSZIQIRX4PERF](MZMWMSR Capital Improvement Plan CAPITAL IMPROVEMENT PLAN PROJECT | by Division Financial- Summary & FiveLIST Year Financial Forecast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ity of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 34 -                   Table of Contents 'ETMXEP-QTVSZIQIRX4PERF](MZMWMSR Capital Improvement Plan CAPITAL IMPROVEMENT PLAN PROJECT | by Division Financial- Summary & FiveLIST Year Financial Forecast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ity of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 35 -                     Table of Contents 'ETMXEP-QTVSZIQIRX4PERF](MZMWMSR Capital Improvement Plan CAPITAL IMPROVEMENT PLAN PROJECT | by Division Financial- Summary & FiveLIST Year Financial Forecast -RXLSYWERHWSJHSPPEVW %HSTXIH  4VSNIGX 4YFPMG;SVOW 4MQE6SEH:MEHI:IRXYVEXS:ME0MRHE 7&  6EMRXVII(VMZIEX%VM^SRE7XEXI6SYXI8VEJJMG  -RXIVGLERKI 7+ 6EMRXVII(VMZI,E]HIR6SEHXS%VM^SRE7XEXI6SYXI  7' 6EMRXVII(VMZI7GSXXWHEPI6SEHXS,E]HIR6SEH 7&  6IHJMIPH6SEH6EMRXVII(VMZIXS,E]HIR6SEH 7&   6SEH[E]'ETEGMX] 7EJIX]-QTVSZIQIRXW =+  7GSXXWHEPI6SEH(M\MPIXE(VMZIXS'EVIJVII,MKL[E]  8)14 7GSXXWHEPI6SEH.SQE\6SEHXS(M\MPIXE(VMZI  8)14 7GSXXWHEPI6SEH4MRREGPI4IEO4EVO[E]XS.SQE\6SEH  8)14* 7GSXXWHEPI6SEH8LSQTWSR4IEO4EVO[E]XS4MRREGPI  4IEO6SEH4LEWI-- 8)14* 7LIE&SYPIZEVH-RXIVWIGXMSRW%VM^SRE7XEXI6SYXIXS  XL7XVIIX 8)14 7LIE9RHIVTEWW%GGIWWEXXL7XVIIX 8&   7MHI[EPO-QTVSZIQIRXW =+  7O]7SRK%797GSXXWHEPI'IRXIVJSV-RRSZEXMSR%VX  'SQTSRIRX (' 7SPMH;EWXI9TKVEHIWERH-QTVSZIQIRXW4VSKVEQ  &+ 7SPMH;EWXI:ILMGPI1SRMXSVMRK7]WXIQ .&  7XVIIX3TIVEXMSRW;SVOERH%WWIX1EREKIQIRX7]WXIQ  .&  7XVIIXPMKLX6ITPEGIQIRX =8)14  8LSQEW6SEHXL7XVIIXXSVH7XVIIX 7+   8VEJJMG7MKREP'SRWXVYGXMSR =*   8VEJJMG7MKREP'SRWXVYGXMSR =+   8VEMP-QTVSZIQIRX4VSKVEQ =+  8VERWMX6SYXI-QTVSZIQIRXW 8'  8VERWMX7XST-QTVSZIQIRXW 8'  ;IWX;SVPH8VEMP'SRRIGXMSRW 8'  ;EXIV6IWSYVGIW %HZERGI;EXIV8VIEXQIRX4PERX1IQFVERIW  ;EWXI[EXIV :& %HZERGI;EXIV8VIEXQIRX4PERX1IQFVERIW  6ITPEGIQIRX ;* *SVIGEWX  *SVIGEWX  *SVIGEWX  *SVIGEWX  8SXEP 4EKI                                                                                                                                                                   6IGYVVMRK'ETMXEP1EMRXIRERGI4VSNIGXW City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 36 - Table of Contents 'ETMXEP-QTVSZIQIRX4PERF](MZMWMSR Capital Improvement Plan CAPITAL IMPROVEMENT PLAN PROJECT | by Division Financial- Summary & FiveLIST Year Financial Forecast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ity of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 37 - 8SXEP 4EKI                                        Table of Contents 'ETMXEP-QTVSZIQIRX4PERF](MZMWMSR Capital Improvement Plan CAPITAL IMPROVEMENT PLAN PROJECT | by Division Financial- Summary & FiveLIST Year Financial Forecast -RXLSYWERHWSJHSPPEVW 4VSNIGX ;EXIV6IWSYVGIW 7XEXI0ERH2IEV0IKIRH8VEMPW-- ;* 8IGLRSPSK]1EWXIV4PER-HIRXMJMIH;EWXI[EXIV4VSNIGXW :) 8IGLRSPSK]1EWXIV4PER-HIRXMJMIH;EXIV4VSNIGXW ;) 8LSQEW+VSYRH[EXIV8VIEXQIRX*EGMPMX] ;' ;EWXI[EXIV*YRH'SRXMRKIRG] >) ;EWXI[EXIV-QTEGX*IIW :' ;EWXI[EXIV7]WXIQ-QTVSZIQIRXW :* ;EWXI[EXIV7]WXIQ3ZIVWM^MRK :* ;EWXI[EXIV8IGLRSPSK]1EWXIV4PER :& ;EWXI[EXIV8VIEXQIRX*EGMPMX]-QTVSZIQIRXW :( ;EXIVERH7I[IV7]WXIQ3TXMQM^EXMSR ;& ;EXIV'EQTYW:EHSWI;IPP'SRWXVYGXMSR 8)14* ;EXIV'EQTYW:EHSWI;IPP6ILEFMPMXEXMSR ;& ;EXIV(MWXVMFYXMSR7]WXIQ-QTVSZIQIRXW ;& ;EXIV*YRH'SRXMRKIRG] >) ;EXIV-QTEGX*IIW ;' ;EXIV1IXIV6ITPEGIQIRX4VSKVEQ ;& ;EXIV4EVXMGMTEXMSR4VSKVEQ ;& ;EXIV5YEPMX]0EF)UYMTQIRX6ITPEGIQIRX ;+ ;EXIV6IGPEQEXMSR4EVXMGMTEXMSR4VSKVEQ :& ;EXIV6IGPEQEXMSR7IGYVMX])RLERGIQIRXW :& ;EXIV6IWSYVGIW-QTEGX*IIW ;' ;EXIV7]WXIQ3ZIVWM^MRK ;* ;EXIV7]WXIQ7IGYVMX])RLERGIQIRX4VSNIGXW ;) ;EXIV8IGLRSPSK]1EWXIV4PER ;& ;EXIV8VIEXQIRX*EGMPMX]-QTVSZIQIRXW ;( ;EXIV8VIEXQIRX4PERX1IQFVERIW ;& ;IPP7MXI-R'VSWWVSEHW)EWX2SVXLSJXLI%VM^SRE 7XEXI6SYXI ;* ;IPP7MXIW ;& ;IPP7MXIW6ILEFMPMXEXMSR ;& ;IWX;SVPH-QTVSZIQIRXW ;& >SRI;EXIV7]WXIQ-QTVSZIQIRXW4LEWI ;* >SRI;EXIV7]WXIQ-QTVSZIQIRXW ;' >SRI;;EXIV7]WXIQ-QTVSZIQIRXW ;( >SRI.SQE\6SEH8VERWQMWWMSR0MRI ;+ %HSTXIH  *SVIGEWX  *SVIGEWX  *SVIGEWX  *SVIGEWX  8SXEP 4EKI                                                                                                                                                                                                                                                      6IGYVVMRK'ETMXEP1EMRXIRERGI4VSNIGXW City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 38 - Table of Contents 'ETMXEP-QTVSZIQIRX4PERF](MZMWMSR Capital Improvement Plan CAPITAL IMPROVEMENT PLAN PROJECT | by Division Financial- Summary & FiveLIST Year Financial Forecast -RXLSYWERHWSJHSPPEVW 4VSNIGX ;EXIV6IWSYVGIW >SRI(.SQE\6SEH8VERWQMWWMSR0MRI ;+ %HSTXIH  *SVIGEWX  *SVIGEWX  *SVIGEWX  *SVIGEWX  8SXEP 4EKI        6IGYVVMRK'ETMXEP1EMRXIRERGI4VSNIGXW City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 39 - Table of Contents 'ETMXEP-QTVSZIQIRX4PERF]4VSKVEQ Capital Improvement Plan CAPITAL IMPROVEMENT PLAN PROJECT LIST | by Program Financial- Summary & Five Year Financial Forecast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ity of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 40 -                    Table of Contents 'ETMXEP-QTVSZIQIRX4PERF]4VSKVEQ Capital Improvement Plan CAPITAL IMPROVEMENT PLAN PROJECT LIST | by Program Financial- Summary & Five Year Financial Forecast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ity of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 41 - *SVIGEWX  8SXEP 4EKI                Table of Contents 'ETMXEP-QTVSZIQIRX4PERF]4VSKVEQ Capital Improvement Plan CAPITAL IMPROVEMENT PLAN PROJECT LIST | by Program Financial- Summary & Five Year Financial Forecast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ity of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 42 -                                                       Table of Contents 'ETMXEP-QTVSZIQIRX4PERF]4VSKVEQ Capital Improvement Plan CAPITAL IMPROVEMENT PLAN PROJECT LIST | by Program Financial- Summary & Five Year Financial Forecast -RXLSYWERHWSJHSPPEVW %HSTXIH  4VSNIGX *SVIGEWX  7IVZMGI*EGMPMXMIW8IGLRSPSK]-QTVSZIQIRXW 7XVIIX3TIVEXMSRW;SVOERH%WWIX1EREKIQIRX7]WXIQ   .& 9XMPMX]&MPPMRK1EREKIQIRX7]WXIQ 8)14*   8VERWTSVXEXMSR%ZMEXMSR%ZMEXMSR-QTVSZIQIRXW %MVTSVX*YXYVI+VERXW'SRXMRKIRG] >&   %MVTSVX1EWXIV4PER9THEXI 8)14   %MVTSVX1SRYQIRX7MKR %+   %MVTSVX4EZIQIRX4VIWIVZEXMSR4VSKVEQ %&   %MVTSVX7IGYVMX]*IRGMRK-QTVSZIQIRXW %+   %MVTSVX8IVQMREP%VIE6IHIZIPSTQIRX4VSNIGX %&   %TVSR6IGSRWXVYGXMSR(IPXE%TVSR %'   %ZMEXMSR1EXGL'SRXMRKIRG] >&   'IMPMRK-QTVSZIQIRXWEX%MVTSVX347&YMPHMRK %+   (IPXE%TVSR-QTVSZIQIRXW4LEWI-- %+   (IWMKR'SRWXVYGX2SVXL+IRIVEP%ZMEXMSR&S\,ERKEVW   %* )RZMVSRQIRXEP%WWIWWQIRXJSV0ERH%GUYMWMXMSR   8)14%&* )\MX8E\M[E]W&&ERH& 8)14*   /MPS6EQT6ILEFMPMXEXMSR %+   0ERH%GUYMWMXMSR%GVIW 8)14*   4IVMQIXIV7IVZMGI6SEH6ILEFMPMXEXMSR %+   6IGSRWXVYGX8E\M[E]%ERH)\MXW %&   6ILEFMPMXEXI6YR[E] %&   6ILEFMPMXEXI8E\M[E]' %+   6YR[E]6ILEFMPMXEXMSR6IGSRWXVYGXMSR   'SRWXVYGXMSR 8)14 6YR[E]6ILEFMPMXEXMSR6IGSRWXVYGXMSR(IWMKR   %+ 6YR[E]+YEVH0MKLXW %)   ;MPHPMJI,E^EVH1EREKIQIRX4PER 8)14*   8VERWTSVXEXMSR7XVIIXW7XVIIX-QTVSZIQIRXW XL7XVIIX-RHMER7GLSSP6SEHXS8LSQEW6SEH 7+   %(%8VERWMXMSR4PER-QTPIQIRXEXMSR 7*   'EVIJVII,MKL[E]'EZI'VIIO6SEHXS7GSXXWHEPI6SEH   8)14 *VERO0PS]H;VMKLX&SYPIZEVHEX%VM^SRE7XEXI6SYXI   8VEJJMG-RXIVGLERKI 8)14 ,ETT]:EPPI]6H4MQE6HXS%PQE7GLSSP6H 7)   *SVIGEWX  *SVIGEWX  *SVIGEWX  8SXEP 4EKI                                                                                                                                                 6IGYVVMRK'ETMXEP1EMRXIRERGI4VSNIGXW City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 43 -       Table of Contents 'ETMXEP-QTVSZIQIRX4PERF]4VSKVEQ Capital Improvement Plan CAPITAL IMPROVEMENT PLAN PROJECT LIST | by Program Financial- Summary & Five Year Financial Forecast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ity of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 44 -                             Table of Contents 'ETMXEP-QTVSZIQIRX4PERF]4VSKVEQ Capital Improvement Plan CAPITAL IMPROVEMENT PLAN PROJECT LIST | by Program Financial- Summary & Five Year Financial Forecast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ity of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 45 - Table of Contents 'ETMXEP-QTVSZIQIRX4PERF]4VSKVEQ Capital Improvement Plan CAPITAL IMPROVEMENT PLAN PROJECT LIST | by Program Financial- Summary & Five Year Financial Forecast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ity of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 46 -                                    Table of Contents 'ETMXEP-QTVSZIQIRX4PERF]4VSKVEQ Capital Improvement Plan CAPITAL IMPROVEMENT PLAN PROJECT LIST | by Program Financial- Summary & Five Year Financial Forecast -RXLSYWERHWSJHSPPEVW %HSTXIH  4VSNIGX ;EXIV1EREKIQIRX;EXIV-QTVSZIQIRXW -VVMKEXMSR;EXIV(MWXVMFYXMSR7]WXIQ-QTVSZIQIRXW  ;& -;(7,EVUYELEPE:EPPI]-VVMKEXMSR(MWXVMGX4VSTIVX]  (IWIVX1SYRXEMR+SPJ'PYF ;& -;(7,EVUYELEPE:EPPI]-VVMKEXMSR(MWXVMGX4VSTIVX]  7GSXXWHEPI2EXMSREP+SPJ'PYF ;& 1EWXIV4PER;EXIV ;&  6EHMS8IPIQIXV]1SRMXSVMRK%YXSQEXMSR'MX][MHI;EXIV  ;& 6IKMSREP6IGLEVKI&EWMRW ;&  6MS:IVHIXL7XVIIX8VERWQMWWMSR1EMRW ;+  7MXI6IWIVZSMV7XSVEKI)\TERWMSR ;*  7XEXI0ERH2IEV0IKIRH8VEMPW- ;*  7XEXI0ERH2IEV0IKIRH8VEMPW-- ;*  8IGLRSPSK]1EWXIV4PER-HIRXMJMIH;EXIV4VSNIGXW  ;) 8LSQEW+VSYRH[EXIV8VIEXQIRX*EGMPMX] ;'  ;EXIVERH7I[IV7]WXIQ3TXMQM^EXMSR ;&  ;EXIV'EQTYW:EHSWI;IPP'SRWXVYGXMSR 8)14*  ;EXIV'EQTYW:EHSWI;IPP6ILEFMPMXEXMSR ;&  ;EXIV(MWXVMFYXMSR7]WXIQ-QTVSZIQIRXW ;&  ;EXIV*YRH'SRXMRKIRG] >)  ;EXIV-QTEGX*IIW ;'  ;EXIV1IXIV6ITPEGIQIRX4VSKVEQ ;&  ;EXIV4EVXMGMTEXMSR4VSKVEQ ;&  ;EXIV5YEPMX]0EF)UYMTQIRX6ITPEGIQIRX ;+  ;EXIV6IWSYVGIW-QTEGX*IIW ;'  ;EXIV7]WXIQ3ZIVWM^MRK ;*  ;EXIV7]WXIQ7IGYVMX])RLERGIQIRX4VSNIGXW ;)  ;EXIV8IGLRSPSK]1EWXIV4PER ;&  ;EXIV8VIEXQIRX*EGMPMX]-QTVSZIQIRXW ;(  ;EXIV8VIEXQIRX4PERX1IQFVERIW ;&  ;IPP7MXI-R'VSWWVSEHW)EWX2SVXLSJXLI%VM^SRE  7XEXI6SYXI ;* ;IPP7MXIW ;&  ;IPP7MXIW6ILEFMPMXEXMSR ;&  ;IWX;SVPH-QTVSZIQIRXW ;&  >SRI;EXIV7]WXIQ-QTVSZIQIRXW4LEWI  ;* *SVIGEWX  *SVIGEWX  *SVIGEWX  *SVIGEWX  8SXEP 4EKI                                                                                                                                                                                                 6IGYVVMRK'ETMXEP1EMRXIRERGI4VSNIGXW City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 47 - Table of Contents 'ETMXEP-QTVSZIQIRX4PERF]4VSKVEQ Capital Improvement Plan CAPITAL IMPROVEMENT PLAN PROJECT LIST | by Program Financial- Summary & Five Year Financial Forecast -RXLSYWERHWSJHSPPEVW 4VSNIGX ;EXIV1EREKIQIRX;EXIV-QTVSZIQIRXW >SRI;EXIV7]WXIQ-QTVSZIQIRXW ;' >SRI;;EXIV7]WXIQ-QTVSZIQIRXW ;( >SRI.SQE\6SEH8VERWQMWWMSR0MRI ;+ >SRI(.SQE\6SEH8VERWQMWWMSR0MRI ;+ %HSTXIH  *SVIGEWX  *SVIGEWX  *SVIGEWX  *SVIGEWX  8SXEP 4EKI                             6IGYVVMRK'ETMXEP1EMRXIRERGI4VSNIGXW City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 48 - Table of Contents Capital Improvement Plan CAPITAL IMPROVEMENT PLAN | CIP Operating Impacts Financial Summary & Five Year Financial Forecast Overview CIP Operating Impacts The Operating and CIP budgets are presented in three separate publications. The operating budget is presented in Volumes One and Two, and the CIP budget is in Volume Three. Even though the Operating and CIP budgets are displayed separately, both are connected by the CIP Operating Impacts. CIP Operating Impacts During the CIP budget development process staff provides annual estimates of additional costs and possible cost reductions that will impact the Operating budget. The extensive CIP prioritization process includes a review of CIP projects by the Operating Impacts Review Team represented by individuals from Facilities Management, Street Operations, Fleet Management, Parks Management and Information Technology. The team’s objective is to determine when operating impacts will result and to quantify the value of the impact. Examples of additional costs include positions, facilities maintenance, utilities, asphalt maintenance, street sweeping, landscape maintenance and annual software licensing. Estimated new revenues and/or operational expenditure savings associated with capital projects are also taken into consideration during this review. The Operating Impacts Review Team provides their results to the City Treasurer’s Office so these may be incorporated in the Operating Budget five-year financial forecast, and to ensure funding will be available to cover the costs once the CIP projects are completed. Extra costs are absorbed by the division’s operating budget whenever possible. As part of the annual Operating Budget development process, the operating impacts of capital projects are identified, forecasted, prioritized and justified. The operating impacts relating to projects scheduled for completion in FY 2019/20 have been included in the appropriate divisional operating budget. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 49 - Table of Contents *SVIGEWXIH3TIVEXMRK-QTEGXW *=  MRXLSYWERHW *SVIGEWXIH3TIVEXMRK-QTEGXW *=  MRXLSYWERHW Rounding differences may occur City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 50 - Table of Contents Capital Improvement Plan 'ETMXEP-QTVSZIQIRX4PER3TIVEXMRK-QTEGXW CAPITAL IMPROVEMENT Impacts FinancialPLAN Summary|&CIP FiveOperating Year Financial Forecast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ity of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 51 - Table of Contents Capital Improvement Plan 'ETMXEP-QTVSZIQIRX4PER3TIVEXMRK-QTEGXW CAPITAL IMPROVEMENT Impacts FinancialPLAN Summary|&CIP FiveOperating Year Financial Forecast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ity of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 52 - Table of Contents Capital Improvement Plan 'ETMXEP-QTVSZIQIRX4PER3TIVEXMRK-QTEGXW CAPITAL IMPROVEMENT Impacts FinancialPLAN Summary|&CIP FiveOperating Year Financial Forecast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ity of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 53 - Table of Contents Capital Improvement Plan 'ETMXEP-QTVSZIQIRX4PER3TIVEXMRK-QTEGXW CAPITAL IMPROVEMENT Impacts FinancialPLAN Summary|&CIP FiveOperating Year Financial Forecast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ity of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 54 - Table of Contents Capital Improvement Plan 'ETMXEP-QTVSZIQIRX4PER3TIVEXMRK-QTEGXW CAPITAL IMPROVEMENT Impacts FinancialPLAN Summary|&CIP FiveOperating Year Financial Forecast -RXLSYWERHWSJHSPPEVW 4VSNIGX ;IWX;SVPH8VEMP'SRRIGXMSRW 8' 'SRXVEGXYEP7IVZMGIWGSWXWVIPEXIHXSXLIQEMRXIRERGISJE RI[TEXLW]WXIQ Total Forecasted Operating Impacts *SVIGEWX  *SVIGEWX  *SVIGEWX  *SVIGEWX  8SXEP 4EKI       900.2 2,098.6 2,430.1 2,754.2 8,183.1 2SXIW3TIVEXMRKMQTEGXWVIPEXMRKXSTVSNIGXWWGLIHYPIHJSVGSQTPIXMSRMR*=LEZIFIIRMRGPYHIHMRXLIETTVSTVMEXI HMZMWMSREPSTIVEXMRKFYHKIX City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 55 - FY 2019/20 Adopted Budget City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 56 - Table of Contents 4VSNIGX(IWGVMTXMSRW COMMUNITY FACILITIES -RXLSYWERHWSJHSPPEVW 'SQQYRMX]*EGMPMXMIW 'SQQYRMX]*EGMPMXMIWTVSKVEQWJSGYWSRIRLERGMRKERHTVSXIGXMRKEHMZIVWIJEQMP]SVMIRXIHGSQQYRMX][LIVIRIMKLFSVLSSHW EVIWEJIERH[IPPQEMRXEMRIH8LIWIVIGVIEXMSREPRIIHWEVIQIXF]TVSZMHMRKVIGVIEXMSRJEGMPMXMIWTEVOWTEVOMQTVSZIQIRXW QYPXMYWITEXLWRIMKLFSVLSSHIRLERGIQIRXW]SYXLWTSVXWPMKLXMRKEUYEXMGGIRXIVWPMFVEV]JEGMPMXMIWERHWIRMSVGIRXIVW %TTVS\MQEXIP]TIVGIRX QMPPMSR SJXLI'-4LEWFIIRMHIRXMJMIHXSEHHVIWWXLIRIIHWSJXLMWTVSKVEQ 4VSNIGX 'SQQYRMX]*EGMPMXMIW 0MFVEV]0MFVEV]-QTVSZIQIRXW 'MZMG'IRXIV0MFVEV]7GSXXWHEPI,IVMXEKI'SRRIGXMSR 4* 'MZMG'IRXIV0MFVEV]7XSV]8MQI6SSQ)\TERWMSR 4* 2IMKLFSVLSSH 'SQQYRMX] %UYEXMGW'LIQMGEP7]WXIQ6ITPEGIQIRX 4( %VXWMR4YFPMG4PEGIW () (S[RXS[R)RXIVXEMRQIRX(MWXVMGX7XVIIX 4IHIWXVMER 0MKLXMRK () (S[RXS[R7TPEWL4EH 4) +EXI[E]1SRYQIRX1EVOIV4YFPMG%VX4VSNIGX (+ +VIIR[E],E]HIR*VERO0PS]H;VMKLX4YFPMG%VX (+ 4EMYXI2IMKLFSVLSSH'IRXIV%(%&EXLVSSQ 6IRSZEXMSRW 4) 7GSXXWHEPI6SEH4VIWIVZEXMSR7XVIIXWGETI )RLERGIQIRX (& 7O]7SRK%797GSXXWHEPI'IRXIVJSV-RRSZEXMSR%VX 'SQTSRIRX (' 82)'1SRYQIRX7MKR (* 84'7XEHMYQ'SYVWI1MH[E]+VMPP-QTVSZIQIRXW 4+ ;IWX;SVPH0SX,)PIGXVMGEP-QTVSZIQIRXW () ;IWX;SVPH4YVGLEWISJ4SVXEFPI6:4IHIWXEPW () ;IWX;SVPH8IRX6IQSZEP (( 4EVOW4EVO-QTVSZIQIRXW %UYEXMGW0MJIG]GPI6ITPEGIQIRX 4+ 1G'SVQMGO7XMPPQER664EVO-QTVSZIQIRXW4LEWI- 4+ 1G(S[IPP6SEH&IVQ0ERHWGETMRK () 4EVO%QIRMXMIW 4+ 4EVO6IWXVSSQW 4+ 4PE]KVSYRH6ILEFMPMXEXMSR 4+ 6IGYVVMRK'ETMXEP1EMRXIRERGI4VSNIGXW %HSTXIH  *SVIGEWX  *SVIGEWX  *SVIGEWX  *SVIGEWX  8SXEP 4EKI                                                                                                                                                   City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 57 -         Table of Contents 4VSNIGX(IWGVMTXMSRW COMMUNITY FACILITIES -RXLSYWERHWSJHSPPEVW 4VSNIGX 'SQQYRMX]*EGMPMXMIW 4EVOW4EVO-QTVSZIQIRXW 6IRSZEXI-RHMER&IRH;EWL%VIE:MWXEHIP'EQMRS 4EVO 4( 7GSXXWHEPI7XEHMYQ-RJVEWXVYGXYVI-QTVSZIQIRXW 4& 7GSXXWHEPI7XEHMYQ6IRSZEXMSRW 4) 7GSXXWHEPI7XEHMYQ7EJIX]6ITEMVW 1EMRXIRERGI 4( 6IGYVVMRK'ETMXEP1EMRXIRERGI4VSNIGXW %HSTXIH  *SVIGEWX  *SVIGEWX  *SVIGEWX  *SVIGEWX  8SXEP 4EKI                           City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 58 -   Table of Contents COMMUNITY FACILITIES | Library/Library Improvements Library/Library Improvements Civic Center Library - Scottsdale Heritage Connection - (PF03) Est. Completion: 12/19 Location: Civic Center Library Project Type: Construction Related Description: Provide physical and digital space for the Scottsdale Heritage Connection (SHC) who collect, organize and make accessible materials relating to Scottsdale's past, present and future. The materials focus on culture, geography, people, government and history. The collection informs, educates and entertains through physical and virtual resources, public programs and community partnerships. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Contingency Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) General Fund Contributions Total: 19.7 329.4 41.0 39.0 9.9 439.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 337.8 101.2 439.0 (310.8) (90.6) (401.3) 27.0 10.6 37.7 - - - - 27.0 10.6 37.7  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 59 - Table of Contents COMMUNITY FACILITIES | Library/Library Improvements Library/Library Improvements Civic Center Library - Story Time Room Expansion - (PF02) Est. Completion: 06/20 Civic Center Library Location: Project Type: Construction Related Description: Expand and revitalize the Civic Center Library story time room to house library programs. The area will be able to accommodate large programs with active participants. The expansion will allow for active parent and children participation in the morning early learning programs. The added space will also be adaptable for activities during the after-school hours such as those for Science, Technology, Engineering, Art and Math (STEAM) that have the goal of developing foundational math, science and literacy skills. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Contingency Design/Construction Admin Machinery and Equipment Salaries Total: Funding Sources (In thousands of dollars) General Fund Contributions Grants Library Gifts Memorial Fund Total: 19.7 167.7 41.0 41.8 25.0 9.8 305.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 153.6 51.1 32.8 67.5 305.0 (2.8) (2.8) 150.8 51.1 32.8 67.5 302.1 - - - - 150.8 51.1 32.8 67.5 302.1  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 60 - Table of Contents COMMUNITY FACILITIES | Neighborhood & Community Neighborhood & Community Aquatics Chemical System Replacement - (PD01) Est. Completion: 06/20 Aquatic centers citywide (Eldorado, Chaparral, Cactus and McDowell Mountain Ranch) Location: Project Type: Construction Related Description: Bring the city's aquatic operations into compliance with federal Homeland Security guidelines by replacing the existing chemical treatment systems in all city pools with an on-site chlorine generation system. Funding Sources (In thousands of dollars) General Fund Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 4,433.1 4,433.1 (2,319.9) (2,319.9) 2,113.2 2,113.2 - - - - 2,113.2 2,113.2 Arts in Public Places - (DE05) Est. Completion: N/A Citywide Location: Project Type: Construction Related Description: Commission and acquire public art as part of the city's Art in Public Places Program under the Code of Ordinances, Chapter 20, Article VII-Public Art, Sections 20-121 to 20-123. The city shall expend an amount equal to one percent of the city council approved budget for each capital improvement project that is publicly visible including city buildings, structures, drainage projects, parks, transportation streetscapes, multi-use pathways, transit and pedestrian amenities (such as bus shelters, sidewalks and shade structures), bridges and plazas. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Construction Total: Funding Sources (In thousands of dollars) General Fund 2015 GO Bond - Q5 - Public Safety Fire Aviation Funds Regional Sales Tax - Arterial Life Cycle Program Sewer Rates SRP Aesthetic Fund Transportation 0.2% Sales Tax Total: 750.1 750.1 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 25.7 48.1 53.0 (26.1) (2.5) - (0.4) 45.6 53.0 - - - - (0.4) 45.6 53.0 89.6 - 89.6 - - - - 89.6 8.8 236.1 288.9 750.1 (236.1) (118.5) (383.2) 8.8 170.3 366.9 - - - - 8.8 170.3 366.9  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 61 - Table of Contents COMMUNITY FACILITIES | Neighborhood & Community Neighborhood & Community Downtown Entertainment District Street & Pedestrian Lighting - (DE02) Est. Completion: 06/20 North to south from Camelback Road to 6th Avenue and east to west from the Civic Center Plaza to Buckboard Location: Trail Project Type: Construction Related Description: Design and install up to eighteen new street and pedestrian level light poles and fixtures to enhance the nighttime lighting and improve public safety within the Entertainment District. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs City Fees Construction Contingency Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) General Fund Total: 23.2 4.5 245.8 44.6 43.6 11.6 373.3 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 373.3 373.3 (97.3) (97.3) 276.0 276.0 - - - - 276.0 276.0  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 62 - Table of Contents COMMUNITY FACILITIES | Neighborhood & Community Neighborhood & Community Downtown Splash Pad - (PE01) Est. Completion: 06/20 In the plaza between the Marshall Way Bridge over the Arizona Canal and Stetson Drive Location: Project Type: Construction Related Description: Design and construct splash pad to provide a fun and safe location for families and visitors. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs City Fees Construction Contingency Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) General Fund Total: 10.6 3.8 110.1 20.3 19.8 5.3 169.9 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 169.9 169.9 (60.1) (60.1) 109.7 109.7 - - - - 109.7 109.7 Gateway Monument Marker Public Art Project - (DG02) Est. Completion: 06/20 Thirteen locations at high-volume traffic entry points throughout the city Location: Project Type: Construction Related Description: Work with Scottsdale Arts to replace the thirteen existing gateway monuments with one or more new designs. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs City Fees Construction Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) General Fund Total: 9.0 2.3 128.0 13.0 4.5 156.8 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 156.8 156.8 - 156.8 156.8 - - - - 156.8 156.8  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 63 - Table of Contents COMMUNITY FACILITIES | Neighborhood & Community Neighborhood & Community Greenway-Hayden/Frank Lloyd Wright Public Art - (DG01) Est. Completion: 06/21 Area around Greenway-Hayden/Frank Lloyd Wright Location: Project Type: Construction Related Description: Work with Scottsdale Arts to locate a site, commission and acquire public art as part of the city's Art in Public Places Program. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs City Fees Construction Contingency Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) Sewer Rates Total: 12.2 1.0 363.7 41.8 54.5 12.2 485.4 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 485.4 485.4 - 485.4 485.4 - - - - 485.4 485.4 Paiute Neighborhood Center ADA Bathroom Renovations - (PE06) Est. Completion: 06/20 Paiute Neighborhood Center Location: Project Type: Construction Related Description: Renovate bathrooms to meet Americans with Disabilities Act (ADA) standards for accessibility. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Design/Construction Admin Total: Funding Sources (In thousands of dollars) General Fund CDBG Total: 5.4 147.4 25.0 177.8 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 5.4 172.4 177.8 (0.6) (170.9) (171.5) 4.8 1.5 6.3 - - - - 4.8 1.5 6.3  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 64 - Table of Contents COMMUNITY FACILITIES | Neighborhood & Community Neighborhood & Community Scottsdale Road Preservation Streetscape Enhancement - (DB50) Est. Completion: 12/19 Along Scottsdale Road from the southern to the northern city limits Location: Project Type: Construction Related Description: Acquire, preserve and restore desert lands along Scottsdale Road and promote its designation as a Scenic Corridor. Enhance Scottsdale Road’s streetscape image along its entire length to reflect its significance as the signature roadway of the community. Project may include the modification, restoration, and/or improvement of landscaping, street hardware, street signs, overhead power lines, walkways, trails, transit facilities and public art. Total Project Cost Funding Sources (In thousands of dollars) General Fund Bond 2000 Grants Transportation 0.2% Sales Tax Total: ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 31.1 (29.7) 24,455.2 (24,455.2) 96.5 (96.5) 280.2 (198.4) 24,863.1 (24,779.8) 1.5 81.8 83.3 - - - - 1.5 81.8 83.3 SkySong - ASU Scottsdale Center for Innovation - Art Component - (DC03) Est. Completion: 06/20 Southeast corner of Scottsdale Road and McDowell Road Location: Project Type: Construction Related Description: Provide an art component, as part of the city's lease responsibility with the Arizona State University Foundation (ASUF) to provide infrastructure to support site development. Funding Sources (In thousands of dollars) General Fund Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 607.5 607.5 (104.2) (104.2) 503.3 503.3 - - - - 503.3 503.3 TNEC - Monument Sign - (DF01) Est. Completion: 12/19 WestWorld Location: Project Type: Construction Related Description: Install a Monument Sign at the Tony Nelssen Equestrian Center facility. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Machinery and Equipment Total: Funding Sources (In thousands of dollars) Tourism Development Funds Total: 36.6 36.6 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 36.6 36.6 - 36.6 36.6 - - - - 36.6 36.6  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 65 - Table of Contents COMMUNITY FACILITIES | Neighborhood & Community Neighborhood & Community TPC Stadium Course - Midway Grill Improvements - (PG06) Est. Completion: 06/21 Tournament Players Club (TPC) Scottsdale Location: Project Type: Construction Related Description: Design and construct improvements to the Midway Grill on the TPC Scottsdale stadium course. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Design/Construction Admin Total: Funding Sources (In thousands of dollars) Tournament Player's Club Basin Total: 72.0 1,800.0 1,872.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 1,872.0 1,872.0 - 1,872.0 1,872.0 - - - - 1,872.0 1,872.0 WestWorld Lot H Electrical Improvements - (DE07) Est. Completion: 12/19 WestWorld Location: Project Type: Construction Related Description: Relocate two existing 800-amp electrical service stations into underground vaults to accommodate the new Barrett-Jackson tent configuration. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) Tourism Development Funds Total: 10.3 131.0 13.6 5.1 160.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 160.0 160.0 (124.1) (124.1) 35.9 35.9 - - - - 35.9 35.9  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 66 - Table of Contents COMMUNITY FACILITIES | Neighborhood & Community Neighborhood & Community WestWorld Purchase of Portable RV Pedestals - (DE08) Est. Completion: 12/19 WestWorld Location: Project Type: Construction Related Description: Purchase 126 portable Recreational Vehicle (RV) pedestals. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Machinery and Equipment Total: Funding Sources (In thousands of dollars) Tourism Development Funds Total: 377.0 377.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 377.0 377.0 (353.8) (353.8) 23.2 23.2 - - - - 23.2 23.2 WestWorld Tent Removal - (DD03) Est. Completion: 06/20 WestWorld Location: Project Type: Construction Related Description: Complete civil restorations and electrical relocations associated with dismantling the city tent. Restoration includes asphalt patching and capping existing water lines. Electrical relocations include existing above ground facilities. Funding Sources (In thousands of dollars) General Fund Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 700.0 700.0 (45.2) (45.2) 654.8 654.8 - - - - 654.8 654.8  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 67 - Table of Contents COMMUNITY FACILITIES | Parks/Park Improvements Parks/Park Improvements Aquatics Lifecycle Replacement - (PG04) Est. Completion: 06/24 Pools citywide Location: Project Type: Construction Related Description: Replace pool equipment and amenities to maintain a safe and enjoyable environment for the public at each of the city’s four swimming pools. This project replaces equipment such as pumps and filters, amenities like diving towers, slides and play features and structural elements such as pool decking as they reach the end of their lifecycle. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Contingency Machinery and Equipment Total: Funding Sources (In thousands of dollars) General Fund Total: 151.1 521.0 3,434.2 4,106.2 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 4,106.2 4,106.2 - 703.8 703.8 1,057.6 1,057.6 1,449.6 1,449.6 169.3 169.3 726.0 726.0 4,106.2 4,106.2 Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 68 - Table of Contents COMMUNITY FACILITIES | Parks/Park Improvements Parks/Park Improvements McCormick-Stillman RR Park Improvements - Phase I - (PG03) Est. Completion: 06/20 McCormick-Stillman Railroad Park Location: Project Type: Construction Related Description: Begin the implementation of the Phase I improvements identified in the McCormick-Stillman Railroad Park Masterplan, which includes the replacement of the existing bunkhouse, relocation of the Merci Train and expansion of the parking lot. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs City Fees Construction Contingency Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) General Fund McCormick RailRoad Park Total: 251.1 62.8 2,615.9 523.2 470.9 125.6 4,049.5 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 3,199.5 850.0 4,049.5 - 3,199.5 850.0 4,049.5 - - - - 3,199.5 850.0 4,049.5 Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 69 - Table of Contents COMMUNITY FACILITIES | Parks/Park Improvements Parks/Park Improvements McDowell Road - Berm Landscaping - (DE01) Est. Completion: 06/20 North side of McDowell Road, adjacent to Indian Bend Wash Location: Project Type: Construction Related Description: Design, construct, and maintain landscaping and pedestrian improvements on two city-owned vacant parcels located on the north side of McDowell Road on either side of the Indian Bend Wash. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Art in Public Places Construction Contingency Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) General Fund Total: 57.4 6.0 597.4 167.5 107.5 28.7 964.5 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 964.5 964.5 (6.9) (6.9) 957.7 957.7 - - - - 957.7 957.7 Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 70 - Table of Contents COMMUNITY FACILITIES | Parks/Park Improvements Parks/Park Improvements Park Amenities - (PG05) Est. Completion: 06/24 Parks citywide Location: Project Type: Construction Related Description: Replace and improve equipment and amenities throughout the parks system as recommended by the Community Services Master Plan. The replacement of aging ramadas, installation of shade structures at ball fields, improvements to spray pads, replacement or installation of fencing in various locations, and addition to inventory of sand valley courts will maintain and improve the excellent level of service at Scottsdale parks. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs City Fees Construction Contingency Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) General Fund Total: 104.4 26.1 3,057.8 151.6 130.4 52.2 3,522.5 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 3,522.5 3,522.5 - 669.5 669.5 758.0 758.0 747.0 747.0 694.0 694.0 654.0 654.0 3,522.5 3,522.5 Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 71 - Table of Contents COMMUNITY FACILITIES | Parks/Park Improvements Parks/Park Improvements Park Restrooms - (PG01) Est. Completion: 06/23 Eldorado, Pima, Vista del Camino and McCormick-Stillman Railroad Parks Location: Project Type: Construction Related Description: Design, demolish and reconstruct restroom/storage buildings in four city parks. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs City Fees Construction Contingency Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) General Fund Total: 551.7 77.6 5,770.1 646.6 971.8 275.8 8,293.5 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 8,293.5 8,293.5 - 1,339.8 1,339.8 1,389.9 1,389.9 4,451.9 4,451.9 1,111.9 1,111.9 - 8,293.5 8,293.5 Playground Rehabilitation - (PG02) Est. Completion: 06/22 Parks citywide Location: Project Type: Construction Related Description: Replace aging and dilapidated playground equipment and install or replace shade structures at some city parks. As playground equipment reaches the end of its service life it becomes less useful and attractive to park users and in some cases must be closed due to safety concerns. Playground rehabilitation ensures park users can enjoy all park amenities. Shade structures also extend the life of playground equipment by protecting it from sun damage. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Contingency Machinery and Equipment Total: Funding Sources (In thousands of dollars) General Fund Total: 46.5 105.7 1,057.0 1,209.2 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 1,209.2 1,209.2 - 547.7 547.7 416.7 416.7 244.7 244.7 - - 1,209.2 1,209.2 Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 72 - Table of Contents COMMUNITY FACILITIES | Parks/Park Improvements Parks/Park Improvements Renovate Indian Bend Wash Area/Vista del Camino Park - (PD05) Est. Completion: 12/19 Vista del Camino Lakes Location: Project Type: Construction Related Description: Develop a master plan for the Indian Bend Wash from McKellips Road to Thomas Road. Design and implement an interim solution for repair of the drainage structure north of McKellips Road. Funding Sources (In thousands of dollars) General Fund Bond 2000 Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 864.9 278.5 1,143.3 (24.7) (278.5) (303.1) 840.2 840.2 - - - - 840.2 840.2 Scottsdale Stadium Infrastructure Improvements - (PB57) Est. Completion: N/A Scottsdale Stadium Location: Project Type: Construction Related Description: Maintain and replace aging building components in the stadium. Funding Sources (In thousands of dollars) General Fund Stadium Improvement IGA Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 10.0 1,614.5 1,624.5 (8.4) (287.3) (295.7) 1.6 518.3 520.0 202.2 202.2 202.2 202.2 202.2 202.2 202.2 202.2 1.6 1,327.1 1,328.8 Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 73 - Table of Contents COMMUNITY FACILITIES | Parks/Park Improvements Parks/Park Improvements Scottsdale Stadium Renovations - (PE05) Est. Completion: 06/20 Scottsdale Stadium Location: Project Type: Construction Related Description: Expand and renovate the clubhouse/training areas to include flexible multiuse facilities with meeting rooms, kitchen and serving areas that will support clubhouse utilization for the spring training season and multiuse event center activity throughout the year. Expand and improve shade to the right field Charro Lodge area, upgrade the main entry plaza adjacent to Drinkwater Boulevard and first base concourse and bleachers. Enhance the press box/multi-use rooms, ticketing facilities and city offices. Upgrade overall site and building infrastructure, code and safety features to support year-round multi-use event center activities. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs City Fees Construction Contingency Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) Giants Contributions MPC Bonds Stadium Stadium's Concessionaire Tourism Development Funds Total: 530.8 85.4 48,595.2 773.2 350.0 265.4 50,600.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 5,000.0 33,100.0 2,500.0 10,000.0 50,600.0 (3,823.0) (4,940.1) (8,763.2) 5,000.0 29,277.0 2,500.0 5,059.9 41,836.8 - - - - 5,000.0 29,277.0 2,500.0 5,059.9 41,836.8 Scottsdale Stadium Safety Repairs & Maintenance - (PD02) Est. Completion: 06/20 Scottsdale Stadium Location: Project Type: Construction Related Description: Renovate and improve various areas in the Scottsdale Stadium to improve safety. Included are the renovation of concrete walkways, replacement of concrete tree grates and improvement of general lighting in all concourses and pedestrian walkways. Funding Sources (In thousands of dollars) General Fund Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 1,723.0 1,723.0 (1,569.3) (1,569.3) 153.7 153.7 - - - - 153.7 153.7 Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 74 - Table of Contents 4VSNIGX(IWGVMTXMSRW DRAINAGE/FLOOD CONTROL -RXLSYWERHWSJHSPPEVW (VEMREKI*PSSH'SRXVSP (VEMREKI*PSSH'SRXVSPJSGYWIWSRTVSXIGXMRKEHMZIVWIJEQMP]SVMIRXIHGSQQYRMX][LIVIRIMKLFSVLSSHWEVIWEJIERH[IPP QEMRXEMRIHF]TVIZIRXMRKTVSTIVX]HEQEKIJVSQJPSSHMRK8LMWTVSKVEQEGLMIZIWXLIWIKSEPWXLVSYKLJPSSHTPEMRQETTMRK QIIXMRKVIKYPEXSV]VIUYMVIQIRXWERHMHIRXMJ]MRKERHGSVVIGXMRKLE^EVHWXSVIHYGIJYXYVIJPSSHHEQEKITSXIRXMEP8LMWMW EGGSQTPMWLIHXLVSYKLXLIYWISJHIXIRXMSRFEWMRWGYPZIVXERHGLERRIPTVSNIGXWERHETVSKVEQSJRIMKLFSVLSSHHVEMREKI MQTVSZIQIRXW%TTVS\MQEXIP]TIVGIRX 5QMPPMSR SJXLI'-4LEWFIIRMHIRXMJMIHXSEHHVIWWXLIHVEMREKIERHJPSSH GSRXVSPRIIHWSJXLIGMX] 4VSNIGX (VEMREKI*PSSH'SRXVSP (VEMREKI*PSSH'SRXVSP 'VSWWVSEHW)EWX*PSSH'SRXVSP4LEWI- *& +VERMXI6IIJ;EXIVWLIH *& 4VMRGIWW(VMZI(VEMREKI4VSNIGX *' 6E[LMHI;EWL*PSSH'SRXVSP'37'SRXVMFYXMSR *) 6IEXE;EWL*PSSH'SRXVSP *& 7XSVQ[EXIV*II'SRXMRKIRG] >+ 6IGYVVMRK'ETMXEP1EMRXIRERGI4VSNIGXW %HSTXIH  *SVIGEWX  *SVIGEWX  *SVIGEWX                                            City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 75 - *SVIGEWX  8SXEP 4EKI Table of Contents COMMUNITY DRAINAGE/FLOOD FACILITIES CONTROL | Library/Library | Drainage/Flood Improvements Control Drainage / Flood Control Crossroads East Flood Control Phase I - (FB53) Est. Completion: 12/21 Along the powerline corridor, and the Arizona State Route 101 Detention Basin Outfall Location: Project Type: Construction Related Description: Construct a trapezoidal open drainage channel along the powerline corridor, a stormwater detention basin on a 52-acre site north of the Arizona State Route 101, west of Pima Road and south of the Water Campus, known as the Loop 101 Detention Basin, and an outfall from the Loop 101 Detention Basin to Mayo Boulevard to protect Crossroads East and downstream development from the 100-year flood. Funding Sources (In thousands of dollars) General Fund AZ State Land Department Reimbursement Contributions MPC Bonds - Stormwater Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 1,423.2 (1,640.6) (217.4) - - - - (217.4) 937.4 (62.1) 875.3 - - - - 875.3 593.1 14,062.6 17,016.3 (593.1) (2,295.9) 14,062.6 14,720.4 - - - - 14,062.6 14,720.4  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 76 - Table of Contents COMMUNITY DRAINAGE/FLOOD FACILITIES CONTROL | Library/Library | Drainage/Flood Improvements Control Drainage / Flood Control Granite Reef Watershed - (FB50) Est. Completion: 06/24 Chaparral Road to the Salt River, Granite Reef Road to Pima Road Location: Project Type: Construction Related Description: Perform value engineering, final design, and construction of the project in participation with Salt River Pima-Maricopa Indian Community and the Flood Control District of Maricopa County. Design concept is being evaluated to efficiently convey stormwater from south of Indian School Road to the Salt River. Funding Sources (In thousands of dollars) General Fund Bond 2000 Flood Control District IGA Salt River Pima Maricopa Indian Community IGA Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2023/24 Total Remaining Budget 5,967.0 3,128.9 24,221.1 (179.3) (3,128.9) (4,540.4) 5,787.7 762.6 - - - 18,918.1 5,787.7 19,680.7 14,532.7 (2,616.6) (141.6) - - - 12,057.7 11,916.1 47,849.8 (10,465.2) 6,408.7 - - - 30,975.8 37,384.6 Forecast 2022/23  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 77 - Table of Contents COMMUNITY DRAINAGE/FLOOD FACILITIES CONTROL | Library/Library | Drainage/Flood Improvements Control Drainage / Flood Control Princess Drive Drainage Project - (FC01) Est. Completion: 06/20 Princess Drive east of Scottsdale Road Location: Project Type: Construction Related Description: Analyze the drainage that is conveyed through the existing box culvert under Princess Drive east of Scottsdale Road. Design and construct modifications to enhance the flow under Princess Drive to reduce sedimentation within the structure. Funding Sources (In thousands of dollars) Contributions Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 1,425.0 1,425.0 (213.4) (213.4) 1,211.6 1,211.6 - - - - 1,211.6 1,211.6 Rawhide Wash Flood Control COS Contribution - (FE01) Est. Completion: 06/22 Location: Rawhide Wash from one-half mile north of Happy Valley Road to Pinnacle Peak Road, east of Scottsdale Road. Project Type: Construction Related Description: Complete the City of Scottsdale's contribution to the larger Rawhide Wash project that will be completed in partnership with the City of Phoenix, the Arizona State Land Department and the Maricopa County Flood Control District. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Design/Construction Admin Total: Funding Sources (In thousands of dollars) General Fund Total: 2,000.0 2,000.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 2,000.0 2,000.0 (69.4) (69.4) 1,930.6 1,930.6 - - - - 1,930.6 1,930.6  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 78 - Table of Contents COMMUNITY DRAINAGE/FLOOD FACILITIES CONTROL | Library/Library | Drainage/Flood Improvements Control Drainage / Flood Control Reata Wash Flood Control - (FB55) Est. Completion: 06/24 Reata Wash from Pinnacle Peak Road to WestWorld Location: Project Type: Construction Related Description: Design channel, levee, culvert, and erosion control improvements to reduce the size of the Reata Wash floodplain protecting existing homes, businesses and infrastructure. Funding Sources (In thousands of dollars) General Fund Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 2,256.0 2,256.0 (1,629.5) (1,629.5) 626.5 626.5 - - - - 626.5 626.5 Stormwater Fee Contingency - (ZG01) Est. Completion: Location: Project Type: Description: N/A Citywide Construction Related Provide a budgetary appropriation set aside for citywide emergencies or unforeseen expenditures not otherwise budgeted. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Contingency Total: Funding Sources (In thousands of dollars) CIP Stormwater Utility Bill Fee Total: 5,000.0 5,000.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 5,000.0 5,000.0 - 1,000.0 1,000.0 1,000.0 1,000.0 1,000.0 1,000.0 1,000.0 1,000.0 1,000.0 1,000.0 5,000.0 5,000.0  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 79 - FY 2019/20 Adopted Budget City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 80 - Table of Contents 4VSNIGX(IWGVMTXMSRW PRESERVATION -RXLSYWERHWSJHSPPEVW 4VIWIVZEXMSR 4VIWIVZEXMSRJSGYWIWSRTVIWIVZMRKXLIGLEVEGXIVERHIRZMVSRQIRXSJ7GSXXWHEPI8LMWKSEPMWQIXF]PERHEGUYMWMXMSREGXMZMXMIW JSVXLI1G(S[IPP7SRSVER4VIWIVZIJSVXLITYVTSWISJQEMRXEMRMRKWGIRMGZMI[WTVIWIVZMRKREXMZITPERXWERH[MPHPMJIERH TVSZMHMRKTYFPMGEGGIWWXSXLI1G(S[IPP1SYRXEMRWERH7SRSVER(IWIVX8LIIPIGXMSRI\TERHIHXLIVIGSQQIRHIHWXYH] FSYRHEV]JVSQXLISVMKMREPEGVIWXSEFSYXEGVIW8LIIPIGXMSRTVSZMHIHEREHHMXMSREPVIZIRYIWXVIEQ  TIVGIRXWEPIWXE\VEXIMRGVIEWI EW[IPPEWXLIFSRHMRKGETEGMX] QMPPMSR XLEXGSRXMRYIWXSTVSZMHIEYXLSVMX]XSGEVV]SR TVIWIVZEXMSRIJJSVXW%TTVS\MQEXIP]TIVGIRX QMPPMSR SJXLI'-4LEWFIIRMHIRXMJMIHXSEHHVIWWXLMWTVSKVEQ %HSTXIH  4VSNIGX 4VIWIVZEXMSR 4VIWIVZEXMSR4VIWIVZEXMSR-QTVSZIQIRXW 'IRXVEP%VIE8VEMP'SRWXVYGXMSR (&  )\TERHIH1G(S[IPP7SRSVER4VIWIVZI 4&  *VEIWJMIPHERH+VERMXI1SYRXEMR8VEMPLIEHW 4(  2SVXLERH'IRXVEP%VIE%GGIWW'SRXVSP 7XEFMPM^EXMSR  4& 2SVXL%VIE8VEMP'SRWXVYGXMSR 4&  4MQE(]REQMXI8VEMPLIEH 4&  6IWXSVEXMSR,EFMXEX-RZEWMZI4PERX;MPHPERH*MVI  4VIZIRXMSR 7EJIX]-QTVSZIQIRXW 4& 7SYXL%VIE%GGIWW'SRXVSP 4&  7SYXL%VIE8VEMP'SRWXVYGXMSR 4&  6IGYVVMRK'ETMXEP1EMRXIRERGI4VSNIGXW *SVIGEWX  *SVIGEWX  *SVIGEWX                                                        City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 81 - *SVIGEWX  8SXEP 4EKI Table of Contents PRESERVATION | Preservation/Preservation Improvements Preservation/Preservation Improvements Central Area Trail Construction - (DB52) Est. Completion: 12/20 McDowell Sonoran Preserve, various planned trail locations in the central area Location: Project Type: Construction Related Description: Construct various multi-use trails in the central Preserve (approximately ten miles of trails). These multi-use trails are identified in the Master Trails Plan for the Preserve recommended by the McDowell Sonoran Preserve Commission and approved by City Council. Funding Sources (In thousands of dollars) Preserve Sales Tax 2004 (0.15) Preserve Tax 04 - Land & Improvements Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 406.4 (406.4) - - - - - - 466.1 (185.1) 281.0 - - - - 281.0 872.5 (591.5) 281.0 - - - - 281.0 Expanded McDowell Sonoran Preserve - (PB66) Est. Completion: N/A McDowell Mountain Preserve Location: Project Type: Construction Related Description: Purchase Preserve land within the estimated 34,000 acre planned Preserve boundary, as approved by the voters in May 1995 and November 1998. Total Project Cost Funding Sources (In thousands of dollars) G.O. Preserve Bonds Preserve Tax 04 - Land & Improvements Preserve Tax 95 Land Acquisition Only Total: ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 20,098.7 (20,098.7) - - - - - - (167.7) 32,709.5 - - - - 32,709.5 15,291.0 (15,291.0) 68,267.0 (35,557.5) 32,709.5 - - - - 32,709.5 32,877.3 Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 82 - Table of Contents PRESERVATION | Preservation/Preservation Improvements Preservation/Preservation Improvements Fraesfield and Granite Mountain Trailheads - (PD04) Est. Completion: 12/20 McDowell Sonoran Preserve, Dynamite Boulevard and 134th Street and Lone Mountain Road and 136th Street Location: Project Type: Construction Related Description: Construct amenities including trail connections, signage, driveway, parking, shade ramadas, restrooms, interpretative materials, mountain climbing staging, equestrian amenities, staff/volunteer support facilities, storage and other infrastructure improvements to serve passive recreational users at the north community access areas in the McDowell Sonoran Preserve. These access areas will serve as staging areas for exploration of the Preserve through connection to the existing and planned citywide trail system both in and outside of the Preserve. Funding Sources (In thousands of dollars) Preserve Tax 04 - Land & Improvements Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 7,000.0 (5,797.8) 1,202.2 - - - - 1,202.2 7,000.0 (5,797.8) 1,202.2 - - - - 1,202.2 North and Central Area Access Control & Stabilization - (PB54) Est. Completion: 06/21 McDowell Sonoran Preserve near Pima Road, 136th Street, Dynamite Boulevard and Stagecoach Road Location: Project Type: Construction Related Description: Stabilize, plan and improve several existing informal trail access points in the northern region of the McDowell Sonoran Preserve. The project will include stabilization of entry roads and the installation of gates, fencing and signage as required around the perimeter of the central and northern region of the Preserve. Funding Sources (In thousands of dollars) Preserve Sales Tax 2004 (0.15) Preserve Tax 04 - Land & Improvements Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 1,141.3 (1,141.3) - - - - - - 2,758.7 (2,168.5) 490.2 100.0 - - - 590.2 3,900.0 (3,309.8) 490.2 100.0 - - - 590.2 Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 83 - Table of Contents PRESERVATION | Preservation/Preservation Improvements Preservation/Preservation Improvements North Area Trail Construction - (PB50) Est. Completion: 06/21 McDowell Sonoran Preserve, generally north of Dynamite Boulevard east of Pima Road Location: Project Type: Construction Related Description: Eradicate approximately two-thirds of the existing trails and restore the land. Improve the remaining one-third of existing trails, which are included in the Conceptual Trails Plan for the Preserve recommended by the McDowell Sonoran Preserve Commission and approved by City Council. Funding Sources (In thousands of dollars) Preserve Sales Tax 2004 (0.15) Preserve Tax 04 - Land & Improvements Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 964.3 (964.3) - - - - - - 2,235.7 (1,310.6) 825.1 100.0 - - - 925.1 3,200.0 (2,274.9) 825.1 100.0 - - - 925.1 Pima/Dynamite Trailhead - (PB65) Est. Completion: 06/21 McDowell Sonoran Preserve, Northeast of Pima Road and Dynamite Boulevard Location: Project Type: Construction Related Description: Construct amenities including trail connections, signage, driveway, parking, shade ramadas, restrooms, small amphitheater, interpretative materials, equestrian amenities, staff/volunteer support facilities, storage and other infrastructure improvements to serve passive recreational users. This access area will serve as a staging area for exploration of the Preserve through connection to the existing and planned citywide trail system both in and outside of the Preserve. Funding Sources (In thousands of dollars) Contributions Preserve Tax 04 - Land & Improvements Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 50.0 (50.0) - - - - - - 8,270.9 (1,285.3) 6,985.6 - - - - 6,985.6 8,320.9 (1,335.3) 6,985.6 - - - - 6,985.6 Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 84 - Table of Contents PRESERVATION | Preservation/Preservation Improvements Preservation/Preservation Improvements Restoration, Habitat, Invasive Plant, Wildland Fire Prevention & Safety Improvements - (PB52) Est. Completion: 06/23 McDowell Sonoran Preserve Location: Project Type: Construction Related Description: Eradicate unwanted trails and roads and restore these areas. Remove invasive plants and establish wildland fire prevention buffer along road and driveway edges of the Preserve. Funding Sources (In thousands of dollars) Contributions Preserve Sales Tax 2004 (0.15) Preserve Tax 04 - Land & Improvements Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 5.7 20.1 (5.7) (20.1) - - - - - - 2,681.2 (215.7) 1,535.5 330.0 300.0 300.0 - 2,465.5 2,707.0 (241.5) 1,535.5 330.0 300.0 300.0 - 2,465.5 South Area Access Control - (PB61) Est. Completion: 06/23 McDowell Sonoran Preserve generally South of the Deer Valley Road alignment Location: Project Type: Construction Related Description: Improve and expand several existing trail heads in the southern region of the McDowell Sonoran Preserve. The project will include additional parking, entry roads, and the installation of fencing and signage as required around the perimeter of the southern region of the Preserve. Funding Sources (In thousands of dollars) Preserve Sales Tax 2004 (0.15) Preserve Tax 04 - Land & Improvements Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 603.2 (603.2) - - - - - - 2,146.8 (470.5) 1,226.3 150.0 150.0 150.0 - 1,676.3 2,750.0 (1,073.7) 1,226.3 150.0 150.0 150.0 - 1,676.3 South Area Trail Construction - (PB51) Est. Completion: 06/20 McDowell Sonoran Preserve, north-south corridor in the interior of the McDowell Mountains Location: Project Type: Construction Related Description: Construct a remote, interior, secondary, multi-use trail connecting existing trails in the south part of the Preserve to existing trails in the central area of the Preserve along a north-south corridor. This multi-use trail is identified in the Master Trails Plan for the Preserve recommended by the McDowell Sonoran Preserve Commission and approved by City Council. Funding Sources (In thousands of dollars) Preserve Sales Tax 2004 (0.15) Preserve Tax 04 - Land & Improvements Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 410.4 (410.4) - - - - - - 579.6 (25.6) 554.0 - - - - 554.0 990.0 (436.0) 554.0 - - - - 554.0 Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 85 - FY 2019/20 Adopted Budget City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 86 - Table of Contents 4VSNIGX(IWGVMTXMSRW PUBLIC SAFETY -RXLSYWERHWSJHSPPEVW 4YFPMG7EJIX] 4YFPMG7EJIX]TVSKVEQWJSGYWSRIRLERGMRKERHTVSXIGXMRKEHMZIVWIJEQMP]SVMIRXIHGSQQYRMX][LIVIRIMKLFSVLSSHWEVIWEJI 8LMWKSEPMWQIXF]TVSZMHMRKJMVIERHTSPMGIWXEXMSRWXVEMRMRKJEGMPMXMIWERHEYXSQEXMSRW]WXIQWVIPEXIHXSJMVIERHTSPMGI STIVEXMSRW%TTVS\MQEXIP]TIVGIRX QMPPMSR SJXLI'-4LEWFIIRMHIRXMJMIHXSEHHVIWWXLITYFPMGWEJIX]RIIHWSJXLI GMX] 4VSNIGX 4YFPMG7EJIX] *MVI4VSXIGXMSR %MVGVEJX6IWGYIERH*MVIJMKLXMRK:ILMGPI 8)14 *MVI7TIGMEPX])UYMTQIRX )+ *MVI7XEXMSR6IPSGEXMSR &' *MVI7XEXMSR0ERH%GUYMWMXMSR &* *MVI7XEXMSR(IWMKRERH'SRWXVYGXMSR &' 2EXMSREP*MVI4VSXIGXMSR%WWSGMEXMSR 2*4% 7XEXMSR 7XERHEVHW 8)14*  4YFPMG7EJIX]*MVI6EHMS6ITPEGIQIRX =* 6IRSZEXI*MVI7XEXMSR 8)14* 4SPMGI %HZERGIH1SFMPI7SPYXMSRW .& &EPPMWXMG+PEWWEX4SPMGI(ITEVXQIRX*EGMPMXMIW &) 'PSWIH'MVGYMX8IPIZMWMSR ''8:  7IGYVMX]'EQIVE 7]WXIQ ERH%GGIWW'SRXVSP6ITPEGIQIRX .(  'VMQI0EFSVEXSV])UYMTQIRX6ITPEGIQIRX =*  'VMQI0EFSVEXSV])UYMTQIRX6ITPEGIQIRX =+ .EMP(SVQMXSV] &*  4SPMGI4SVXEFPIERH:ILMGPI6EHMS6ITPEGIQIRX =*  4SPMGI4SVXEFPIERH:ILMGPI6EHMS6ITPEGIQIRX =+ 6IGSVHW1EREKIQIRX7]WXIQERH'SQTYXIV%MHIH (MWTEXGL)RLERGIQIRXWERH6IJVIWL .& 6IGYVVMRK'ETMXEP1EMRXIRERGI4VSNIGXW %HSTXIH  *SVIGEWX  *SVIGEWX  *SVIGEWX  *SVIGEWX                                                                                                                    City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 87 - 8SXEP 4EKI      Table of Contents COMMUNITY FACILITIES PUBLIC | Library/Library SAFETY | Fire Improvements Protection Fire Protection Aircraft Rescue and Firefighting Vehicle - (TEMP2322) Est. Completion: 06/21 Fire Station 609 - Scottsdale Airport Location: Project Type: Construction Related Description: Replace the 2004 Oshkosh Class 4 Aircraft Rescue and Firefighting (ARFF) vehicle to be used to provide fire protection and operational response to the Scottsdale Airport. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Machinery and Equipment Total: Funding Sources (In thousands of dollars) Aviation Funds Fleet Rates Total: 1,006.5 1,006.5 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 251.6 754.9 1,006.5 - - 251.6 754.9 1,006.5 - - - 251.6 754.9 1,006.5 Fire Specialty Equipment - (EG01) Est. Completion: 06/20 Citywide Location: Project Type: Technology Related Description: Replace aging specialty Public Safety - Fire patient heart monitors. The equipment is essential for the care and safety of Scottsdale citizens and fire personnel. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Machinery and Equipment Total: Funding Sources (In thousands of dollars) General Fund Total: 1,340.4 1,340.4 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 1,340.4 1,340.4 - 1,340.4 1,340.4 - - - - 1,340.4 1,340.4  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 88 - Table of Contents COMMUNITY FACILITIES PUBLIC | Library/Library SAFETY | Fire Improvements Protection Fire Protection Fire Station 603 Relocation - (BC04) Est. Completion: 08/20 McCormick Ranch area Location: Project Type: Construction Related Description: Purchase land, design and construct a new fire station in the McCormick Ranch area to replace the existing Fire Station 603 and improve response times to that portion of the city. The new station will include crew quarters and facilities, office space, Occupational Safety and Health Administration (OSHA) certified decontamination area, safety gear storage and an apparatus bay. Funding Sources (In thousands of dollars) General Fund 2015 GO Bond - Q5 - Public Safety Fire 2015 GO Bond Interest In-Lieu Fees Transportation Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 480.6 7,561.5 324.0 26.4 8,392.6 (24.7) (3,100.3) (3,125.0) 456.0 4,461.2 324.0 26.4 5,267.5 - - - - 456.0 4,461.2 324.0 26.4 5,267.5  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 89 - Table of Contents COMMUNITY FACILITIES PUBLIC | Library/Library SAFETY | Fire Improvements Protection Fire Protection Fire Station 612 Land Acquisition - (BF02) Est. Completion: 06/20 Fire Station 612 - Northwest of the Airpark near the Arizona State Route 101 and Hayden Road Location: Project Type: Construction Related Description: Purchase land in preparation for the future construction of a new 12,000 square foot fire station northwest of the Airpark near the Arizona State Route 101 and Hayden Road. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Land/ROW Total: Funding Sources (In thousands of dollars) General Fund Total: 60.0 2,910.0 2,970.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 2,970.0 2,970.0 (2.3) (2.3) 2,967.7 2,967.7 - - - - 2,967.7 2,967.7 Fire Station 616 Design and Construction - (BC03) Est. Completion: 07/20 110th Street and Cave Creek Road Location: Project Type: Construction Related Description: Construct a new fire station to replace a temporary facility at 110th Street and Cave Creek Road. The new station will include crew quarters and facilities, office space, Occupational Safety and Health Administration (OSHA) certified decontamination area, safety gear storage and an apparatus bay. Funding Sources (In thousands of dollars) General Fund 2015 GO Bond - Q5 - Public Safety Fire Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 1,790.8 3,719.3 5,510.1 (2.0) (392.0) (394.0) 1,788.8 3,327.3 5,116.1 - - - - 1,788.8 3,327.3 5,116.1  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 90 - Table of Contents COMMUNITY FACILITIES PUBLIC | Library/Library SAFETY | Fire Improvements Protection Fire Protection National Fire Protection Association (NFPA) Station Standards - (TEMP1484-F) Est. Completion: 06/21 Fire Stations 607, 609, 610, 611, 614 and 615 Location: Project Type: Construction Related Description: Renovate and enhance six fire stations to meet applicable National Fire Protection Association (NFPA) 1581 standards while meeting the operational needs of the Public Safety - Fire Division. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs City Fees Construction Contingency Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) General Fund Total: 107.4 26.8 1,099.9 241.9 110.0 53.7 1,639.8 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 1,639.8 1,639.8 - - 1,639.8 1,639.8 - - - 1,639.8 1,639.8  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 91 - Table of Contents COMMUNITY FACILITIES PUBLIC | Library/Library SAFETY | Fire Improvements Protection Fire Protection Public Safety-Fire Radio Replacement - (YF31) Est. Completion: N/A Citywide Location: Project Type: Technology Related Description: Replace Public Safety - Fire radios carried in vehicles and by individual fire personnel to ensure reliable and effective public safety response to emergency calls. The Public Safety - Fire Division uses 66 mobile and 166 portable radios to respond to calls and serve the community. This equipment is used every day of the year and is subjected to extreme conditions and hazardous environments. Replacing radios on a scheduled lifecycle basis contributes to the safety of our first responders and to their ability to handle emergency response. Portable radios carried by individual fire personnel require replacement every five to seven years; mobile radios carried in vehicles require replacement every seven to ten years. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Machinery and Equipment Total: Funding Sources (In thousands of dollars) General Fund Total: 38.3 862.7 901.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 901.0 901.0 (36.4) (36.4) 88.4 88.4 - 485.4 485.4 166.0 166.0 124.8 124.8 864.6 864.6 Renovate Fire Station 606 - (TEMP1734-F) Est. Completion: 06/22 Fire Station 606, 10850 East Via Linda Road Location: Project Type: Construction Related Description: Raze Fire Station 606 and design and build a new 10,000 square foot fire station to serve the current response area. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Art in Public Places City Fees Construction Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) General Fund Total: 80.4 10.5 20.1 1,004.9 82.4 40.2 1,238.4 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 1,238.4 1,238.4 - - - 1,238.4 1,238.4 - - 1,238.4 1,238.4  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 92 - Table of Contents COMMUNITY FACILITIES | Library/Library PUBLIC SAFETY Improvements | Police Police Advanced Mobile Solutions - (JB61) Est. Completion: 06/20 Citywide Location: Project Type: Technology Related Description: Purchase Advanced Mobile Solutions including Citrix & NetMotion expansion, related licensing, new Advanced Authentication requirements and mobile computing solutions. Funding Sources (In thousands of dollars) General Fund RICO Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 8.7 97.0 105.7 (5.1) (80.4) (85.5) 3.7 16.6 20.3 - - - - 3.7 16.6 20.3 Ballistic Glass at Police Department Facilities - (BE02) Est. Completion: 06/20 Public Safety - Police District 1 Location: Project Type: Construction Related Description: Design and construct ballistic glass and other target hardening features at the Public Safety - Police District 1 location. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Contingency Total: Funding Sources (In thousands of dollars) General Fund Total: 25.2 280.0 30.5 335.7 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 335.7 335.7 (34.3) (34.3) 301.4 301.4 - - - - 301.4 301.4 Closed Circuit Television (CCTV) (Security Camera System) and Access Control Replacement - (JD05) Est. Completion: 06/22 Citywide Location: Project Type: Technology Related Description: Replace non-functioning Closed Circuit Television (CCTV) security equipment. Funding Sources (In thousands of dollars) General Fund Court Enhancement Funds Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 1,902.5 198.0 2,100.5 (809.8) (117.8) (927.5) 781.0 80.2 861.2 239.8 239.8 71.9 71.9 - - 1,092.7 80.2 1,173.0  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 93 - Table of Contents COMMUNITY FACILITIES | Library/Library PUBLIC SAFETY Improvements | Police Police Crime Laboratory Equipment Replacement - (YG03) Est. Completion: N/A Public Safety - Police District 1 Location: Project Type: Technology Related Description: Replace or upgrade crime laboratory equipment and instrumentation that has reached or exceeded its manufacturer's life expectancy. This reduces the time it takes to examine forensic evidence, increases the reliability of examination results in court and reduces maintenance issues and system down-time. This equipment and instrumentation are used daily and are on a five-year replacement cycle. Maintaining updated equipment is a standard required by the Scottsdale crime lab’s national accreditation, through which the Public Safety - Police can access national forensic databases when investigating crimes. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Information Technology Machinery and Equipment Total: Funding Sources (In thousands of dollars) General Fund Forensic Science IGAs Total: 77.9 237.4 934.0 1,249.3 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 1,069.3 180.0 1,249.3 - 259.9 40.0 299.9 225.9 40.0 265.9 197.7 40.0 237.7 178.4 40.0 218.4 207.4 20.0 227.4 1,069.3 180.0 1,249.3  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 94 - Table of Contents COMMUNITY FACILITIES | Library/Library PUBLIC SAFETY Improvements | Police Police Crime Laboratory Equipment Replacement - (YF03) Est. Completion: N/A Public Safety - Police District 1 Location: Project Type: Technology Related Description: Replace or upgrade crime laboratory equipment and instrumentation that has reached or exceeded its manufacturer's life expectancy. This reduces the time it takes to examine forensic evidence, increases the reliability of examination results in court and reduces maintenance issues and system down-time. This equipment and instrumentation are used daily and are on a five-year replacement cycle. Maintaining updated equipment is a standard required by the Scottsdale crime lab’s national accreditation, through which the Public Safety - Police can access national forensic databases when investigating crimes. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Machinery and Equipment Total: Funding Sources (In thousands of dollars) General Fund Forensic Science IGAs Total: 26.7 297.0 323.7 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 303.7 20.0 323.7 (101.1) (13.4) (114.6) 202.6 6.6 209.1 - - - - 202.6 6.6 209.1  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 95 - Table of Contents COMMUNITY FACILITIES | Library/Library PUBLIC SAFETY Improvements | Police Police Jail Dormitory - (BF03) Est. Completion: 06/22 Public Safety - Police District 2 Jail Location: Project Type: Construction Related Description: Design and construct three dormitories at the District 2 Jail to implement the Out of Jurisdiction Confinement (OOJC) program to house non-violent, low risk defendants sentenced in the Scottsdale City Court. The program will provide an additional revenue stream to the city, while reducing the city's cost to house defendants at the Maricopa County jail. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Contingency Design/Construction Admin Machinery and Equipment Salaries Total: Funding Sources (In thousands of dollars) General Fund Total: 48.5 410.6 71.8 52.0 100.0 19.4 702.3 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 702.3 702.3 (27.5) (27.5) 424.8 424.8 250.0 250.0 - - - 674.8 674.8  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 96 - Table of Contents COMMUNITY FACILITIES | Library/Library PUBLIC SAFETY Improvements | Police Police Police Portable and Vehicle Radio Replacement - (YG06) Est. Completion: N/A Citywide Location: Project Type: Technology Related Description: Replace Public Safety - Police radios carried in vehicles and by individual police personnel to ensure reliable and effective public safety response to emergency calls. Police radios see nearly continuous use every day of the year, most are subjected to extreme conditions and hazardous environments. Replacing radios on a scheduled lifecycle basis contributes to the safety of our first responders and to their ability to handle emergency response. Portable radios carried by individual police personnel are on a seven-year replacement plan and vehicle radios are on a ten-year replacement plan. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Machinery and Equipment Total: Funding Sources (In thousands of dollars) General Fund Total: 432.3 4,624.3 5,056.5 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 5,056.5 5,056.5 - 991.9 991.9 991.9 991.9 991.9 991.9 992.7 992.7 1,088.1 1,088.1 5,056.5 5,056.5 Police Portable and Vehicle Radio Replacement - (YF06) Est. Completion: N/A Citywide Location: Project Type: Technology Related Description: Replace Public Safety - Police radios carried in vehicles and by individual police personnel to ensure reliable and effective public safety response to emergency calls. Police radios see nearly continuous use every day of the year, most are subjected to extreme conditions and hazardous environments. Replacing radios on a scheduled lifecycle basis contributes to the safety of our first responders and to their ability to handle emergency response. Portable radios carried by individual police personnel are on a seven-year replacement plan and vehicle radios are on a ten-year replacement plan. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Machinery and Equipment Total: Funding Sources (In thousands of dollars) General Fund Total: 94.5 1,050.0 1,144.5 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 1,144.5 1,144.5 (1,009.2) (1,009.2) 135.3 135.3 - - - - 135.3 135.3  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 97 - Table of Contents COMMUNITY FACILITIES | Library/Library PUBLIC SAFETY Improvements | Police Police Records Management System and Computer Aided Dispatch Enhancements and Refresh - (JB62) Est. Completion: 06/21 Citywide Location: Project Type: Technology Related Description: Replace the outdated Police Computer Aided Dispatch (CAD) and Records Management System (RMS) with a web-based platform designed to interface with new applications and improve reporting and analytics capabilities. The upgrade will enhance mapping and radio capabilities, improve vehicle dispatching, upgrade text-to-9-1-1 capabilities, increase efficiency in report writing and provide better case management. Funding Sources (In thousands of dollars) General Fund RICO Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 543.4 363.0 906.4 (0.6) (0.6) 32.1 363.0 395.1 510.8 510.8 - - - 542.9 363.0 905.9  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 98 - Table of Contents 4VSNIGX(IWGVMTXMSRW SERVICE FACILITIES -RXLSYWERHWSJHSPPEVW 7IVZMGI*EGMPMXMIW 7IVZMGI*EGMPMXMIWJSGYWSRGSSVHMREXMRKPERHYWIERHMRJVEWXVYGXYVITPERRMRK[MXLMRXLIGSRXI\XSJJMRERGMEPHIQERHWERH EZEMPEFPIVIWSYVGIW8LIWITVSKVEQWEGLMIZIXLMWKSEPXLVSYKLXLIVIRSZEXMSRSJGYVVIRXJEGMPMXMIWERHXIGLRSPSK]RIIHW RIGIWWEV]JSVXLIIJJMGMIRXERHIJJIGXMZISTIVEXMSRWSJXLIGMX]%TTVS\MQEXIP]TIVGIRX QMPPMSR SJXLI'-4LEWFIIR MHIRXMJMIHXSEHHVIWWXLMWTVSKVEQ %HSTXIH  4VSNIGX 7IVZMGI*EGMPMXMIW 1YRMGMTEP*EGMPMXMIW-QTVSZIQIRXW %HHMXMSREP'SQTVIWWIH2EXYVEP+EW '2+ 7XEXMSR  &' 'MX]'SYVX'YWXSQIV7IVZMGI'SYRXIVWERH0SFF]  6IQSHIP &) 'SYVXLSYWI-QTVSZIQIRXW%VGLMXIGXYVEP7IVZMGIW  &* )\TERWMSRSJ)\MWXMRK4EVOMRK+EVEKIW (*   *EGMPMXMIW6ITEMVERH1EMRXIRERGI4VSKVEQ =*   *EGMPMXMIW6ITEMVERH1EMRXIRERGI4VSKVEQ =+  *PIIX*YIP7MXI9TKVEHI &)  *PIIX7SYXL'SVTSVEXI=EVH'SQTVIWWIH2EXYVEP+EW  'SQTPMERGI &+ 2SVXL'SVT=EVH'2+'SQTPMERGI &&  7SPMH;EWXI9TKVEHIWERH-QTVSZIQIRXW4VSKVEQ  &+ 8IGLRSPSK]-QTVSZIQIRXW '-4'SRXMRKIRG] >&  '-4'SRXMRKIRG]JSV*YXYVI+VERXW >&  (EXE'IRXIV6IWMPMIRG]4PER .(  )RXIVTVMWI6IWSYVGI4PERRMRK7]WXIQ 8)14*  -VVMKEXMSR'SRXVSP7]WXIQ 4*   -82IX[SVO-RJVEWXVYGXYVI =*   -82IX[SVO-RJVEWXVYGXYVI =+   -87IVZIV-RJVEWXVYGXYVI =*   -87IVZIV-RJVEWXVYGXYVI =+  0MGIRWIERH4IVQMX1EREKIQIRX7]WXIQ .(  0SFF]5YIYMRK7]WXIQ6ITPEGIQIRXW .(  3RPMRI&MPP4E]QIRXERH4VIWIRXQIRX7]WXIQ .&  4E]VSPP7]WXIQ6ITPEGIQIRX .&  6MWO1EREKIQIRX7]WXIQ .*   7GSXXWHEPI:MHIS2IX[SVO8IPIGEWX4VSHYGXMSR:MHIS  7XVIEQMRKERH/MZE4VIWIRXEXMSR)UYMTQIRX =* 6IGYVVMRK'ETMXEP1EMRXIRERGI4VSNIGXW *SVIGEWX  *SVIGEWX  *SVIGEWX  *SVIGEWX  8SXEP 4EKI                                                                                              City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 99 -                                                          Table of Contents 4VSNIGX(IWGVMTXMSRW SERVICE FACILITIES -RXLSYWERHWSJHSPPEVW 4VSNIGX 7IVZMGI*EGMPMXMIW 8IGLRSPSK]-QTVSZIQIRXW  7GSXXWHEPI:MHIS2IX[SVO8IPIGEWX4VSHYGXMSR:MHIS 7XVIEQMRKERH/MZE4VIWIRXEXMSR)UYMTQIRX =+ 7SPMH;EWXI:ILMGPI1SRMXSVMRK7]WXIQ .& 7XVIIX3TIVEXMSRW;SVOERH%WWIX1EREKIQIRX 7]WXIQ .& 9XMPMX]&MPPMRK1EREKIQIRX7]WXIQ 8)14* 6IGYVVMRK'ETMXEP1EMRXIRERGI4VSNIGXW %HSTXIH  *SVIGEWX  *SVIGEWX  *SVIGEWX  *SVIGEWX  8SXEP 4EKI                             City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 100 - Table of Contents SERVICE COMMUNITY FACILITIES FACILITIES | Municipal | Library/Library Facilities/Improvements Improvements Municipal Facilities/Improvements Additional Compressed Natural Gas (CNG) Station - (BC01) Est. Completion: 06/20 Solid Waste Transfer Station Location: Project Type: Construction Related Description: Build a Compressed Natural Gas (CNG) fueling station to support the growing number of CNG powered solid waste refuse trucks. The city has fiftynine vehicles with CNG powered engines in its fleet that are currently serviced by only one compression station located at the city’s North Corporate Yard. Funding Sources (In thousands of dollars) Fleet Rates Sanitation Rates Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 765.0 1,875.0 2,640.0 (585.5) (904.4) (1,489.9) 179.5 970.6 1,150.1 - - - - 179.5 970.6 1,150.1 City Court Customer Service Counters and Lobby Remodel - (BE01) Est. Completion: 06/20 City Court Location: Project Type: Construction Related Description: Design and remodel the City Court’s customer service counters and lobby areas. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Design/Construction Admin Total: Funding Sources (In thousands of dollars) Court Enhancement Funds Total: 11.0 264.0 23.5 298.5 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 298.5 298.5 (20.9) (20.9) 277.6 277.6 - - - - 277.6 277.6  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 101 - Table of Contents SERVICE COMMUNITY FACILITIES FACILITIES | Municipal | Library/Library Facilities/Improvements Improvements Municipal Facilities/Improvements Courthouse Improvements - Architectural Services - (BF01) Est. Completion: 06/20 City Court Location: Project Type: Construction Related Description: Develop a courthouse improvements strategic plan and develop design for a future building modification and construction project. The work will be completed by an architectural firm that has courthouse design/construction/consulting experience. This firm will work closely with the court’s courthouse improvement team. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Design/Construction Admin Total: Funding Sources (In thousands of dollars) Court Enhancement Funds Total: 5.0 165.0 170.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 170.0 170.0 (89.1) (89.1) 80.9 80.9 - - - - 80.9 80.9 Expansion of Existing Parking Garages - (DF02) Est. Completion: 06/20 Location: Northwest corner of 2nd Street and Brown Avenue and west of Scottsdale Road, north of 3rd Avenue Project Type: Construction Related Description: Study the potential expansion of two existing parking structures in the downtown area. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Design/Construction Admin Total: Funding Sources (In thousands of dollars) In-Lieu Parking Total: 81.1 81.1 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 81.1 81.1 - 81.1 81.1 - - - - 81.1 81.1  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 102 - Table of Contents SERVICE COMMUNITY FACILITIES FACILITIES | Municipal | Library/Library Facilities/Improvements Improvements Municipal Facilities/Improvements Facilities Repair and Maintenance Program - (YF01) Est. Completion: N/A Citywide Location: Project Type: Construction Related Description: Repair and replace equipment and facilities that serve the community including air conditioning and ventilation systems, lighting and plumbing, roofs, foundations, pathways and other structural elements. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Contingency Design/Construction Admin Machinery and Equipment Total: Funding Sources (In thousands of dollars) General Fund Total: 145.7 1,295.7 242.8 91.2 873.3 2,648.7 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 2,648.7 2,648.7 (2,121.9) (2,121.9) 526.8 526.8 - - - - 526.8 526.8 Facilities Repair and Maintenance Program - (YG01) Est. Completion: N/A Citywide Location: Project Type: Construction Related Description: Repair and replace equipment and facilities that serve the community including air conditioning and ventilation systems, lighting and plumbing, roofs, foundations, pathways and other structural elements. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Contingency Design/Construction Admin Machinery and Equipment Total: Funding Sources (In thousands of dollars) General Fund Total: 510.7 3,098.8 849.0 1,259.6 7,048.4 12,766.5 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 12,766.5 12,766.5 - 2,549.0 2,549.0 2,502.5 2,502.5 2,550.0 2,550.0 2,560.0 2,560.0 2,605.0 2,605.0 12,766.5 12,766.5  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 103 - Table of Contents SERVICE COMMUNITY FACILITIES FACILITIES | Municipal | Library/Library Facilities/Improvements Improvements Municipal Facilities/Improvements Fleet Fuel Site Upgrade - (BE03) Est. Completion: 06/20 North Corporate Yard and Public Safety - Police District 3 Location: Project Type: Construction Related Description: Investigate, design and construct replacements for up to five existing underground storage tanks. These tanks are used to fuel a large portion of the city's vehicle fleet. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Contingency Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) Fleet Rates Total: 194.0 2,068.8 404.1 363.7 97.0 3,127.4 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 3,127.4 3,127.4 (1,029.3) (1,029.3) 2,098.1 2,098.1 - - - - 2,098.1 2,098.1  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 104 - Table of Contents SERVICE COMMUNITY FACILITIES FACILITIES | Municipal | Library/Library Facilities/Improvements Improvements Municipal Facilities/Improvements Fleet South Corporate Yard Compressed Natural Gas Compliance - (BG02) Est. Completion: 12/21 South Corporate Yard Location: Project Type: Construction Related Description: Modify Building F to comply with current building codes for the service and maintenance of Compressed Natural Gas (CNG) vehicles. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Design/Construction Admin Total: Funding Sources (In thousands of dollars) Fleet Rates Total: 45.5 1,000.0 154.5 1,200.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 1,200.0 1,200.0 - 1,200.0 1,200.0 - - - - 1,200.0 1,200.0  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 105 - Table of Contents SERVICE COMMUNITY FACILITIES FACILITIES | Municipal | Library/Library Facilities/Improvements Improvements Municipal Facilities/Improvements North Corp Yard CNG Compliance - (BB53) Est. Completion: 06/20 North Corporate Yard Location: Project Type: Construction Related Description: Bring the city's fleet shop into compliance with current building codes for the service and maintenance of Compressed Natural Gas (CNG) vehicles. Funding Sources (In thousands of dollars) Fleet Rates Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 1,358.4 1,358.4 (62.1) (62.1) 1,296.4 1,296.4 - - - - 1,296.4 1,296.4 Solid Waste Upgrades and Improvements Program - (BG01) Est. Completion: N/A Solid Waste Transfer Station Location: Project Type: Construction Related Description: Protect the city’s solid waste infrastructure through the systematic and rational upgrade or replacement of specialized structures and machinery supporting Solid Waste Service. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Contingency Design/Construction Admin Machinery and Equipment Total: Funding Sources (In thousands of dollars) Sanitation Rates Total: 8.7 39.6 17.4 22.0 129.8 217.5 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 217.5 217.5 - 217.5 217.5 - - - - 217.5 217.5  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 106 - Table of Contents Capital Improvement Plan CAPITAL IMPROVEMENT SERVICE FACILITIES PLAN - PROJECT | Technology LIST |Financial Alphabetical Financial Summary & Five YearImprovements Forecast Technology Improvements CIP Contingency - (ZB50) Est. Completion: N/A Citywide Location: Project Type: Construction Related Description: Provide budgetary appropriation set aside for citywide emergencies or unforeseen expenditures not otherwise budgeted. Funding Sources (In thousands of dollars) General Fund Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 45,000.0 45,000.0 - 25,000.0 25,000.0 5,000.0 5,000.0 5,000.0 5,000.0 5,000.0 5,000.0 5,000.0 5,000.0 45,000.0 45,000.0 CIP Contingency for Future Grants - (ZB51) Est. Completion: N/A Citywide Location: Project Type: Construction Related Description: Provide budgetary appropriation set aside for citywide unforeseen grants not otherwise budgeted. Funding Sources (In thousands of dollars) Grants Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 25,000.0 25,000.0 - 5,000.0 5,000.0 5,000.0 5,000.0 5,000.0 5,000.0 5,000.0 5,000.0 5,000.0 5,000.0 25,000.0 25,000.0 Data Center Resiliency Plan - (JD01) Est. Completion: 12/19 Citywide Location: Project Type: Technology Related Description: Plan for the catastrophic loss of the city's primary data center as well as other divisional data centers. Establish a new data center with a third-party provider. The new data center will be leveraged to provide a resilient diverse option for each of the existing data centers. Provide the hardware and software required to establish service at the new data center. Modify the existing city primary data center to integrate with the new data center. Funding Sources (In thousands of dollars) General Fund Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 4,900.0 4,900.0 (4,161.4) (4,161.4) 738.6 738.6 - - - - 738.6 738.6  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 107 - Table of Contents Capital Improvement Plan CAPITAL IMPROVEMENT SERVICE FACILITIES PLAN - PROJECT | Technology LIST |Financial Alphabetical Financial Summary & Five YearImprovements Forecast Technology Improvements Enterprise Resource Planning System - (TEMP1833-F) Est. Completion: 06/22 Citywide Location: Project Type: Technology Related Description: Replace outdated enterprise resource planning system to enable the effective administration of the city's financial, purchasing, and warehouse systems. The system that has managed the general ledger, fixed assets, budget, capital projects, accounts receivable, accounts payable, purchasing, requisitions, and supplies (warehouse) no longer meets the needs of the city. A new system will streamline overall financial operations and allow the city to continue to operate effectively in meeting the various local, state, and federal mandates. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Contingency Information Technology Total: Funding Sources (In thousands of dollars) General Fund Total: 88.0 400.0 4,000.0 4,488.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 4,488.0 4,488.0 - - - 4,488.0 4,488.0 - - 4,488.0 4,488.0 Irrigation Control System - (PF01) Est. Completion: 06/21 Citywide Location: Project Type: Technology Related Description: Complete lifecycle replacement of the irrigation control system for all city parks and rights-of-way to control daily water usage, to meet watering industry standards for safe and aesthetic turf and vegetation and to comply with the state water consumption requirements. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Information Technology Total: Funding Sources (In thousands of dollars) General Fund Total: 65.2 1,303.7 1,368.9 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 1,368.9 1,368.9 (1,225.9) (1,225.9) 143.0 143.0 - - - - 143.0 143.0  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 108 - Service Facilities Technology Improvements Irrigation Control System - (PF01) Est. Completion: 06/21 Location: Citywide Project Type: Description: Technology Related Lifecycle replacement of the irrigation control system for all city parks and right-of-ways to control daily water usage, meet watering industry standards for safe and aesthetic turf and vegetation and to comply with the state water consumption requirements. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs 65.2 Information Technology 1,303.7 Total: 1,368.9 Funding Sources (In thousands of dollars) Total ITD Project Expenditures Cost (Thru 06/18) General Fund 1,368.9 Total: 1,368.9 FY 2018/19 Budget - 1,368.9 - 1,368.9 FY 2019/20 Forecast - FY 2020/21 Forecast - FY 2021/22 Forecast FY 2022/23 Forecast - - - Total Remaining Budget 1,368.9 - 1,368.9 FY 2022/23 Forecast Total Remaining Budget IT - Network Infrastructure - (YE07)  Est. Completion: N/A Location: Citywide Project Type: Description: Planned systematic upgrade and ongoing replacement of the city’s computer network infrastructure. Technology Related Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs 31.5 Information Technology 350.0 Total: 381.5 Funding Sources (In thousands of dollars) Total ITD Project Expenditures Cost (Thru 06/18) General Fund 314.5 Aviation Funds 1.8 CDBG 2.0 Fleet Rates 4.1 Sanitation Rates 5.5 Self Insurance 1.2 Sewer Rates 9.9 Transportation 0.2% Sales Tax 12.9 Water Rates Total: (117.1) - FY 2018/19 Budget 197.4 1.8 FY 2019/20 Forecast - FY 2020/21 Forecast - FY 2021/22 Forecast - - 2.0 - - - - 4.1 - - - - 5.5 1.2 9.9 12.9 - - - - 197.4 1.8 2.0 4.1 5.5 1.2 9.9 12.9 29.8 (13.7) 16.0 - - - - 16.0 381.5 (130.8) 250.7 - - - - 250.7  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. Table of Contents Capital Improvement Plan CAPITAL IMPROVEMENT SERVICE FACILITIES PLAN - PROJECT | Technology LIST |Financial Alphabetical Financial Summary & Five YearImprovements Forecast Technology Improvements IT - Network Infrastructure - (YG07) Est. Completion: N/A Citywide Location: Project Type: Technology Related Description: Upgrade and replace computer network hardware including routers, cabling, firewalls, security appliances and other components that comprise the electronic backbone of city services. The city’s computer networks are used continuously and support the full array of city operations. These components are on a seven-year lifecycle replacement that accounts for routine wear and tear and constantly evolving business needs and service demands (the industry average varies with different types of equipment, but the average life of network equipment is seven years). The replacement list is reviewed and updated annually to reflect the functionality of the current equipment, business needs and changes in technology. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Information Technology Total: Funding Sources (In thousands of dollars) General Fund Aviation Funds CDBG Fleet Rates Sanitation Rates Self Insurance Sewer Rates Transportation 0.2% Sales Tax Water Rates Total: 138.4 3,460.0 3,598.4 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 2,971.2 17.5 15.4 43.3 45.3 10.3 96.8 131.8 266.7 3,598.4 - 429.4 2.5 2.2 6.3 6.5 1.5 14.0 19.1 38.5 520.0 528.1 3.1 2.7 7.7 8.1 1.8 17.2 23.4 47.4 639.6 1,094.9 6.5 5.7 15.9 16.7 3.8 35.7 48.6 98.3 1,326.0 446.5 2.6 2.3 6.5 6.8 1.5 14.5 19.8 40.1 540.8 472.3 2.8 2.5 6.9 7.2 1.6 15.4 21.0 42.4 572.0 2,971.2 17.5 15.4 43.3 45.3 10.3 96.8 131.8 266.7 3,598.4  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 109 - Table of Contents Capital Improvement Plan CAPITAL IMPROVEMENT SERVICE FACILITIES PLAN - PROJECT | Technology LIST |Financial Alphabetical Financial Summary & Five YearImprovements Forecast Technology Improvements IT - Network Infrastructure - (YF07) Est. Completion: N/A Citywide Location: Project Type: Technology Related Description: Upgrade and replace computer network hardware including routers, cabling, firewalls, security appliances and other components that comprise the electronic backbone of city services. The city’s computer networks are used continuously and support the full array of city operations. These components are on a seven-year lifecycle replacement that accounts for routine wear and tear and constantly evolving business needs and service demands (the industry average varies with different types of equipment, but the average life of network equipment is seven years). The replacement list is reviewed and updated annually to reflect the functionality of the current equipment, business needs and changes in technology. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Information Technology Total: Funding Sources (In thousands of dollars) General Fund Aviation Funds CDBG Fleet Rates Sanitation Rates Self Insurance Sewer Rates Transportation 0.2% Sales Tax Water Rates Total: 34.7 385.0 419.7 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 345.9 1.9 2.2 4.5 6.0 1.3 10.9 14.1 32.8 419.7 (116.3) (3.8) (4.4) (10.1) (0.3) (0.8) (135.7) 229.6 1.9 2.2 0.7 1.6 1.3 0.8 13.8 32.0 284.0 - - - - 229.6 1.9 2.2 0.7 1.6 1.3 0.8 13.8 32.0 284.0  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 110 - Table of Contents Capital Improvement Plan CAPITAL IMPROVEMENT SERVICE FACILITIES PLAN - PROJECT | Technology LIST |Financial Alphabetical Financial Summary & Five YearImprovements Forecast Technology Improvements IT - Server Infrastructure - (YF08) Est. Completion: N/A Citywide Location: Project Type: Technology Related Description: Upgrade and replace computer servers and related infrastructure as these systems reach the end of their service life. These critical systems host applications and data supporting both public and internal services and business processes such as public safety dispatch systems, the city’s website and the online utility billing and payment portal. This hardware is on a five-year replacement lifecycle (the industry average for server equipment is three to five years). The replacement list is reviewed and updated annually to reflect the latest business needs and changes in technology. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Information Technology Total: Funding Sources (In thousands of dollars) General Fund Aviation Funds CDBG Fleet Rates Sanitation Rates Self Insurance Sewer Rates Transportation 0.2% Sales Tax Water Rates Total: 34.3 858.5 892.8 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 560.0 8.7 9.9 20.2 27.4 6.0 49.2 63.7 147.8 892.8 (75.9) (8.7) (9.9) (20.2) (27.4) (6.0) (49.2) (63.7) (147.8) (408.7) 484.1 484.1 - - - - 484.1 484.1  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 111 - Table of Contents Capital Improvement Plan CAPITAL IMPROVEMENT SERVICE FACILITIES PLAN - PROJECT | Technology LIST |Financial Alphabetical Financial Summary & Five YearImprovements Forecast Technology Improvements IT - Server Infrastructure - (YG08) Est. Completion: N/A Citywide Location: Project Type: Technology Related Description: Upgrade and replace computer servers and related infrastructure as these systems reach the end of their service life. These critical systems host applications and data supporting both public and internal services and business processes such as public safety dispatch systems, the city’s website and the online utility billing and payment portal. This hardware is on a five-year replacement lifecycle (the industry average for server equipment is three to five years). The replacement list is reviewed and updated annually to reflect the latest business needs and changes in technology. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Information Technology Total: Funding Sources (In thousands of dollars) General Fund Aviation Funds CDBG Fleet Rates Sanitation Rates Self Insurance Sewer Rates Transportation 0.2% Sales Tax Water Rates Total: 292.8 7,321.2 7,614.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 6,286.9 37.3 32.7 91.4 95.9 22.1 204.8 278.7 564.2 7,614.0 - 812.4 4.8 4.2 11.8 12.4 2.9 26.5 36.0 72.9 983.8 488.1 2.9 2.5 7.1 7.4 1.7 15.9 21.6 43.8 591.2 462.7 2.7 2.4 6.7 7.1 1.6 15.1 20.5 41.5 560.4 1,464.1 8.7 7.6 21.3 22.3 5.1 47.7 64.9 131.4 1,773.1 3,059.6 18.2 15.9 44.5 46.7 10.7 99.7 135.6 274.6 3,705.5 6,286.9 37.3 32.7 91.4 95.9 22.1 204.8 278.7 564.2 7,614.0 License and Permit Management System - (JD04) Est. Completion: 06/20 Citywide Location: Project Type: Technology Related Description: Implement a new, modern license and permit management system to enable the administration of over 30,000 regulatory license and permit holders and collection of over $3 million annually. Funding Sources (In thousands of dollars) General Fund Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 472.5 472.5 (205.9) (205.9) 266.6 266.6 - - - - 266.6 266.6  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 112 - Table of Contents Capital Improvement Plan CAPITAL IMPROVEMENT SERVICE FACILITIES PLAN - PROJECT | Technology LIST |Financial Alphabetical Financial Summary & Five YearImprovements Forecast Technology Improvements Lobby Queuing System Replacements - (JD03) Est. Completion: 06/20 City Court Location: Project Type: Technology Related Description: Provide an efficient and effective way to manage lobby flow and provide performance metrics to assist with staff resourcing. The new system assigns service call numbers to patrons of the court and prioritizes waiting periods. Funding Sources (In thousands of dollars) Court Enhancement Funds Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 84.0 84.0 (48.1) (48.1) 35.9 35.9 - - - - 35.9 35.9 Online Bill Payment and Presentment System - (JB65) Est. Completion: 06/20 Citywide Location: Project Type: Technology Related Description: Implement a new and modern online payment and presentment platform to enable the collection of over one million water, sewer and solid waste payments annually. Funding Sources (In thousands of dollars) Sanitation Rates Sewer Rates Water Rates Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 126.5 126.5 128.5 381.5 (61.6) (5.9) (95.6) (163.2) 64.9 120.6 32.9 218.3 - - - - 64.9 120.6 32.9 218.3  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 113 - Table of Contents Capital Improvement Plan CAPITAL IMPROVEMENT SERVICE FACILITIES PLAN - PROJECT | Technology LIST |Financial Alphabetical Financial Summary & Five YearImprovements Forecast Technology Improvements Payroll System Replacement - (JB59) Est. Completion: 06/20 Citywide Location: Project Type: Technology Related Description: Implement a fully integrated Payroll and Human Resources Information System to enable a cost-effective, citywide resource which will reduce redundancy and human error, while increasing organizational efficiency. Funding Sources (In thousands of dollars) General Fund Aviation Funds CDBG Court Enhancement Funds Fleet Rates Forensic Science IGAs McCormick RailRoad Park RICO Sanitation Rates Section 8 Self Insurance Sewer Rates Transportation 0.2% Sales Tax Water Rates Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 469.7 5.1 1.5 4.4 17.0 0.5 4.6 248.2 33.4 2.8 2.8 11.8 30.3 67.6 899.7 (317.7) (5.1) (1.5) (4.4) (17.0) (0.5) (4.6) (248.2) (33.4) (2.8) (2.8) (11.8) (30.3) (67.6) (747.7) 152.0 152.0 - - - - 152.0 152.0 Risk Management System - (JF02) Est. Completion: 06/20 Citywide Location: Project Type: Technology Related Description: Implement a new, modern risk management platform to effectively manage our liability and workmen’s compensation claims. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Contingency Information Technology Total: Funding Sources (In thousands of dollars) Self Insurance Total: 27.5 50.0 500.0 577.5 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 577.5 577.5 - 577.5 577.5 - - - - 577.5 577.5  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 114 - Table of Contents Capital Improvement Plan CAPITAL IMPROVEMENT SERVICE FACILITIES PLAN - PROJECT | Technology LIST |Financial Alphabetical Financial Summary & Five YearImprovements Forecast Technology Improvements Scottsdale Video Network Telecast/Production/Video Streaming and Kiva Presentation Equipment - (YG04) Est. Completion: N/A Citywide Location: Project Type: Technology Related Description: Replace audio, visual and television broadcast equipment in City Hall and the Scottsdale video production studio that support recording and televising public meetings of the City Council and citizen board and commissions, and video productions to help residents stay informed about city priorities, projects, programs and services. Telecast equipment has an average lifespan of five to ten years, and equipment in the Kiva meeting space at City Hall (such as the video projector) is used far more often than similar equipment. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Machinery and Equipment Total: Funding Sources (In thousands of dollars) General Fund Total: 18.8 469.0 487.8 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 487.8 487.8 - 44.7 44.7 114.4 114.4 135.2 135.2 131.0 131.0 62.4 62.4 487.8 487.8 Scottsdale Video Network Telecast/Production/Video Streaming and Kiva Presentation Equipment - (YF04) Est. Completion: N/A Citywide Location: Project Type: Technology Related Description: Replace audio, visual and television broadcast equipment in City Hall and the Scottsdale video production studio that support recording and televising public meetings of the City Council and citizen board and commissions, and video productions to help residents stay informed about city priorities, projects, programs and services. Telecast equipment has an average lifespan of five to ten years, and equipment in the Kiva meeting space at City Hall (such as the video projector) is used far more often than similar equipment. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Machinery and Equipment Total: Funding Sources (In thousands of dollars) General Fund Total: 6.1 68.0 74.1 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 74.1 74.1 (34.8) (34.8) 39.3 39.3 - - - - 39.3 39.3  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 115 - Table of Contents Capital Improvement Plan CAPITAL IMPROVEMENT SERVICE FACILITIES PLAN - PROJECT | Technology LIST |Financial Alphabetical Financial Summary & Five YearImprovements Forecast Technology Improvements Solid Waste Vehicle Monitoring System - (JB66) Est. Completion: 06/20 Citywide Location: Project Type: Technology Related Description: Purchase and replace existing vehicle monitoring system hardware for the solid waste vehicle fleet that will provide vehicle maintenance and operations monitoring. The applications will assist in increasing the productivity and efficiency of Solid Waste operations. Funding Sources (In thousands of dollars) Sanitation Rates Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 1,082.5 1,082.5 (625.0) (625.0) 457.5 457.5 - - - - 457.5 457.5 Street Operations Work and Asset Management System - (JB56) Est. Completion: 12/19 Citywide Location: Project Type: Technology Related Description: Purchase and integrate a software package to provide asset and work management capabilities for all the maintenance work falling under the jurisdiction of the Street Operations department. This includes work and assets relating to shoulders and drainage, pavement management, signs and markings, traffic signals, streetlights and street cleaning. Funding Sources (In thousands of dollars) Transportation 0.2% Sales Tax Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 168.0 168.0 (135.4) (135.4) 32.6 32.6 - - - - 32.6 32.6  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 116 - Table of Contents Capital Improvement Plan CAPITAL IMPROVEMENT SERVICE FACILITIES PLAN - PROJECT | Technology LIST |Financial Alphabetical Financial Summary & Five YearImprovements Forecast Technology Improvements Utility Billing Management System - (TEMP2119-F) Est. Completion: 01/24 Citywide Location: Project Type: Technology Related Description: Implement a new, modern utility billing system to enable the administration of over 100,000 utility accounts managing $120 million annually. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Contingency Information Technology Total: Funding Sources (In thousands of dollars) Sanitation Rates Sewer Rates Water Rates Total: 180.0 450.0 4,500.0 5,130.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 180.0 450.0 4,500.0 5,130.0 - - - - 180.0 450.0 4,500.0 5,130.0 - 180.0 450.0 4,500.0 5,130.0  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 117 - FY 2019/20 Adopted Budget City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 118 - Table of Contents 4VSNIGX(IWGVMTXMSRW TRANSPORTATION -RXLSYWERHWSJHSPPEVW 8VERWTSVXEXMSR 8VERWTSVXEXMSRTVSKVEQWJSGYWSRTVSZMHMRKJSVXLIWEJIIJJMGMIRXERHEJJSVHEFPIQSZIQIRXSJTISTPIERHKSSHW8LMW TVSKVEQQIIXWXLMWKSEPF]EXXIQTXMRKXSSJJIVVIEPXVERWTSVXEXMSRGLSMGIWMRE[E]XLEXQIIXWXLIRIIHWSJXLIGSQQYRMX]-R ZSXIVWEYXLSVM^IHETIVGIRXTVMZMPIKIXE\XSJYRHXVERWTSVXEXMSRSTIVEXMSRWERHMQTVSZIQIRXW-RZSXIVWETTVSZIH E]IEVI\XIRWMSRSJELEPJGIRXXVERWTSVXEXMSRWEPIWXE\MR1EVMGSTE'SYRX]XLEX[EWJMVWXETTVSZIHMRXSJYRHJVII[E] GSRWXVYGXMSR8LMWTVSKVEQPSSOWJSVXLIFIWXYWISJXLIWIJYRHMRKWSYVGIWERHEHHVIWWIWXLIQYPXMQSHEPGSRGITX-R ZSXIVWETTVSZIHETVIGIRXTVMZMPIKIXE\JSVETIVMSHSJXIR]IEVWJSVXVERWTSVXEXMSRMQTVSZIQIRXTVSNIGXW%TTVS\MQEXIP] TIVGIRX QMPPMSR SJXLI'-4LEWFIIRMHIRXMJMIHXSEHHVIWWXLIXVERWTSVXEXMSRRIIHWSJXLIGMX] 4VSNIGX 8VERWTSVXEXMSR %ZMEXMSR%ZMEXMSR-QTVSZIQIRXW %MVTSVX*YXYVI+VERXW'SRXMRKIRG] >& %MVTSVX1EWXIV4PER9THEXI 8)14 %MVTSVX1SRYQIRX7MKR %+ %MVTSVX4EZIQIRX4VIWIVZEXMSR4VSKVEQ %& %MVTSVX7IGYVMX]*IRGMRK-QTVSZIQIRXW %+ %MVTSVX8IVQMREP%VIE6IHIZIPSTQIRX4VSNIGX %& %TVSR6IGSRWXVYGXMSR(IPXE%TVSR %' %ZMEXMSR1EXGL'SRXMRKIRG] >& 'IMPMRK-QTVSZIQIRXWEX%MVTSVX347&YMPHMRK %+ (IPXE%TVSR-QTVSZIQIRXW4LEWI-- %+ (IWMKR'SRWXVYGX2SVXL+IRIVEP%ZMEXMSR&S\ ,ERKEVW %* )RZMVSRQIRXEP%WWIWWQIRXJSV0ERH%GUYMWMXMSR 8)14%&* )\MX8E\M[E]W&&ERH& 8)14* /MPS6EQT6ILEFMPMXEXMSR %+ 0ERH%GUYMWMXMSR%GVIW 8)14* 4IVMQIXIV7IVZMGI6SEH6ILEFMPMXEXMSR %+ 6IGSRWXVYGX8E\M[E]%ERH)\MXW %& 6ILEFMPMXEXI6YR[E] %& 6ILEFMPMXEXI8E\M[E]' %+ 6YR[E]6ILEFMPMXEXMSR6IGSRWXVYGXMSR 'SRWXVYGXMSR 8)14 6YR[E]6ILEFMPMXEXMSR6IGSRWXVYGXMSR(IWMKR %+ 6YR[E]+YEVH0MKLXW %) ;MPHPMJI,E^EVH1EREKIQIRX4PER 8)14* 7XVIIXW7XVIIX-QTVSZIQIRXW XL7XVIIX-RHMER7GLSSP6SEHXS8LSQEW6SEH 7+ 6IGYVVMRK'ETMXEP1EMRXIRERGI4VSNIGXW %HSTXIH  *SVIGEWX  *SVIGEWX  *SVIGEWX  *SVIGEWX                                                                                                                                              8SXEP 4EKI                             City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 119 - Table of Contents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ity of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 120 -                          Table of Contents 4VSNIGX(IWGVMTXMSRW TRANSPORTATION -RXLSYWERHWSJHSPPEVW 4VSNIGX 8VERWTSVXEXMSR 7XVIIXW7XVIIX-QTVSZIQIRXW 7GSXXWHEPI6SEH.SQE\6SEHXS(M\MPIXE(VMZI 8)14 7GSXXWHEPI6SEH4MRREGPI4IEO4EVO[E]XS.SQE\ 6SEH 8)14* 7GSXXWHEPI6SEH8LSQTWSR4IEO4EVO[E]XS 4MRREGPI4IEO6SEH4LEWI-- 8)14* 7LIE&SYPIZEVH-RXIVWIGXMSRW%VM^SRE7XEXI6SYXI XSXL7XVIIX 8)14  7XVIIXPMKLX6ITPEGIQIRX =8)14 8LSQEW6SEHXL7XVIIXXSVH7XVIIX 7+ 8VERWTSVXEXMSR*YRH'SRXMRKIRG] >* 8VEJJMG8VEJJMG6IHYGXMSR ,E]HIR8LSQEW7EJIX]-QTVSZIQIRXW 8& -877MKREP7]WXIQ9TKVEHIW 8&  2IMKLFSVLSSH8VEJJMG1EREKIQIRX4VSKVEQ =+  6SEH[E]'ETEGMX] 7EJIX]-QTVSZIQIRXW =+  8VEJJMG7MKREP'SRWXVYGXMSR =*  8VEJJMG7MKREP'SRWXVYGXMSR =+ 8VERWMX8VERWMX-QTVSZIQIRXW XL7XVIIX&VMHKI6IGSRWXVYGXMSRSZIVXLI%VM^SRE 'EREP 8) %HZERGIH8VEJJMG7MKREP'SRXVSP'EFMRIXW4LEWI-- 8) %VM^SRE'EREP4EXL'LETEVVEPXS1G(SREPHXS-RHMER &IRH;EWL 8& %VM^SRE'EREP4EXL4YFPMG%VX4VSNIGX 8)  &MOI[E]W4VSKVEQ =+ (S[RXS[R1EMR7XVIIX7XVIIXWGETI 4IHIWXVMER -QTVSZIQIRXW () (VMRO[EXIV&VMHKI-RXIVMQ7XVYGXYVEP6ITEMVW 8) 0IKEG](VMZI,YEPETEM(VMZI'SRRIGXSV 8+ 1E]S&SYPIZEVH9RHIVTEWW 9RMSR,MPPW(VMZI %VM^SRE7XEXI6SYXIXSXL7XVIIX 8)14 1YWXERK8VERWMX4EWWIRKIV*EGMPMX] 8& 3PH8S[R4IHIWXVMER-QTVSZIQIRXW 8( 4MQE6SEH.SQE\6SEHXS(]REQMXI&SYPIZEVH 8)14 4MQE6SEH0EW4MIHVEWXS7XEKIGSEGL4EWW 8)14 6IGYVVMRK'ETMXEP1EMRXIRERGI4VSNIGXW %HSTXIH  *SVIGEWX  *SVIGEWX  *SVIGEWX  *SVIGEWX                                                                                                                                                     8SXEP 4EKI                                    City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 121 - Table of Contents 4VSNIGX(IWGVMTXMSRW TRANSPORTATION -RXLSYWERHWSJHSPPEVW 4VSNIGX 8VERWTSVXEXMSR 8VERWMX8VERWMX-QTVSZIQIRXW 7LIE9RHIVTEWW%GGIWWEXXL7XVIIX 8&  7MHI[EPO-QTVSZIQIRXW =+  8VEMP-QTVSZIQIRX4VSKVEQ =+ 8VERWMX6SYXI-QTVSZIQIRXW 8' 8VERWMX7XST-QTVSZIQIRXW 8' ;IWX;SVPH8VEMP'SRRIGXMSRW 8' 6IGYVVMRK'ETMXEP1EMRXIRERGI4VSNIGXW %HSTXIH  *SVIGEWX  *SVIGEWX  *SVIGEWX  *SVIGEWX  8SXEP 4EKI                                           City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 122 - Table of Contents COMMUNITY TRANSPORTATION FACILITIES | Aviation/Aviation | Library/Library Improvements Aviation/Aviation Improvements z Airport Future Grants Contingency - (ZB53) Est. Completion: N/A Scottsdale Airport Location: Project Type: Construction Related Description: Provide budgetary appropriation set aside for unforeseen aviation grants not otherwise budgeted. Funding Sources (In thousands of dollars) Grants Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 16,750.5 16,750.5 - 3,350.1 3,350.1 3,350.1 3,350.1 3,350.1 3,350.1 3,350.1 3,350.1 3,350.1 3,350.1 16,750.5 16,750.5 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 15.6 334.4 350.0 - - - - - 15.6 334.4 350.0 15.6 334.4 350.0 Airport Master Plan Update - (TEMP2274) Est. Completion: 06/24 Scottsdale Airport Location: Project Type: Construction Related Description: Update the Airport Master Plan (AMP). Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Contingency Total: Funding Sources (In thousands of dollars) Aviation Funds Grants Total: 2.5 345.0 2.5 350.0  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 123 - Table of Contents COMMUNITY TRANSPORTATION FACILITIES | Aviation/Aviation | Library/Library Improvements Aviation/Aviation Improvements Airport Monument Sign - (AG01) Est. Completion: 12/19 Scottsdale Airport Location: Project Type: Construction Related Description: Install a monument sign at the corner of Scottsdale Road and Butherus Drive. The sign will serve as a main entry into the airport, and provide a unique, identifiable characteristic of the airpark area and provide wayfinding signage to incoming visitors. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Design/Construction Admin Total: Funding Sources (In thousands of dollars) Aviation Funds Total: 2.5 55.0 2.5 60.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 60.0 60.0 - 60.0 60.0 - - - - 60.0 60.0 Airport Pavement Preservation Program - (AB52) Est. Completion: N/A Scottsdale Airport Location: Project Type: Construction Related Description: Perform pavement preservation for various paved areas at the Scottsdale Airport. Funding Sources (In thousands of dollars) Aviation Funds Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 1,313.0 1,313.0 (716.5) (716.5) 596.5 596.5 - - - - 596.5 596.5  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 124 - Table of Contents COMMUNITY TRANSPORTATION FACILITIES | Aviation/Aviation | Library/Library Improvements Aviation/Aviation Improvements Airport Security Fencing Improvements - (AG06) Est. Completion: 12/20 Scottsdale Airport Location: Project Type: Construction Related Description: Install 3,000 linear feet of existing airport security fencing, including the replacement of fencing panels as needed and upgrade vehicle and aircraft automated gates. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Contingency Design/Construction Admin Total: Funding Sources (In thousands of dollars) Aviation Funds Grants Total: 5.0 224.0 5.0 26.0 260.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 11.6 248.4 260.0 - 11.6 248.4 260.0 - - - - 11.6 248.4 260.0 Airport Terminal Area Redevelopment Project - (AB59) Est. Completion: 12/19 Scottsdale Airport Location: Project Type: Construction Related Description: Redevelop the Airport Terminal Building and Aviation Business Center to create a single and modern hangar, office facility and parking facility to accommodate existing and new tenants. Total Project Cost Funding Sources (In thousands of dollars) Aviation Funds MPC Bonds Tourism Development Funds Total: ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 2,460.4 (1,977.2) 24,844.3 (25,323.2) 412.5 (412.5) 27,717.2 (27,713.0) 483.2 (478.9) 4.2 - - - - 483.2 (478.9) 4.2  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 125 - Table of Contents COMMUNITY TRANSPORTATION FACILITIES | Aviation/Aviation | Library/Library Improvements Aviation/Aviation Improvements Apron Reconstruction - Delta Apron - (AC02) Est. Completion: 06/20 Scottsdale Airport Location: Project Type: Construction Related Description: Design and reconstruct the Delta aircraft parking apron that is necessary to meet Federal Aviation Administration (FAA) standards. The existing pavement has exceeded its 20-year life expectancy. Funding Sources (In thousands of dollars) Aviation Funds Grants Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 169.9 3,630.1 3,800.0 (113.1) (2,302.4) (2,415.6) 56.7 1,327.7 1,384.4 - - - - 56.7 1,327.7 1,384.4 Aviation Match Contingency - (ZB52) Est. Completion: N/A Scottsdale Airport Location: Project Type: Construction Related Description: Provide budget appropriation set aside for the city's matching portion of unforeseen grants not otherwise budgeted. Funding Sources (In thousands of dollars) Aviation Funds Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 1,250.0 1,250.0 - 250.0 250.0 250.0 250.0 250.0 250.0 250.0 250.0 250.0 250.0 1,250.0 1,250.0 Ceiling Improvements at Airport OPS Building - (AG07) Est. Completion: 12/20 Scottsdale Airport Location: Project Type: Construction Related Description: Repair or replace exterior panels as needed at the Airport Operations Building. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Contingency Total: Funding Sources (In thousands of dollars) Aviation Funds Total: 1.5 37.0 1.5 40.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 40.0 40.0 - 40.0 40.0 - - - - 40.0 40.0  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 126 - Table of Contents COMMUNITY TRANSPORTATION FACILITIES | Aviation/Aviation | Library/Library Improvements Aviation/Aviation Improvements Delta Apron Improvements Phase II - (AG03) Est. Completion: 06/20 Scottsdale Airport Location: Project Type: Construction Related Description: Rehabilitate and reconstruct Delta apron Phase II on the south end of the airport and restripe markings. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Contingency Design/Construction Admin Total: Funding Sources (In thousands of dollars) Aviation Funds Grants Total: 5.0 426.0 5.0 40.0 476.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 21.3 454.7 476.0 - 21.3 454.7 476.0 - - - - 21.3 454.7 476.0 Design/Construct North General Aviation Box Hangars - (AF01) Est. Completion: 12/20 Scottsdale Airport Location: Project Type: Construction Related Description: Design and construct up to 18 aircraft box hangars at the North Apron (Taxiway Kilo). Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Contingency Design/Construction Admin Total: Funding Sources (In thousands of dollars) Aviation Funds Total: 53.0 4,732.0 159.0 303.0 5,247.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 5,247.0 5,247.0 (65.8) (65.8) 5,181.2 5,181.2 - - - - 5,181.2 5,181.2  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 127 - Table of Contents COMMUNITY TRANSPORTATION FACILITIES | Aviation/Aviation | Library/Library Improvements Aviation/Aviation Improvements Environmental Assessment for Land Acquisition - (TEMPAB57-F) Est. Completion: 06/21 Scottsdale Airport Location: Project Type: Construction Related Description: Conduct an environmental assessment as a prerequisite to land acquisition surrounding the airport. This land will be used to accommodate future aviation needs and increase airport capacity. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Contingency Land/ROW Total: Funding Sources (In thousands of dollars) Aviation Funds Grants Total: 2.0 10.0 188.0 200.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 8.9 191.1 200.0 - - 8.9 191.1 200.0 - - - 8.9 191.1 200.0 Exit Taxiways B2, B9 and B15 - (TEMP2084-F) Est. Completion: 06/23 Scottsdale Airport Location: Project Type: Construction Related Description: Construct new exit taxiways (B2, B9 and B15) to improve efficiency of aircraft ground operations. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Contingency Design/Construction Admin Total: Funding Sources (In thousands of dollars) Aviation Funds Grants Total: 10.5 903.0 31.5 105.0 1,050.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 46.9 1,003.1 1,050.0 - - 4.7 100.3 105.0 42.2 902.8 945.0 - - 46.9 1,003.1 1,050.0  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 128 - Table of Contents COMMUNITY TRANSPORTATION FACILITIES | Aviation/Aviation | Library/Library Improvements Aviation/Aviation Improvements Kilo Ramp Rehabilitation - (AG02) Est. Completion: 12/20 Scottsdale Airport Location: Project Type: Construction Related Description: Design and construct pavement improvements on the north end of the airport where aircraft parking is located. That section of the airport is known as Kilo ramp. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Contingency Design/Construction Admin Total: Funding Sources (In thousands of dollars) Aviation Funds Grants Total: 5.0 986.0 10.0 100.0 1,101.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 49.2 1,051.8 1,101.0 - 49.2 1,051.8 1,101.0 - - - - 49.2 1,051.8 1,101.0 Land Acquisition 4.0 Acres - (TEMP1882-F) Est. Completion: 06/23 Scottsdale Airport Location: Project Type: Construction Related Description: Acquire approximately four acres of land for airport development on the north side of the property. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Contingency Land/ROW Total: Funding Sources (In thousands of dollars) Aviation Funds Grants Total: 190.0 285.0 9,025.0 9,500.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 424.7 9,075.4 9,500.0 - - - - 424.7 9,075.4 9,500.0 - 424.7 9,075.4 9,500.0  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 129 - Table of Contents COMMUNITY TRANSPORTATION FACILITIES | Aviation/Aviation | Library/Library Improvements Aviation/Aviation Improvements Perimeter Service Road Rehabilitation - (AG05) Est. Completion: 12/20 Scottsdale Airport Location: Project Type: Construction Related Description: Repair the asphalt pavement sections of the airport's existing perimeter service road. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Contingency Design/Construction Admin Total: Funding Sources (In thousands of dollars) Aviation Funds Grants Total: 5.0 380.0 5.0 20.0 410.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 18.3 391.7 410.0 - 18.3 391.7 410.0 - - - - 18.3 391.7 410.0 Reconstruct Taxiway "A" and Exits - (AB60) Est. Completion: 12/19 Scottsdale Airport Location: Project Type: Construction Related Description: Design and reconstruct Taxiway "Alpha" pavement and exits, which is necessary to meet Federal Aviation Administration (FAA) standards for the design aircraft. Also install light-emitting diode (LED) lighting and signage. Funding Sources (In thousands of dollars) Aviation Funds Grants Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 219.0 4,681.0 4,900.0 (228.8) (4,338.3) (4,567.1) (9.8) 342.6 332.9 - - - - (9.8) 342.6 332.9  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 130 - Table of Contents COMMUNITY TRANSPORTATION FACILITIES | Aviation/Aviation | Library/Library Improvements Aviation/Aviation Improvements Rehabilitate Runway 03/21 - (AB61) Est. Completion: 12/20 Scottsdale Airport Location: Project Type: Construction Related Description: Rehabilitate the airport's runway electrical systems and pavement areas to meet Federal Aviation Administration (FAA) standards. Project includes improving the runway shoulders and blast pads as well as installing lightemitting diode (LED) lighting and airfield signage. Funding Sources (In thousands of dollars) Aviation Funds Grants Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 104.8 1,535.2 1,640.0 (112.7) (77.0) (189.7) (7.9) 1,458.2 1,450.3 - - - - (7.9) 1,458.2 1,450.3 Rehabilitate Taxiway "C" - (AG08) Est. Completion: 06/21 Scottsdale Airport Location: Project Type: Construction Related Description: Design and reconstruct Taxiway "Charlie", which is necessary to meet the Federal Aviation Administration (FAA) standards. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Contingency Design/Construction Admin Total: Funding Sources (In thousands of dollars) Aviation Funds Grants Total: 5.0 225.0 5.0 25.0 260.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 11.6 248.4 260.0 - 11.6 248.4 260.0 - - - - 11.6 248.4 260.0  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 131 - Table of Contents COMMUNITY TRANSPORTATION FACILITIES | Aviation/Aviation | Library/Library Improvements Aviation/Aviation Improvements Runway 03/21 Rehabilitation/Reconstruction - Construction - (TEMP2273) Est. Completion: 06/21 Scottsdale Airport Location: Project Type: Construction Related Description: Begin construction phase of the pavement rehabilitation/reconstruction of Runway 03/21. The project includes restriping markings as well. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Contingency Design/Construction Admin Total: Funding Sources (In thousands of dollars) Aviation Funds Grants Total: 10.0 10,480.0 10.0 100.0 10,600.0 Total Project Cost ITD Expenditures (Thru 06/19) 473.8 10,126.2 10,600.0 - Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 473.8 - 10,126.2 - 10,600.0 - - - 473.8 10,126.2 10,600.0 Adopted 2019/20 Runway 03/21 Rehabilitation/Reconstruction - Design - (AG04) Est. Completion: 06/20 Scottsdale Airport Location: Project Type: Construction Related Description: Begin design phase of the pavement rehabilitation/reconstruction of Runway 03/21. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Contingency Design/Construction Admin Total: Funding Sources (In thousands of dollars) Aviation Funds Grants Total: 5.0 5.0 290.0 300.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 13.4 286.6 300.0 - 13.4 286.6 300.0 - - - - 13.4 286.6 300.0  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 132 - Table of Contents COMMUNITY TRANSPORTATION FACILITIES | Aviation/Aviation | Library/Library Improvements Aviation/Aviation Improvements Runway Guard Lights - (AE01) Est. Completion: 12/23 Scottsdale Airport Location: Project Type: Construction Related Description: Install guard lights at the runway hold position markings at entrances to the runway at Taxiways A3, A4, A5, A7, A10, A13, and A15 on the west side of the runway. Additionally, place guard lights at the extensions of Taxiways B10/C10 and B12 as an added safety measure on the east side of the runway. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Design/Construction Admin Total: Funding Sources (In thousands of dollars) Aviation Funds Grants Total: 10.0 1,620.0 370.0 2,000.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 89.4 1,910.6 2,000.0 - - - 8.0 172.0 180.0 81.4 1,738.6 1,820.0 - 89.4 1,910.6 2,000.0 Wildlife Hazard Management Plan - (TEMP2085-F) Est. Completion: 06/24 Scottsdale Airport Location: Project Type: Construction Related Description: Identify wildlife near the airport and develop mitigation actions to prevent the risk of wildlife strikes. The Federal Aviation Administration (FAA) requires airport sponsors to maintain a safe operating environment. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Design/Construction Admin Total: Funding Sources (In thousands of dollars) Aviation Funds Grants Total: 5.0 95.0 100.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 4.5 95.5 100.0 - - - - - 4.5 95.5 100.0 4.5 95.5 100.0  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 133 - Table of Contents TRANSPORTATION | Streets/Street Improvements Streets/Street Improvements 68th Street: Indian School Road to Thomas Road - (SG02) Est. Completion: 12/21 68th Street: Indian School Road to Thomas Road Location: Project Type: Construction Related Description: Design and construct left turn bays, bike lanes, pedestrian improvements and complete the street including intersection improvements at Osborn Road. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Design/Construction Admin Total: Funding Sources (In thousands of dollars) Grants Transportation 0.2% Sales Tax Total: 36.3 681.9 179.1 897.2 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 615.2 282.0 897.2 - 186.9 186.9 615.2 95.0 710.3 - - - 615.2 282.0 897.2  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 134 - Table of Contents TRANSPORTATION | Streets/Street Improvements Streets/Street Improvements ADA Transition Plan Implementation - (SF03) Est. Completion: 12/24 Citywide Location: Project Type: Construction Related Description: Implement Americans with Disabilities Act (ADA) improvements throughout Scottsdale that are not already being incorporated into large transportation projects. The ADA passed by the United States Congress in 1990, in part, requires that all public and private facilities accommodate persons with physical or mental impairments. These accommodations include infrastructure such as ramps at street intersections, shared-use path, sidewalk widths and slopes, and traffic signal pedestrian pushbuttons. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Contingency Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) Transportation 0.2% Sales Tax Total: 180.0 1,260.0 120.0 180.0 60.0 1,800.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 1,800.0 1,800.0 (325.2) (325.2) 274.8 274.8 300.0 300.0 300.0 300.0 300.0 300.0 300.0 300.0 1,474.8 1,474.8  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 135 - Table of Contents TRANSPORTATION | Streets/Street Improvements Streets/Street Improvements Carefree Highway: Cave Creek Road to Scottsdale Road - (TEMP1979) Est. Completion: 06/26 Carefree Highway: Cave Creek Road to Scottsdale Road Location: Project Type: Construction Related Description: Widen Carefree Highway from Cave Creek Road to Scottsdale Road into a four-lane roadway, including raised landscaped median, bike lanes and sidewalk. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Land/ROW Total: Funding Sources (In thousands of dollars) Regional Sales Tax - Arterial Life Cycle Program Transportation 0.1% Sales Tax 2019 Total: 582.0 9,826.6 4,142.5 14,551.1 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2023/24 Total Remaining Budget 10,186.4 - - - - - 10,186.4 10,186.4 4,364.7 14,551.1 - - - - - 4,364.7 - 14,551.1 4,364.7 14,551.1 Forecast 2022/23 Frank Lloyd Wright Boulevard at Arizona State Route 101 Traffic Interchange - (TEMP1967) Est. Completion: 12/25 Frank Lloyd Wright Boulevard at Arizona State Route 101 Traffic Interchange Location: Project Type: Construction Related Description: Redesign the Frank Lloyd Wright Boulevard intersection to improve safety and capacity including left turn and right turn bay modifications. Project will examine existing signal timing and phasing and consider modifications to improve efficiency. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Design/Construction Admin Land/ROW Total: Funding Sources (In thousands of dollars) Regional Sales Tax - Arterial Life Cycle Program Transportation 0.1% Sales Tax 2019 Total: 72.8 1,233.2 411.1 102.2 1,819.2 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 1,273.5 - - - - - 1,273.5 1,273.5 545.7 1,819.2 - - - - - 545.7 1,819.2 545.7 1,819.2  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 136 - Table of Contents TRANSPORTATION | Streets/Street Improvements Streets/Street Improvements Happy Valley Rd: Pima Rd to Alma School Rd - (SE02) Est. Completion: 06/20 Happy Valley Road: Pima Road to Alma School Road Location: Project Type: Construction Related Description: Widen Happy Valley Road from Pima Road to Alma School Road to two-lanes-per-direction with a raised median, bicycle lanes, and sidewalks to improve safety, capacity and accessibility safety for motor vehicles, bicycles, and pedestrians. A roundabout at the Alma School Road intersection is included. This segment of roadway is currently one lane in each direction with no center median. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs City Fees Construction Contingency Design/Construction Admin Land/ROW Salaries Total: Funding Sources (In thousands of dollars) In-Lieu Fees Transportation Regional Sales Tax - Arterial Life Cycle Program Transportation 0.2% Sales Tax Total: 205.0 112.4 14,487.6 1,319.9 600.0 1,100.0 146.4 17,971.3 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 275.0 - 275.0 - - - - 275.0 12,621.2 (386.2) 12,235.0 - - - - 12,235.0 5,075.1 17,971.3 (165.5) (551.7) 4,909.6 17,419.6 - - - - 4,909.6 17,419.6  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 137 - Table of Contents TRANSPORTATION | Streets/Street Improvements Streets/Street Improvements Hayden Road at Arizona State Route 101 Interchange Improvements - (TEMP1981) Est. Completion: 12/25 Hayden Road at Arizona State Route 101 Interchange Location: Project Type: Construction Related Description: Construct capacity and safety improvements at the Arizona State Route 101 and Hayden interchange. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Design/Construction Admin Land/ROW Total: Funding Sources (In thousands of dollars) Regional Sales Tax - Arterial Life Cycle Program Transportation 0.1% Sales Tax 2019 Total: 212.3 4,323.9 425.7 345.5 5,307.4 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 3,715.1 - - - - - 3,715.1 3,715.1 1,592.3 5,307.4 - - - - - 1,592.3 5,307.4 1,592.3 5,307.4 Indian Bend Wash Underpass at Chaparral Road - (SF01) Est. Completion: 06/20 Under Chaparral Road adjacent to and east of Hayden Road Location: Project Type: Construction Related Description: Design and construct an underpass for the Indian Bend Wash path under Chaparral Road east of Hayden Road. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Art in Public Places City Fees Construction Contingency Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) Grants Transportation 0.2% Sales Tax Total: 130.0 18.3 32.5 1,354.1 270.8 240.6 65.0 2,111.3 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 1,182.6 928.7 2,111.3 - 1,182.6 928.7 2,111.3 - - - - 1,182.6 928.7 2,111.3  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 138 - Table of Contents TRANSPORTATION | Streets/Street Improvements Streets/Street Improvements McDowell Road Bicycle Lanes from Pima Road to 64th Street - (SD01) Est. Completion: 06/20 McDowell Road from Pima Road to 64th Street Location: Project Type: Construction Related Description: Design and construct bicycle lanes to provide continuous bicycle lane facilities along entire corridor. The motor vehicle travel lanes and median on McDowell Road will be narrowed, but the number of lanes well remain the same at three per direction. Funding Sources (In thousands of dollars) Grants Transportation 0.2% Sales Tax Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 3,595.7 242.3 3,838.0 (443.2) (97.1) (540.3) 3,152.4 145.2 3,297.7 - - - - 3,152.4 145.2 3,297.7 Miller Road Underpass at Arizona State Route 101 - (SC03) Est. Completion: 12/20 Miller Road at Arizona State Route 101 Location: Project Type: Construction Related Description: Complete the City of Scottsdale's proportionate share of the design and construction of an underpass of Miller Road at Arizona State Route 101 to connect the south side of the freeway to the north. This street connection is identified on the Streets Plan in the Transportation Master Plan and is one of the regional Arterial Life Cycle Program projects. Funding Sources (In thousands of dollars) Regional Sales Tax - Arterial Life Cycle Program Transportation 0.2% Sales Tax Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 14,004.0 (3,123.4) 10,880.6 - - - - 10,880.6 4,401.7 18,405.7 (1,338.6) (4,462.0) 3,063.1 13,943.7 - - - - 3,063.1 13,943.7  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 139 - Table of Contents TRANSPORTATION | Streets/Street Improvements Streets/Street Improvements Osborn Road Complete Street: Hayden Road to Scottsdale Road - (SF02) Est. Completion: 06/20 Osborn Road from Hayden Road to Scottsdale Road Location: Project Type: Construction Related Description: Design and construct bicycle lanes and sidewalk segments along Osborn Road from Hayden Road to Scottsdale Road. This project includes an Indian Bend Wash path connection and a roundabout at Miller Road and Osborn Road. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Art in Public Places City Fees Construction Design/Construction Admin Land/ROW Salaries Total: Funding Sources (In thousands of dollars) Grants Transportation 0.2% Sales Tax Total: 162.6 23.3 40.6 2,031.9 300.3 47.1 81.3 2,687.1 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 1,214.5 1,472.6 2,687.1 (187.9) (187.9) 1,214.5 1,284.7 2,499.2 - - - - 1,214.5 1,284.7 2,499.2  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 140 - Table of Contents TRANSPORTATION | Streets/Street Improvements Streets/Street Improvements Pavement Overlay Program - (YF29) Est. Completion: N/A Citywide Location: Project Type: Construction Related Description: Complete ongoing street pavement overlays and all associated improvements, which may include milling and surface treatments on the existing roadway, traffic control, new pavement thickness, water valve and manhole lowering and raising, signal detection upgrades from loops to video, Americans with Disabilities Act (ADA) upgrades for concrete ramps and signal push buttons, concrete repairs to curbs and sidewalks, new striping plans, new thermo plastic striping and new signage for bike lanes and sidewalks. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Total: Funding Sources (In thousands of dollars) Transportation 0.2% Sales Tax Total: 849.3 5,700.7 6,550.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 6,550.0 6,550.0 (6,410.6) (6,410.6) 139.4 139.4 - - - - 139.4 139.4 Pavement Overlay Program - (YG29) Est. Completion: N/A Citywide Location: Project Type: Construction Related Description: Complete ongoing street pavement overlays and all associated improvements, which may include milling and surface treatments on the existing roadway, traffic control, new pavement thickness, water valve and manhole lowering and raising, signal detection upgrades from loops to video, Americans with Disabilities Act (ADA) upgrades for concrete ramps and signal push buttons, concrete repairs to curbs and sidewalks, new striping plans, new thermo plastic striping and new signage for bike lanes and sidewalks. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Total: Funding Sources (In thousands of dollars) Transportation 0.2% Sales Tax Total: 1,256.5 31,493.5 32,750.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 32,750.0 32,750.0 - 6,550.0 6,550.0 6,550.0 6,550.0 6,550.0 6,550.0 6,550.0 6,550.0 6,550.0 6,550.0 32,750.0 32,750.0  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 141 - Table of Contents TRANSPORTATION | Streets/Street Improvements Streets/Street Improvements Pavement Replacement - (TC06) Est. Completion: 06/19 Citywide Location: Project Type: Construction Related Description: Perform ongoing replacement of street pavement overlays and all associated improvements. Total Project Cost Funding Sources (In thousands of dollars) 2015 GO Bond - Q4 - Street Pavement Rehab Transportation 0.2% Sales Tax Total: ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 12,465.5 (12,015.6) 449.9 - - - - 449.9 1,595.0 (1,622.4) 14,060.5 (13,638.0) (27.4) 422.6 - - - - (27.4) 422.6  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 142 - Table of Contents TRANSPORTATION | Streets/Street Improvements Streets/Street Improvements Paving Unpaved Roads - (TEMP2296) Est. Completion: 06/22 128th Street and 132nd Street Location: Project Type: Construction Related Description: Pave unpaved roads to reduce production and emission of the particle pollution matter PM10, which is a mixture of solids and liquid droplets that are a major component of air pollution. PM10 air pollution threatens public health and the environment. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs City Fees Construction Contingency Design/Construction Admin Land/ROW Salaries Total: Funding Sources (In thousands of dollars) Grants Transportation 0.2% Sales Tax Total: 136.4 34.1 1,397.8 307.5 139.8 44.6 68.2 2,128.5 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 1,585.7 542.8 2,128.5 - - - 1,585.7 542.8 2,128.5 - - 1,585.7 542.8 2,128.5  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 143 - Table of Contents TRANSPORTATION | Streets/Street Improvements Streets/Street Improvements Pima Road: Chaparral Road to Thomas Road - (TEMP1965) Est. Completion: 12/25 Pima Road: Chaparral Road to Thomas Road Location: Project Type: Construction Related Description: Design and construct the ultimate minor arterial configuration of Pima Road including major intersections. This project will extend the Pima Road improvements between Chaparral Road and Thomas Road. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Design/Construction Admin Total: Funding Sources (In thousands of dollars) Regional Sales Tax - Arterial Life Cycle Program Salt River Pima Maricopa Indian Community IGA Transportation 0.1% Sales Tax 2019 Total: 401.3 8,869.5 762.0 10,032.8 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 7,023.0 - - - - - 7,023.0 7,023.0 1,805.9 - - - - - 1,805.9 1,805.9 1,203.9 10,032.8 - - - - - 1,203.9 - 10,032.8 1,203.9 10,032.8 Pima Road: Dynamite Boulevard to Las Piedras - (TEMP1963) Est. Completion: 12/25 Pima Road: Dynamite Boulevard to Las Piedras Location: Project Type: Construction Related Description: Design and construct Pima Road from Dynamite Boulevard to Las Piedras to the ultimate cross-section including drainage and intersection improvements. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Design/Construction Admin Land/ROW Total: Funding Sources (In thousands of dollars) Regional Sales Tax - Arterial Life Cycle Program Transportation 0.1% Sales Tax 2019 Total: 521.7 8,774.0 1,781.1 1,966.2 13,043.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 9,130.0 - - - - - 9,130.0 9,130.0 3,913.0 13,043.0 - - - - - 3,913.0 - 13,043.0 3,913.0 13,043.0  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 144 - Table of Contents TRANSPORTATION | Streets/Street Improvements Streets/Street Improvements Pima Road: Happy Valley Road to Jomax Road - (TEMP1934) Est. Completion: 12/25 Pima Road: Happy Valley Road to Jomax Road Location: Project Type: Construction Related Description: Construct Pima Road to its ultimate six-lane major arterial cross section including the major intersection of Jomax Road, but not including the Happy Valley Road intersection. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Design/Construction Admin Land/ROW Total: Funding Sources (In thousands of dollars) Regional Sales Tax - Arterial Life Cycle Program Transportation 0.1% Sales Tax 2019 Total: 376.1 7,310.5 815.1 899.7 9,401.5 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 6,580.7 - - - - - 6,580.7 6,580.7 2,820.8 9,401.5 - - - - - 2,820.8 9,401.5 2,820.8 9,401.5 Pima Road: Krail Street to Chaparral Road - (SC04) Est. Completion: 12/20 Pima Road: Krail Street to Chaparral Road Location: Project Type: Construction Related Description: Widen Pima Road from Krail Street (south of Indian Bend Road) to Chaparral Road to two-lanes-per-direction with a raised median, bicycle lanes, and sidewalks to improve capacity and safety for motor vehicles, bicycles, and pedestrians. This segment of roadway is currently one lane in each direction with no center median. The Salt River Pima-Maricopa Indian Community (SRPMIC) and the Maricopa Association of Governments (MAG) will assist paying the project cost. Funding Sources (In thousands of dollars) Regional Sales Tax - Arterial Life Cycle Program Salt River Pima Maricopa Indian Community IGA Transportation 0.2% Sales Tax Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 14,894.0 (1,840.1) 13,053.9 - - - - 13,053.9 3,697.3 - 3,697.3 - - - - 3,697.3 2,686.2 21,277.5 (793.8) (2,633.8) 1,892.4 18,643.7 - - - - 1,892.4 18,643.7  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 145 - Table of Contents TRANSPORTATION | Streets/Street Improvements Streets/Street Improvements Pima Road: Pinnacle Peak Road to Happy Valley Road - (SC01) Est. Completion: 06/21 Pima Road - Pinnacle Peak Road to Happy Valley Road Location: Project Type: Construction Related Description: Design, acquire right-of-way and construct a six-lane major arterial cross-section with landscaped median, turn lanes, bike lanes, sidewalks, curb and gutter, roadway drainage and Intelligent Transportation Systems (ITS) facilities. Funding Sources (In thousands of dollars) Regional Sales Tax - Arterial Life Cycle Program Transportation 0.2% Sales Tax Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 15,991.0 (1,257.4) 14,733.6 - - - - 14,733.6 6,853.3 22,844.3 (85.1) (1,342.4) 6,768.2 21,501.8 - - - - 6,768.2 21,501.8 Pima Road: Via de Ventura to Via Linda - (SB57) Est. Completion: 06/20 Pima Road/90th Street at Via Linda Road Location: Project Type: Construction Related Description: Design and construct intersection improvements along Pima Road and 90th Street up to Via Linda. Funding Sources (In thousands of dollars) Regional Sales Tax - Arterial Life Cycle Program Transportation 0.2% Sales Tax Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 1,338.7 (101.0) 1,237.7 - - - - 1,237.7 574.0 1,912.7 (56.9) (157.9) 517.1 1,754.8 - - - - 517.1 1,754.8  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 146 - Table of Contents TRANSPORTATION | Streets/Street Improvements Streets/Street Improvements Raintree Drive at Arizona State Route 101 Traffic Interchange - (SG01) Est. Completion: 12/25 Raintree Drive at Arizona State Route 101 Traffic Interchange Location: Project Type: Construction Related Description: Analyze, design and construct the interchange of Raintree Drive and the Arizona State Route 101 to reduce delay and queues, and improve capacity and safety. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Design/Construction Admin Land/ROW Total: Funding Sources (In thousands of dollars) Regional Sales Tax - Arterial Life Cycle Program Transportation 0.1% Sales Tax 2019 Total: 358.3 5,647.7 1,912.4 950.5 8,869.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 6,181.8 - 6,181.8 - - - - 6,181.8 2,687.2 8,869.0 - 2,687.2 8,869.0 - - - - 2,687.2 8,869.0  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 147 - Table of Contents TRANSPORTATION | Streets/Street Improvements Streets/Street Improvements Raintree Drive: Hayden Road to Arizona State Route 101 - (SC02) Est. Completion: 06/20 Scottsdale Airpark Location: Project Type: Construction Related Description: Improve the existing five-lane Raintree Drive corridor between Hayden Road and Arizona State Route 101 by rebuilding intersections, modifying medians, and enhancing pedestrian, bicycle and transit facilities. This is one of the segments of the overarching project to extend Raintree Drive from Scottsdale Road to Arizona State Route 101. Funding Sources (In thousands of dollars) Regional Sales Tax - Arterial Life Cycle Program Transportation 0.2% Sales Tax Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 6,304.0 (307.7) 5,996.3 - - - - 5,996.3 2,702.0 9,006.0 (131.9) (439.6) 2,570.1 8,566.4 - - - - 2,570.1 8,566.4  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 148 - Table of Contents TRANSPORTATION | Streets/Street Improvements Streets/Street Improvements Raintree Drive: Scottsdale Road to Hayden Road - (SB53) Est. Completion: 06/20 Scottsdale Airpark Location: Project Type: Construction Related Description: Design and reconstruct a portion of Redfield Road, 76th Place, Acoma Drive and 78th Way to create the extension of Raintree Drive west of Hayden Road. This is one of the segments of the overarching project to extend Raintree Drive from Scottsdale Road to Hayden Road. Funding Sources (In thousands of dollars) Bond 2000 Regional Sales Tax - Arterial Life Cycle Program Transportation 0.2% Sales Tax Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 991.8 (991.8) - - - - - - 16,052.3 (6,172.4) 9,879.9 - - - - 9,879.9 5,955.1 22,999.1 (901.4) (8,065.6) 5,053.7 14,933.6 - - - - 5,053.7 14,933.6 Redfield Road: Raintree Drive to Hayden Road - (SB56) Est. Completion: 06/20 Scottsdale Airpark Location: Project Type: Construction Related Description: Widen the existing Thunderbird-Redfield corridor from four to five lanes between Scottsdale Road and 76th Place. Also connect to Raintree Drive, resulting in an extension of the Raintree Drive corridor to Scottsdale Road. The completed corridor will be renamed Raintree Drive. Improvements to the intersection of Scottsdale Road may be included. Redfield Road will be restriped and reconstructed as necessary from 76th Place to Hayden Road. The project will increase capacity, improve safety and provide enhanced pedestrian and bike facilities. This is one of the segments to extend Redfield Road from Raintree Drive to Hayden Road. Funding Sources (In thousands of dollars) Regional Sales Tax - Arterial Life Cycle Program Transportation 0.2% Sales Tax Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 1,500.0 - 1,500.0 - - - - 1,500.0 642.9 2,142.9 (3.5) (3.5) 639.3 2,139.3 - - - - 639.3 2,139.3  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 149 - Table of Contents TRANSPORTATION | Streets/Street Improvements Streets/Street Improvements Scottsdale Road: Dixileta Drive to Carefree Highway - (TEMP1972) Est. Completion: 12/25 Scottsdale Road: Dixileta Drive to Carefree Highway Location: Project Type: Construction Related Description: Design and construct Scottsdale Road to the ultimate minor arterial cross-section including major intersections with landscaped median, bike lanes, sidewalks and trails to improve safety, capacity and accessibility for motor vehicles, bicycles and pedestrians. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Design/Construction Admin Land/ROW Total: Funding Sources (In thousands of dollars) Regional Sales Tax - Arterial Life Cycle Program Transportation 0.1% Sales Tax 2019 Total: 676.5 10,983.2 1,871.2 3,381.1 16,912.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2023/24 Total Remaining Budget 11,838.0 - - - - - 11,838.0 11,838.0 5,074.0 16,912.0 - - - - - 5,074.0 - 16,912.0 5,074.0 16,912.0 Forecast 2022/23  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 150 - Table of Contents TRANSPORTATION | Streets/Street Improvements Streets/Street Improvements Scottsdale Road: Jomax Road to Dixileta Drive - (TEMP1971) Est. Completion: 12/25 Scottsdale Road: Jomax Road to Dixileta Drive Location: Project Type: Construction Related Description: Design and construct Scottsdale Road to the ultimate minor arterial cross section including the major intersections with landscaped median, bike lanes, sidewalks and trails to improve safety, capacity and accessibility for motor vehicles, bicycles and pedestrians. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Design/Construction Admin Land/ROW Total: Funding Sources (In thousands of dollars) Grants Regional Sales Tax - Arterial Life Cycle Program Transportation 0.1% Sales Tax 2019 Total: 557.3 9,048.5 1,541.6 2,785.5 13,932.9 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 1,844.2 - - - 1,844.2 - - 1,844.2 9,753.0 - - - - - 9,753.0 9,753.0 2,335.7 13,932.9 - - - 1,844.2 - 2,335.7 - 12,088.7 2,335.7 13,932.9  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 151 - Table of Contents TRANSPORTATION | Streets/Street Improvements Streets/Street Improvements Scottsdale Road: Pinnacle Peak Parkway to Jomax Road – (TEMP1970-F) Est. Completion: 12/24 Scottsdale Road: Pinnacle Peak Parkway to Jomax Road Location: Project Type: Construction Related Description: Design and construct Scottsdale Road to the ultimate major arterial cross section from Pinnacle Peak Parkway to Happy Valley Road, and the minor arterial cross-section from Happy Valley Road to Jomax Road with landscaped median, bike lanes, sidewalks and trails to improve safety, capacity and accessibility for motor vehicles, bicycles and pedestrians. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Art in Public Places City Fees Construction Contingency Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) Regional Sales Tax – Arterial Life Cycle Program Transportation 0.1% Sales Tax 2019 Total: 167.0 21.7 41.7 14,033.2 376.1 171.0 83.5 14,894.2 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 10,425.8 - - - - 1,800.0 8,625.8 10,425.8 4,468.4 14,894.2 - - - - 771.0 3,697.4 2,571.0 12,323.2 4,468.4 14,894.2  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 152 - Table of Contents TRANSPORTATION | Streets/Street Improvements Streets/Street Improvements Scottsdale Road: Thompson Peak Parkway to Pinnacle Peak Road Phase II - (TEMP1969-F) Est. Completion: 12/24 Scottsdale Road: Thompson Peak Parkway to Pinnacle Peak Road Location: Project Type: Construction Related Description: Complete Scottsdale Road to the ultimate arterial configuration including the major intersections of Thompson Peak Parkway, Deer Valley Road, Williams Drive, and Pinnacle Peak Road with landscaped median, bike lanes, sidewalks and trails to improve safety, capacity and accessibility for motor vehicles, bicycles and pedestrians. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Art in Public Places City Fees Construction Contingency Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) Regional Sales Tax - Arterial Life Cycle Program Transportation 0.1% Sales Tax 2019 Total: 568.2 74.0 142.1 13,038.3 1,281.0 582.3 284.1 15,970.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 11,179.0 - - - - 6,128.0 5,051.0 11,179.0 4,791.0 15,970.0 - - - - 2,626.3 8,754.3 2,164.7 7,215.7 4,791.0 15,970.0  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 153 - Table of Contents TRANSPORTATION | Streets/Street Improvements Streets/Street Improvements Shea Boulevard Intersections: Arizona State Route 101 to 136th Street - (TEMP2015) Est. Completion: 12/25 Shea Boulevard Intersections Location: Project Type: Construction Related Description: Construct capacity and safety improvements at the Shea Boulevard corridor intersections from Arizona State Route 101 to 136th Street. Design and construct turn lanes, sidewalks, and bike lanes, at multiple locations. Design and construct roundabouts at several locations on parallel roadways such as Cactus Road and Mountain View Road to divert Shea Boulevard traffic to other routes. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Contingency Design/Construction Admin Land/ROW Machinery and Equipment Salaries Total: Funding Sources (In thousands of dollars) Regional Sales Tax - Arterial Life Cycle Program Transportation 0.1% Sales Tax 2019 Total: 1,511.2 13,615.2 1,889.0 1,511.2 566.7 188.9 755.6 20,037.7 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2023/24 Total Remaining Budget 14,162.0 - - - - - 14,162.0 14,162.0 5,875.7 20,037.7 - - - - - 5,875.7 - 20,037.7 5,875.7 20,037.7 Forecast 2022/23 Streetlight Replacement - (YTEMP2342) Est. Completion: N/A Citywide; primarily in residential neighborhoods south of the Arizona Canal Location: Project Type: Construction Related Description: Replace of a portion of the streetlight poles that have reached the end of their useful life. The total inventory of city streetlight poles is 7,400. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Total: Funding Sources (In thousands of dollars) Transportation 0.2% Sales Tax Total: 11.0 262.0 273.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 273.0 273.0 - - 73.0 73.0 200.0 200.0 - - 273.0 273.0  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 154 - Table of Contents TRANSPORTATION | Streets/Street Improvements Streets/Street Improvements Thomas Road: 56th Street to 73rd Street - (SG03) Est. Completion: 12/25 Thomas Road: 56th Street to 73rd Street Location: Project Type: Construction Related Description: Design and construct a complete street project that will include left turn bays, bike lanes and pedestrian improvements in the major intersections to improve safety, capacity and accessibility to motor vehicles, bicycles and pedestrians. This project will reduce eastbound Thomas Road from three travel lanes per direction to two travel lanes per direction. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Design/Construction Admin Total: Funding Sources (In thousands of dollars) Grants Transportation 0.2% Sales Tax Total: 194.3 4,009.2 605.9 4,809.3 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 3,682.0 1,127.4 4,809.3 - 633.1 633.1 - 3,682.0 494.2 4,176.2 - - 3,682.0 1,127.4 4,809.3 Transportation Fund Contingency - (ZF01) Est. Completion: N/A Citywide Location: Project Type: Construction Related Description: Provides budgetary appropriation set aside for citywide emergencies or unforeseen expenditures not otherwise budgeted. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Contingency Total: Funding Sources (In thousands of dollars) Transportation 0.2% Sales Tax Total: 15,000.0 15,000.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 15,000.0 15,000.0 - 3,000.0 3,000.0 3,000.0 3,000.0 3,000.0 3,000.0 3,000.0 3,000.0 3,000.0 3,000.0 15,000.0 15,000.0  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 155 - Table of Contents TRANSPORTATION OVERVIEW | Traffic/Traffic | Volume Reduction Content Traffic/Traffic Reduction Hayden/Thomas Safety Improvements - (TB57) Est. Completion: 12/20 Hayden Road and Thomas Road Intersection Location: Project Type: Construction Related Description: Design and construct intersection and access improvements to enhance safety and traffic operations. Pedestrian, bike, transit and vehicle improvements are included. Funding Sources (In thousands of dollars) Bond 2000 Grants Transportation 0.2% Sales Tax Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 460.9 1,706.5 2,140.3 4,307.7 (460.9) (387.5) (357.1) (1,205.5) 1,319.0 1,783.2 3,102.2 - - - - 1,319.0 1,783.2 3,102.2 ITS/Signal System Upgrades - (TB56) Est. Completion: 06/22 Citywide Location: Project Type: Construction Related Description: Install fiber optic cable to connect Scottsdale’s traffic signal system and upgrade outdated signal cabinets, controllers and detection. The improvements will connect additional traffic signals to Scottsdale’s Traffic Management Center which will improve signal timing decisions and accident management while the roadways are being cleared. Funding Sources (In thousands of dollars) Transportation 0.2% Sales Tax Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 7,465.0 7,465.0 (4,819.7) (4,819.7) 565.3 565.3 1,040.0 1,040.0 1,040.0 1,040.0 - - 2,645.3 2,645.3  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 156 - Table of Contents TRANSPORTATION OVERVIEW | Traffic/Traffic | Volume Reduction Content Traffic/Traffic Reduction Neighborhood Traffic Management Program - (YG21) Est. Completion: N/A Citywide Location: Project Type: Construction Related Description: Modify streets throughout Scottsdale to reduce traffic speed and volume, such as narrowing travel lanes with medians or restricting turning movements with barriers. These modifications are made exclusively at the request of neighborhood residents. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) Transportation 0.2% Sales Tax Total: 150.0 847.5 200.0 50.0 1,247.5 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 1,247.5 1,247.5 - 247.5 247.5 250.0 250.0 250.0 250.0 250.0 250.0 250.0 250.0 1,247.5 1,247.5 Roadway Capacity & Safety Improvements - (YG19) Est. Completion: N/A Citywide Location: Project Type: Construction Related Description: Modify roadways throughout Scottsdale in order to make the street system work more efficiently, and to improve safety and capacity. Improvements include adding and lengthening left-turn or right-turn lanes, building missing short segments of through travel lanes and adding medians. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) Transportation 0.2% Sales Tax Total: 295.1 3,679.5 368.9 147.5 4,491.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 4,491.0 4,491.0 - 891.0 891.0 900.0 900.0 900.0 900.0 900.0 900.0 900.0 900.0 4,491.0 4,491.0  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 157 - Table of Contents TRANSPORTATION OVERVIEW | Traffic/Traffic | Volume Reduction Content Traffic/Traffic Reduction Traffic Signal Construction - (YF23) Est. Completion: N/A Citywide Location: Project Type: Construction Related Description: Install new traffic signals and relocate existing signals to improve signal timing and public safety. The project will accommodate changes to traffic patterns in Scottsdale as the city develops. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Total: Funding Sources (In thousands of dollars) Transportation 0.2% Sales Tax Total: 40.0 260.0 300.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 300.0 300.0 (230.9) (230.9) 69.1 69.1 - - - - 69.1 69.1 Traffic Signal Construction - (YG23) Est. Completion: N/A Citywide Location: Project Type: Construction Related Description: Install new traffic signals and relocate existing signals to improve signal timing and public safety. The project will accommodate changes to traffic patterns in Scottsdale as the city develops. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Total: Funding Sources (In thousands of dollars) Transportation 0.2% Sales Tax Total: 200.0 1,297.0 1,497.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 1,497.0 1,497.0 - 297.0 297.0 300.0 300.0 300.0 300.0 300.0 300.0 300.0 300.0 1,497.0 1,497.0  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 158 - Table of Contents TRANSPORTATION | Transit/Transit Improvements Transit/Transit Improvements 68th Street Bridge Reconstruction over the Arizona Canal - (TE05) Est. Completion: 12/19 68th Street bridge over the Arizona canal Location: Project Type: Construction Related Description: Investigate, design and replace the 68th Street bridge over the Arizona Canal. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs City Fees Construction Contingency Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) Transportation 0.2% Sales Tax Total: 294.0 5.0 3,433.4 260.6 910.0 147.0 5,050.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 5,050.0 5,050.0 (3,823.5) (3,823.5) 1,226.5 1,226.5 - - - - 1,226.5 1,226.5 Advanced Traffic Signal Control Cabinets Phase II - (TE04) Est. Completion: 06/20 Citywide Location: Project Type: Construction Related Description: Replace standard signal cabinets with advanced hybrid cabinets at arterial to arterial intersections. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Machinery and Equipment Total: Funding Sources (In thousands of dollars) Grants Transportation 0.2% Sales Tax Total: 770.4 770.4 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 679.0 91.4 770.4 (678.9) (91.4) (770.4) - - - - - -  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 159 - Table of Contents TRANSPORTATION | Transit/Transit Improvements Transit/Transit Improvements Arizona Canal Path - Chaparral to McDonald to Indian Bend Wash - (TB58) Est. Completion: 12/19 Arizona Canal from Chaparral Road to McDonald Road Location: Project Type: Construction Related Description: Design and construct a multiuse path along the Arizona Canal from Chaparral Road to the Indian Bend Wash path south of Indian Bend Road. Landscaping, site furnishings, connections to adjacent neighborhoods and pedestrian bridges are included. Funding Sources (In thousands of dollars) Grants Transportation 0.2% Sales Tax Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 2,800.0 717.7 3,517.7 (2,535.2) (204.6) (2,739.9) 264.8 513.1 777.8 - - - - 264.8 513.1 777.8 Arizona Canal Path Public Art Project - (TE02) Est. Completion: 12/19 Arizona Canal from Chaparral Road to McDonald Road Location: Project Type: Construction Related Description: Design and construct the public art component of the Arizona Canal Path - Chaparral to McDonald to Indian Bend Wash project. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Art in Public Places Construction Contingency Salaries Total: Funding Sources (In thousands of dollars) Transportation 0.2% Sales Tax Total: 22.0 55.0 511.0 50.0 11.0 649.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 649.0 649.0 (31.0) (31.0) 618.0 618.0 - - - - 618.0 618.0  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 160 - Table of Contents TRANSPORTATION | Transit/Transit Improvements Transit/Transit Improvements Bikeways Program - (YG28) Est. Completion: N/A Citywide Location: Project Type: Construction Related Description: Improve bicycle and shared-use paths throughout Scottsdale by making connections between missing segments of paved travel ways for bicyclists, pedestrians, and wheelchairs. The project will focus on missing path segments adjacent to canals, in facilities such as Indian Bend Wash, and bicycle lanes on streets. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Contingency Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) Transportation 0.2% Sales Tax Total: 225.0 1,496.0 15.0 200.0 60.0 1,996.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 1,996.0 1,996.0 - 396.0 396.0 400.0 400.0 400.0 400.0 400.0 400.0 400.0 400.0 1,996.0 1,996.0 Downtown Main Street Streetscape & Pedestrian Improvements - (DE03) Est. Completion: 06/20 Main Street from 69th Street to Scottsdale Road Location: Project Type: Construction Related Description: Design and construct bicycle lanes, sidewalks and roadside landscaping, and replace street and pedestrian lighting. Promote main street as a major east/west pedestrian corridor traversing downtown from 69th Street to Brown Avenue and the Civic Center Mall. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs City Fees Construction Contingency Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) General Fund Total: 142.5 27.4 1,507.6 273.8 267.2 71.3 2,289.7 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 2,289.7 2,289.7 (146.5) (146.5) 2,143.2 2,143.2 - - - - 2,143.2 2,143.2  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 161 - Table of Contents TRANSPORTATION | Transit/Transit Improvements Transit/Transit Improvements Drinkwater Bridge Interim Structural Repairs - (TE03) Est. Completion: 12/19 Civic Center Mall west of the Kiva City Hall Location: Project Type: Construction Related Description: Design and construct structural repairs of the Drinkwater Bridge to stop further degradation of the existing structure. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs City Fees Construction Contingency Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) Bond 2000 Regional Sales Tax - Arterial Life Cycle Program Transportation 0.2% Sales Tax Total: 478.4 79.6 7,298.0 724.8 500.0 239.2 9,320.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 560.0 (560.0) - - - - - - 5,999.0 - 5,999.0 - - - - 5,999.0 2,761.0 9,320.0 (3,214.0) (3,774.0) (453.0) 5,546.0 - - - - (453.0) 5,546.0  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 162 - Table of Contents TRANSPORTATION | Transit/Transit Improvements Transit/Transit Improvements Legacy Drive - Hualapai Drive Connector - (TG01) Est. Completion: 06/22 Legacy Boulevard and Hualapai Drive north of the Scottsdale Water Campus Location: Project Type: Construction Related Description: Design and construct Legacy Boulevard from Hayden Road to Hualapai Drive west of Pima Road and north of the Scottsdale Water Campus. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Art in Public Places City Fees Construction Contingency Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) Regional Sales Tax - Arterial Life Cycle Program Transportation 0.1% Sales Tax 2019 Total: 114.8 16.1 28.7 1,595.3 239.2 215.2 57.4 2,266.7 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 1,586.7 - 1,586.7 - - - - 1,586.7 680.0 2,266.7 - 680.0 2,266.7 - - - - 680.0 2,266.7  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 163 - Table of Contents TRANSPORTATION | Transit/Transit Improvements Transit/Transit Improvements Mayo Boulevard Underpass & Union Hills Drive: Arizona State Route 101 to 88th Street - (TEMP2318) Est. Completion: 06/23 Mayo Boulevard Underpass & Union Hills Drive: Arizona State Route 101 to 88th Street Location: Project Type: Construction Related Description: Complete a new roadway connection across Arizona State Route 101 using the former Union Hills Boulevard alignment to improve safety, capacity and accessibility. A roundabout at the Perimeter Drive intersection is included. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Art in Public Places City Fees Construction Contingency Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) Regional Sales Tax - Arterial Life Cycle Program Transportation 0.1% Sales Tax 2019 Total: 982.5 138.0 245.6 13,653.8 2,046.8 1,842.1 491.2 19,400.0 Total Project Cost ITD Expenditures (Thru 06/19) Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 13,580.0 - - 13,580.0 - - - 13,580.0 5,820.0 19,400.0 - - - - - 5,820.0 19,400.0 Adopted 2019/20 5,820.0 19,400.0  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 164 - Table of Contents TRANSPORTATION | Transit/Transit Improvements Transit/Transit Improvements Mustang Transit Passenger Facility - (TB50) Est. Completion: 06/19 Mustang Library at 90th Street and Shea Boulevard Location: Project Type: Construction Related Description: Design and construct a transit facility along 90th Street (intersection with Mustang Library) south of Shea Boulevard. The project includes a two-lane roundabout, traffic control, bus shelters, landscaping and utility relocations. Funding Sources (In thousands of dollars) Bond 2000 Grants Transportation 0.2% Sales Tax Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 1,736.8 5,260.2 422.2 7,419.2 (1,736.8) (3,226.5) (245.2) (5,208.5) 2,033.7 177.1 2,210.7 - - - - 2,033.7 177.1 2,210.7 Old Town Pedestrian Improvements - (TD01) Est. Completion: 12/19 Downtown Scottsdale Location: Project Type: Construction Related Description: Design and construct pedestrian improvements including continuous sidewalk corridors, widen narrow sidewalks, add accessible ramps where needed, modify sidewalk to conform to Americans with Disabilities Act (ADA) requirements and install pedestrian related amenities such as lighting along these areas as appropriate. Funding Sources (In thousands of dollars) Transportation 0.2% Sales Tax Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 3,541.1 3,541.1 (1,630.6) (1,630.6) 1,910.5 1,910.5 - - - - 1,910.5 1,910.5  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 165 - Table of Contents TRANSPORTATION | Transit/Transit Improvements Transit/Transit Improvements Transportation Transit/Transit Improvements Crosscut Canal Bridge and Path - (TB63) Est. Completion: Location: Project Type: Description: 06/18 Crosscut Canal Path south of McDowell Road at approximately 66th Street Construction Related Design and construct a non-motorized bridge over the Crosscut Canal, a ramp and a path. Also connect existing pathways between Tempe and Scottsdale to provide safety for bicycles and pedestrian to access the new transit center south of the Scottsdale Road and McDowell Road intersection. Funding Sources (In thousands of dollars) Grants Total ITD Project Expenditures Cost (Thru 06/17) 445.4 Transportation 0.2% Sales Tax Total: - 706.3 (258.1) 1,151.7 (258.1) FY 2017/18 Budget 445.4 448.2 893.6 FY 2018/19 Forecast - - FY 2019/20 Forecast - - FY 2020/21 Forecast - - FY 2021/22 Forecast - - Total Remaining Budget 445.4 448.2 893.6 Downtown Main Street Streetscape & Pedestrian Improvements - (DE03) Est. Completion: 06/20 Location: Downtown Scottsdale Project Type: Description: Construction Related Design and construct the narrowing of two traffic lanes, widening sidewalks, addition of bike lanes, improvement of street landscaping elements and replacement and improvement of street and pedestrian lighting. Main Street has long been envisioned as a major east/west pedestrian corridor traversing downtown from 69th Street to the Civic Center Mall at Brown Avenue. The focus of this project is on the west side of Main Street from Scottsdale Road to 69th Street. Funding Sources (In thousands of dollars) General Fund Total: Total ITD Project Expenditures Cost (Thru 06/17) FY 2017/18 Budget FY 2018/19 Forecast FY 2019/20 Forecast FY 2020/21 Forecast FY 2021/22 Forecast Total Remaining Budget 2,289.7 - 2,289.7 - - - - 2,289.7 2,289.7 - 2,289.7 - - - - 2,289.7  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. Pima Road: Jomax Road to Dynamite Boulevard - (TEMP2302) Est. Completion: 06/25 Pima Road: Dynamite Road to Jomax Road Location: Project Type: Construction Related Description: Design and construct Pima Road to the ultimate major arterial cross section including major intersections with landscaped median, bike lanes, sidewalks and trails to improve safety, capacity and accessibility for motor vehicles, bicycles and pedestrians. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Design/Construction Admin Land/ROW Total: Funding Sources (In thousands of dollars) Regional Sales Tax - Arterial Life Cycle Program Transportation 0.1% Sales Tax 2019 Total: 322.2 6,263.9 698.4 770.9 8,055.5 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 5,638.7 - - - - - 5,638.7 5,638.7 2,416.8 8,055.5 - - - - - 2,416.8 8,055.5 2,416.8 8,055.5  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 166 - Table of Contents TRANSPORTATION | Transit/Transit Improvements Transit/Transit Improvements Pima Road: Las Piedras to Stagecoach Pass - (TEMP2303) Est. Completion: 12/25 Pima Road: Las Piedras to Stagecoach Pass Location: Project Type: Construction Related Description: Design and construct Pima Road to the ultimate minor arterial cross section including major intersections with landscaped median, bike lanes, sidewalks and trails to improve safety, capacity and accessibility for motor vehicles, bicycles and pedestrians. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Design/Construction Admin Land/ROW Total: Funding Sources (In thousands of dollars) Regional Sales Tax - Arterial Life Cycle Program Transportation 0.1% Sales Tax 2019 Total: 1,392.8 23,512.6 4,754.8 5,248.8 34,909.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2023/24 Total Remaining Budget 24,436.0 - - - - - 24,436.0 24,436.0 10,473.0 34,909.0 - - - - - 10,473.0 - 34,909.0 10,473.0 34,909.0 Forecast 2022/23 Shea Underpass Access at 124th Street - (TB66) Est. Completion: 12/19 Shea Boulevard east of 124th Street Location: Project Type: Construction Related Description: Design and construct a concrete shared use path and an unpaved trail between Sahuaro Drive and Via Linda Road including access to an existing tunnel under Shea Boulevard. Funding Sources (In thousands of dollars) Grants In Lieu Fees In-Lieu Fees Transportation Regional Sales Tax - Arterial Life Cycle Program Transportation 0.2% Sales Tax Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 1,253.0 20.7 42.3 (1,130.7) (20.7) (42.3) 122.4 - - - - - 122.4 - 428.4 (204.1) 224.3 - - - - 224.3 1,013.0 2,757.5 (804.8) (2,202.6) 208.2 554.9 - - - - 208.2 554.9  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 167 - Table of Contents TRANSPORTATION | Transit/Transit Improvements Transit/Transit Improvements Sidewalk Improvements - (YG20) Est. Completion: N/A Citywide Location: Project Type: Construction Related Description: Design and construct missing segments of sidewalks to improve connectivity and repair sidewalks that require more than routine maintenance to enhance the sidewalk system in Scottsdale. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) Transportation 0.2% Sales Tax Total: 92.5 750.5 105.0 50.0 998.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 998.0 998.0 - 198.0 198.0 200.0 200.0 200.0 200.0 200.0 200.0 200.0 200.0 998.0 998.0 Trail Improvement Program - (YG18) Est. Completion: N/A Citywide Location: Project Type: Construction Related Description: Build missing segments of unpaved travel ways for hikers, equestrians, and mountain bicyclists, typically adjacent to canals. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) Transportation 0.2% Sales Tax Total: 225.0 498.0 200.0 75.0 998.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 998.0 998.0 - 198.0 198.0 200.0 200.0 200.0 200.0 200.0 200.0 200.0 200.0 998.0 998.0  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 168 - Table of Contents TRANSPORTATION | Transit/Transit Improvements Transit/Transit Improvements Transit Route 72 Improvements - (TC08) Est. Completion: 06/19 Along Scottsdale Road Transit Route 72 Location: Project Type: Construction Related Description: Design and construct bus stop improvements along Scottsdale Road Transit Route 72. Funding Sources (In thousands of dollars) CIP Regional Sales Tax - Transit Grants Transportation 0.2% Sales Tax Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 238.7 954.7 60.0 1,253.3 (32.1) (128.6) (2.3) (163.0) 206.5 826.1 57.7 1,090.3 - - - - 206.5 826.1 57.7 1,090.3 Transit Stop Improvements - (TC03) Est. Completion: 06/24 Citywide Location: Project Type: Construction Related Description: Implement transit stop modifications that include shade, benches and bicycle racks to comply with city standards and federal requirements, and enhance the transit stop system in Scottsdale. Funding Sources (In thousands of dollars) Transportation 0.2% Sales Tax Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 1,099.0 1,099.0 (602.2) (602.2) 96.8 96.8 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 496.8 496.8 WestWorld Trail Connections - (TC02) Est. Completion: 06/21 Areas adjacent to Westworld, Grayhawk, DC Ranch and McDowell Mountain Ranch communities Location: Project Type: Construction Related Description: Design and construct 4.7 miles of non-motorized connectivity from WestWorld to adjoining neighborhoods and the McDowell Sonoran Preserve. Funding Sources (In thousands of dollars) Grants Transportation 0.2% Sales Tax Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 4,223.6 498.0 4,721.6 (438.3) (438.3) 4,223.6 59.7 4,283.3 - - - - 4,223.6 59.7 4,283.3  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 169 - FY 2019/20 Adopted Budget City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 170 - Table of Contents 4VSNIGX(IWGVMTXMSRW WATER MANAGEMENT -RXLSYWERHWSJHSPPEVW ;EXIV1EREKIQIRX ;EXIV1EREKIQIRXJSGYWIWSRGSSVHMREXMRKPERHYWIERHMRJVEWXVYGXYVITPERRMRK[MXLMRXLIGSRXI\XSJJMRERGMEPHIQERHWERH EZEMPEFPIVIWSYVGIW8LITVSKVEQEGLMIZIWXLMWKSEPF]HIPMZIVMRKWEJIVIPMEFPI[EXIVERHTVSZMHMRK[EXIVVIGPEQEXMSRWIVZMGIW 8LMWTVSKVEQEPWSVIJPIGXWXLIGMX]’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ity of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 171 -                     Table of Contents 4VSNIGX(IWGVMTXMSRW WATER MANAGEMENT -RXLSYWERHWSJHSPPEVW 4VSNIGX ;EXIV1EREKIQIRX ;EXIV-QTVSZIQIRXW 'EQTYW'IRXVEP%VM^SRE4VSNIGX(VEMREKI 4EZMRK -QTVSZIQIRXW ;EXIV  ;& 'LETEVVEP;EXIV8VIEXQIRX4PERX4VIXVIEXQIRX ;& 'PYWXIV%VWIRMG8VIEXQIRX ;+ 'VSWWVSEHW)EWX;EXIV ;* (IIT;IPP6IGLEVKI6IGSZIV]4VSNIGXW ;* )EWX(]REQMXI%VIE8VERWQMWWMSR1EMR ;( *VERO0PS]H;VMKLXMRGL8VERWQMWWMSR1EMR  &SSWXIV7XEXMSR&1SHMJMGEXMSRW ;' -VVMKEXMSR;EXIV(MWXVMFYXMSR7]WXIQ-QTVSZIQIRXW ;& -;(7,EVUYELEPE:EPPI]-VVMKEXMSR(MWXVMGX4VSTIVX] (IWIVX1SYRXEMR+SPJ'PYF ;& -;(7,EVUYELEPE:EPPI]-VVMKEXMSR(MWXVMGX4VSTIVX] 7GSXXWHEPI2EXMSREP+SPJ'PYF ;& 1EWXIV4PER;EXIV ;& 6EHMS8IPIQIXV]1SRMXSVMRK%YXSQEXMSR'MX][MHI ;EXIV ;& 6IKMSREP6IGLEVKI&EWMRW ;& 6MS:IVHIXL7XVIIX8VERWQMWWMSR1EMRW ;+ 7MXI6IWIVZSMV7XSVEKI)\TERWMSR ;* 7XEXI0ERH2IEV0IKIRH8VEMPW- ;* 7XEXI0ERH2IEV0IKIRH8VEMPW-- ;* 8IGLRSPSK]1EWXIV4PER-HIRXMJMIH;EXIV4VSNIGXW ;) 8LSQEW+VSYRH[EXIV8VIEXQIRX*EGMPMX] ;' ;EXIVERH7I[IV7]WXIQ3TXMQM^EXMSR ;& ;EXIV'EQTYW:EHSWI;IPP'SRWXVYGXMSR 8)14 * ;EXIV'EQTYW:EHSWI;IPP6ILEFMPMXEXMSR ;& ;EXIV(MWXVMFYXMSR7]WXIQ-QTVSZIQIRXW ;& ;EXIV*YRH'SRXMRKIRG] >) ;EXIV-QTEGX*IIW ;' ;EXIV1IXIV6ITPEGIQIRX4VSKVEQ ;& ;EXIV4EVXMGMTEXMSR4VSKVEQ ;& ;EXIV5YEPMX]0EF)UYMTQIRX6ITPEGIQIRX ;+ ;EXIV6IWSYVGIW-QTEGX*IIW ;' 6IGYVVMRK'ETMXEP1EMRXIRERGI4VSNIGXW %HSTXIH  *SVIGEWX  *SVIGEWX  *SVIGEWX  *SVIGEWX  8SXEP 4EKI                                                                                                                                                                                  City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 172 -                           Table of Contents 4VSNIGX(IWGVMTXMSRW WATER MANAGEMENT -RXLSYWERHWSJHSPPEVW 4VSNIGX ;EXIV1EREKIQIRX ;EXIV-QTVSZIQIRXW ;EXIV7]WXIQ3ZIVWM^MRK ;* ;EXIV7]WXIQ7IGYVMX])RLERGIQIRX4VSNIGXW ;) ;EXIV8IGLRSPSK]1EWXIV4PER ;& ;EXIV8VIEXQIRX*EGMPMX]-QTVSZIQIRXW ;( ;EXIV8VIEXQIRX4PERX1IQFVERIW ;& ;IPP7MXI-R'VSWWVSEHW)EWX2SVXLSJXLI%VM^SRE 7XEXI6SYXI ;* ;IPP7MXIW ;& ;IPP7MXIW6ILEFMPMXEXMSR ;& ;IWX;SVPH-QTVSZIQIRXW ;& >SRI;EXIV7]WXIQ-QTVSZIQIRXW4LEWI ;* >SRI;EXIV7]WXIQ-QTVSZIQIRXW ;' >SRI;;EXIV7]WXIQ-QTVSZIQIRXW ;( >SRI.SQE\6SEH8VERWQMWWMSR0MRI ;+ >SRI(.SQE\6SEH8VERWQMWWMSR0MRI ;+ 6IGYVVMRK'ETMXEP1EMRXIRERGI4VSNIGXW %HSTXIH  *SVIGEWX  *SVIGEWX  *SVIGEWX  *SVIGEWX                                                                                                    City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 173 - 8SXEP 4EKI Table of Contents WATER MANAGEMENT | Wastewater Improvements Wastewater Improvements Advance Water Treatment Plant Membranes - Wastewater - (VB69) Est. Completion: 12/24 Scottsdale Water Campus Location: Project Type: Construction Related Description: Replace water treatment membranes at the Advanced Water Treatment (AWT) Plant at the Water Campus. Funding Sources (In thousands of dollars) Sewer Rates Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 4,308.0 4,308.0 (1,249.4) (1,249.4) 8.6 8.6 750.0 750.0 500.0 500.0 600.0 600.0 1,200.0 1,200.0 3,058.6 3,058.6 Crossroads East Sewer - (VF03) Est. Completion: 06/20 74th Street to Hayden Road, North of Arizona State Route 101 Location: Project Type: Construction Related Description: Construct sewer lines within the area consistent with a development agreement and the Infrastructure Improvement Plan (IIP). The IIP is a written document per Arizona Revised Statute 9-463.05, identifying growth driven water and wastewater infrastructure needs that are funded with development fees. Advanced construction of streets within the Core North/Core South area by the city will require concurrent installation of sewer lines to provide service for future adjacent development. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs City Fees Construction Contingency Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) Sewer Development Fees Sewer Rates Total: 267.2 66.8 3,156.7 602.2 273.8 133.6 4,500.3 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 4,406.0 94.2 4,500.3 (83.3) (0.6) (83.9) 4,322.8 93.6 4,416.4 - - - - 4,322.8 93.6 4,416.4 Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 174 - Table of Contents Capital Improvement Plan CAPITAL IMPROVEMENT WATER MANAGEMENT PLAN - PROJECT | Wastewater LIST |Financial Alphabetical Financial Summary & Five YearImprovements Forecast Wastewater Improvements Downtown Stormwater Pump Station Rehabilitation - (VD02) Est. Completion: 06/21 Stormwater pump station at the Civic Center Library Location: Project Type: Construction Related Description: Replace the stormwater pumping equipment located at the downtown Civic Center Library. The pump station features the original equipment which has exceeded its useful service life and has created extraordinary maintenance requirements. Funding Sources (In thousands of dollars) Sewer Rates Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 1,278.8 1,278.8 (1,034.9) (1,034.9) 243.9 243.9 - - - - 243.9 243.9 Dynamite Road Sewer Interceptor - (VF01) Est. Completion: 06/21 Dynamite Road east of Pima Road Location: Project Type: Construction Related Description: Install a sewer interceptor in Dynamite Road right-of-way to convey sewer flow to the Scottsdale Water Campus for treatment. This is consistent with the Infrastructure Improvement Plan (IIP). The IIP is a written document per Arizona Revised Statute 9-463.05, identifying growth driven water and wastewater infrastructure needs that are funded with development fees. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs City Fees Construction Contingency Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) Sewer Development Fees Sewer Rates Total: 161.6 30.4 1,245.6 274.0 124.6 60.8 1,897.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 1,857.0 40.0 1,897.0 - 1,857.0 40.0 1,897.0 - - - - 1,857.0 40.0 1,897.0 Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 175 - Table of Contents WATER MANAGEMENT | Wastewater Improvements Wastewater Improvements Jomax Road Sewer Interceptor and Lift Station - (VF02) Est. Completion: 06/21 Jomax Road and 56th Street Location: Project Type: Construction Related Description: Install sewer interceptor and lift station in Jomax Road right-of-way to convey sewer flow to the city's Water Campus for treatment consistent with the Infrastructure Improvement Plan (IIP). The IIP is a written document per Arizona Revised Statute 9-463.05, identifying growth driven water and wastewater infrastructure needs that are funded with development fees. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs City Fees Construction Contingency Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) Sewer Development Fees Sewer Rates Total: 378.0 72.0 2,950.8 649.2 295.1 144.0 4,489.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 4,399.0 90.0 4,489.0 - 4,399.0 90.0 4,489.0 - - - - 4,399.0 90.0 4,489.0 Master - Plan Water Reclamation - (VB70) Est. Completion: 06/23 Citywide Location: Project Type: Construction Related Description: Update master plan for wastewater system management needs including federal regulatory impacts and capital project needs. Master planning activities include condition assessment analyses of existing sewer systems, lift stations, and treatment facilities, as well as updating operating manuals and standard operating procedures. Provides for facility planning, land use planning, and project cost estimating. Facilitates updates to the water reclamation Infrastructure Improvement Plan (IIP) needed to define sewer development fees associated with growth. Funding Sources (In thousands of dollars) Sewer Rates Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 1,455.5 1,455.5 (686.6) (686.6) 608.9 608.9 - - 160.0 160.0 - 768.9 768.9 Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 176 - Table of Contents Capital Improvement Plan CAPITAL IMPROVEMENT WATER MANAGEMENT PLAN - PROJECT | Wastewater LIST |Financial Alphabetical Financial Summary & Five YearImprovements Forecast Wastewater Improvements Radio Telemetry Monitoring Automation Citywide - Wastewater - (VB58) Est. Completion: 12/23 Citywide Location: Project Type: Construction Related Description: Construct radio telemetry facilities at new and existing wastewater facilities to continue to improve operational efficiency through automation. Funding Sources (In thousands of dollars) Sewer Rates Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 3,530.5 3,530.5 (1,941.7) (1,941.7) 1,288.8 1,288.8 150.0 150.0 - 150.0 150.0 - 1,588.8 1,588.8 Reclamation Regulatory Compliance - (VB59) Est. Completion: 06/20 Scottsdale Water Campus Location: Project Type: Technology Related Description: Install a regulatory compliance software program that will automate and streamline the city's aquifer protection and underground storage facility permits requirements. The program will import external laboratory results from the city’s laboratory information system and track individual contaminant results and automatically provide alerts. The program will provide report writing functions that meet the current Arizona Department of Environmental Quality (ADEQ) self-monitoring requirements. This program will also be operated to track and manage the division’s air quality permits. Funding Sources (In thousands of dollars) Sewer Rates Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 250.0 250.0 - 250.0 250.0 - - - - 250.0 250.0 RWDS Improvements - (VB52) Est. Completion: 12/24 North of Central Arizona Project Canal Location: Project Type: Construction Related Description: Improve the Reclaimed Water Distribution System (RWDS) pipeline pump stations and reservoirs. This project will be fully funded by the golf courses receiving reclaimed effluent from the Water Campus through the RWDS. Total Project Cost Funding Sources (In thousands of dollars) Reclaimed Water Distribution System Fund Total: ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 24,825.0 (13,184.5) 5,640.5 1,500.0 1,500.0 1,500.0 1,500.0 11,640.5 24,825.0 (13,184.5) 5,640.5 1,500.0 1,500.0 1,500.0 1,500.0 11,640.5 Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 177 - Table of Contents WATER MANAGEMENT | Wastewater Improvements Wastewater Improvements Sanitary Sewer Lateral Rehabilitation - (VB67) Est. Completion: 12/23 Citywide Location: Project Type: Construction Related Description: Rehabilitate or replace failing sewer service laterals located within the public right-of-way. Funding Sources (In thousands of dollars) Sewer Rates Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 475.0 475.0 (137.5) (137.5) 187.5 187.5 50.0 50.0 50.0 50.0 50.0 50.0 - 337.5 337.5 SROG Regional Wastewater Facilities - (VF04) Est. Completion: 06/24 Wastewater Treatment Plant, 91st Avenue in Phoenix Location: Project Type: Construction Related Description: Expand, modify and improve the regional wastewater conveyance facilities and the 91st Avenue Wastewater Treatment Plant (located in Phoenix) according to existing intergovernmental agreements with the Sub-Regional Operating Group (SROG). Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Total: Funding Sources (In thousands of dollars) Sewer Rates Total: 100.0 32,151.8 32,251.8 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 32,251.8 32,251.8 (2,189.3) (2,189.3) 30,062.5 30,062.5 - - - - 30,062.5 30,062.5 Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 178 - Table of Contents Capital Improvement Plan CAPITAL IMPROVEMENT WATER MANAGEMENT PLAN - PROJECT | Wastewater LIST |Financial Alphabetical Financial Summary & Five YearImprovements Forecast Wastewater Improvements Technology Master Plan Identified Wastewater Projects - (VE01) Est. Completion: 06/23 Citywide Location: Project Type: Technology Related Description: Design and implement multiple capital improvements identified in the Technology Master Plan. Improvement areas will focus on Supervisory Control and Data Acquisition (SCADA) systems, integration of asset management with work order systems, and communications. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Contingency Design/Construction Admin Total: Funding Sources (In thousands of dollars) Sewer Rates Total: 120.0 2,760.0 120.0 200.0 3,200.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 3,200.0 3,200.0 (293.2) (293.2) 2,906.8 2,906.8 - - - - 2,906.8 2,906.8 Wastewater Fund Contingency - (ZE01) Est. Completion: N/A Citywide Location: Project Type: Construction Related Description: Provide budgetary appropriation set aside for water reclamation system emergencies or unforeseen expenditures not otherwise budgeted. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Contingency Total: Funding Sources (In thousands of dollars) Sewer Rates Total: 10,000.0 10,000.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 10,000.0 10,000.0 - 2,000.0 2,000.0 2,000.0 2,000.0 2,000.0 2,000.0 2,000.0 2,000.0 2,000.0 2,000.0 10,000.0 10,000.0 Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 179 - Table of Contents WATER MANAGEMENT | Wastewater Improvements Wastewater Improvements Wastewater Impact Fees - (VC01) Est. Completion: N/A Citywide Location: Project Type: Construction Related Description: Perform a sewer development fee study and audit requirements as required per Arizona Revised Statute 9463.05. Funding Sources (In thousands of dollars) Sewer Development Fees Sewer Rates Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 220.0 5.0 225.0 (58.0) (0.1) (58.1) 162.0 4.9 166.9 - - - - 162.0 4.9 166.9 Wastewater System Improvements - (VF06) Est. Completion: 12/24 Citywide Location: Project Type: Construction Related Description: Design and construct sewer lines, complete treatment plant work and rehabilitate sewer manholes in the aging sewer system per the Asset Management Program. Many of the sewer lines in the city have been in use for over 30 years. In conjunction with the Asset Management Program, sewer lines will be videotaped to identify potential problems. Design will be initiated to correct any identified problems. Additionally, this project will replace undersized sewer lines and provide new infrastructure to support redevelopment associated with downtown revitalization, consistent with the Infrastructure Improvement Plan (IIP). Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs City Fees Construction Contingency Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) Sewer Development Fees Sewer Rates Total: 1,884.7 426.2 26,387.8 3,842.6 2,196.6 852.4 35,590.3 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 1,905.5 33,684.8 35,590.3 (21.6) (3,643.2) (3,664.8) 1,883.9 13,441.6 15,325.5 2,225.0 2,225.0 5,500.0 5,500.0 4,375.0 4,375.0 4,500.0 4,500.0 1,883.9 30,041.6 31,925.5 Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 180 - Table of Contents Capital Improvement Plan CAPITAL IMPROVEMENT WATER MANAGEMENT PLAN - PROJECT | Wastewater LIST |Financial Alphabetical Financial Summary & Five YearImprovements Forecast Wastewater Improvements Wastewater System Oversizing - (VF05) Est. Completion: 12/23 Citywide Location: Project Type: Construction Related Description: Oversize city lines and facilities to meet future capacity to Master Plan standards. Residential owners and developers are required by City Code to extend sewer lines (typically an eight-inch sewer line) at the resident/developer cost, and the city wishes to use that opportunity to upsize the line to accommodate regional flows. The city pays the cost difference between the upsized line and the price the resident/developer would have paid to extend the sewer line in-kind. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Total: Funding Sources (In thousands of dollars) Sewer Rates Total: 12.0 463.3 475.3 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 475.3 475.3 - 375.3 375.3 100.0 100.0 - - - 475.3 475.3 Wastewater Technology Master Plan - (VB66) Est. Completion: 06/20 Citywide Location: Project Type: Technology Related Description: Develop a master plan to examine current capabilities and condition of communications systems. The master plan will involve the development of a roadmap to update, standardize and maintain integrated control systems including Supervisory Control and Data Acquisition (SCADA)/Telemetry infrastructure. The master plan effort will evaluate hardware/software, as well as study overall system resiliency. Funding Sources (In thousands of dollars) Sewer Rates Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 340.0 340.0 (206.0) (206.0) 134.0 134.0 - - - - 134.0 134.0 Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 181 - Table of Contents WATER MANAGEMENT | Wastewater Improvements Wastewater Improvements Wastewater Treatment Facility Improvements - (VD01) Est. Completion: 12/24 Scottsdale Water Campus, Gainey Wastewater Treatment Facility Location: Project Type: Construction Related Description: Design and construct treatment plant modifications at the Scottsdale Water Campus and the Gainey Ranch Wastewater Treatment Facility. This includes the rehabilitation and replacement of wastewater headworks, piping, clarifiers, pumps, filters, electrical and control systems, heating, ventilation and air conditioning (HVAC) equipment, odor control infrastructure, disinfection and other chemical systems. Also provides for miscellaneous site work such as access drives, shade canopies, grading improvements, and site lighting. Funding Sources (In thousands of dollars) Sewer Rates Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 24,361.4 24,361.4 (8,899.0) (8,899.0) 5,762.4 5,762.4 3,000.0 3,000.0 2,600.0 2,600.0 2,100.0 2,100.0 2,000.0 2,000.0 15,462.4 15,462.4 Water Reclamation Participation Program - (VB56) Est. Completion: 06/24 Citywide Location: Project Type: Construction Related Description: Facilitate the extension of sewer collection lines as required by City Code. The program allows the city to administer payback agreements to assist single-family residences connecting to the city's sewer collection system. These paybacks are settled in the future, and the funding outlays made through this program will be repaid to the city with interest. Funding Sources (In thousands of dollars) Sewer Rates Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 8,500.0 8,500.0 (3,140.5) (3,140.5) 1,659.5 1,659.5 1,000.0 1,000.0 1,000.0 1,000.0 1,000.0 1,000.0 700.0 700.0 5,359.5 5,359.5 Water Reclamation Security Enhancements - (VB54) Est. Completion: 12/24 Citywide Location: Project Type: Construction Related Description: Enhance security at wastewater facilities throughout the city by upgrading existing prevention, detection and response systems. This project is the result of recommendations developed through a security survey of all wastewater facilities in the city. Enhancements to existing security measures were identified in the areas of access control, security personnel, surveillance, intrusion detection, site hardening and back-up power. Funding Sources (In thousands of dollars) Sewer Rates Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 6,071.0 6,071.0 (4,546.1) (4,546.1) 349.9 349.9 325.0 325.0 300.0 300.0 200.0 200.0 350.0 350.0 1,524.9 1,524.9 Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 182 - Table of Contents Water Improvements WATER MANAGEMENT | Water Improvements Advance Water Treatment Plant Membranes Replacement - (WF01) Est. Completion: 12/24 Scottsdale Water Campus Location: Project Type: Construction Related Description: Replace water treatment membranes at the Water Campus Advanced Water Treatment (AWT) Plant. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Total: Funding Sources (In thousands of dollars) Water Rates Total: 55.0 882.1 937.1 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 937.1 937.1 - 302.1 302.1 150.9 150.9 96.2 96.2 136.4 136.4 251.5 251.5 937.1 937.1 Air Park Zone 4 Water Transmission Main - (WD02) Est. Completion: 06/20 Scottsdale Road between the Fairmont Scottsdale Princess Resort and the Bell Road alignment Location: Project Type: Construction Related Description: Design and construct a 16-inch water transmission main intended to replace a 12-inch water transmission main that no longer has enough capacity during peak summer water demands. Funding Sources (In thousands of dollars) MPC Bonds Water Rates Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 150.0 1,550.0 1,700.0 (0.1) (36.4) (36.5) 149.9 1,513.6 1,663.5 - - - - 149.9 1,513.6 1,663.5  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 183 - Table of Contents Water Improvements WATER MANAGEMENT | Water Improvements Booster Station 57 Replacement - (WE01) Est. Completion: 06/20 33475 North Scottsdale Road Location: Project Type: Construction Related Description: Rebuild the developer-built booster station that is approximately 25 years old and has reached the end of its useful life. Site improvements include the replacement of substandard electrical and mechanical infrastructure and the existing undersized storage reservoir with a new storage reservoir that provides for sufficient storage volume to meet projected demand and fire flow. The project location is near the Scottsdale/Westland Road intersection and is a vital facility for supplying potable water to this portion of the city’s Water Service Area. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs City Fees Construction Contingency Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) MPC Bonds Water Rates Total: 237.6 48.8 3,860.0 684.8 300.0 48.8 5,180.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 2,830.0 2,350.0 5,180.0 (0.3) (0.3) 2,829.7 2,350.0 5,179.7 - - - - 2,829.7 2,350.0 5,179.7 Booster Station Upgrades - (WB76) Est. Completion: 12/24 Multiple locations Location: Project Type: Construction Related Description: Rehabilitate multiple potable water booster stations and associated equipment that have reached the end of their useful service lives. Many of these facilities were constructed by developers, are more than 25 years old and no longer meet current accepted design standards. Funding Sources (In thousands of dollars) MPC Bonds Water Rates Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 1,000.0 29,638.1 30,638.1 (9,441.0) (9,441.0) 1,000.0 6,697.1 7,697.1 2,500.0 2,500.0 3,000.0 3,000.0 4,000.0 4,000.0 4,000.0 4,000.0 1,000.0 20,197.1 21,197.1  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 184 - Table of Contents Water Improvements WATER MANAGEMENT | Water Improvements BPS 42D/E Transmission Capacity Expansion - (TEMP2089-F) Est. Completion: 06/23 Pima Road and Jomax Road Location: Project Type: Construction Related Description: Install a new transmission pipe to deliver water to northern reaches of the city. Transmission capacity expansion will be consistent with the Infrastructure Improvement Plan (IIP). The IIP is a written document per Arizona Revised Statute 9-463.05, identifying growth driven water and wastewater infrastructure needs that are funded with development fees. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs City Fees Construction Contingency Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) Water Development Fees Water Rates Total: 82.2 15.5 637.2 140.2 63.7 31.1 970.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 950.0 20.0 970.0 - - - 950.0 20.0 970.0 - - 950.0 20.0 970.0 Campus/Central Arizona Project Drainage & Paving Improvements (Water) - (WB73) Est. Completion: 06/20 Pima Road and Hualapai Drive Location: Project Type: Construction Related Description: Design and construct engineered drainage features throughout the Central Arizona Project (CAP) Water Treatment Plant property to collect and direct on-site stormwater to identified discharge points. Uncontrolled runoff currently contributes to nuisance flooding and risk to infrastructure during rainfall. On-site paving improvements have been identified to improve staff mobility throughout the site which contributes to improved safety, security and operational reliability. Funding Sources (In thousands of dollars) Water Rates Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 600.0 600.0 (571.6) (571.6) 28.4 28.4 - - - - 28.4 28.4  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 185 - Table of Contents Water Improvements WATER MANAGEMENT | Water Improvements Chaparral Water Treatment Plant Pretreatment - (WB56) Est. Completion: 06/21 Chaparral Water Treatment Plant Location: Project Type: Construction Related Description: Design and construct pretreatment infrastructure to improve operational performance given new challenges posed by deteriorating source water quality. Funds will be used to address infrastructure and operational needs to achieve compliance with tighter water quality regulations. Funding Sources (In thousands of dollars) Water Rates Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 18,654.1 18,654.1 (8,251.6) (8,251.6) 10,402.5 10,402.5 - - - - 10,402.5 10,402.5 Cluster 3 Arsenic Treatment - (WG04) Est. Completion: 06/22 Remote well sites north of the Scottsdale Water Campus Location: Project Type: Construction Related Description: Design and construct groundwater treatment infrastructure for arsenic treatment. Strengthen the resiliency of city water supply system in the event Central Arizona Project (CAP) water deliveries are reduced or interrupted, and for long-term supply reliability. Facilitate groundwater delivery from Cluster 3 wells into the potable water distribution system while achieving all regulatory water quality standards and city water quality operating goals. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs City Fees Construction Contingency Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) Water Rates Total: 480.0 120.0 5,020.0 1,000.0 600.0 280.0 7,500.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 7,500.0 7,500.0 - 7,500.0 7,500.0 - - - - 7,500.0 7,500.0  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 186 - Table of Contents Water Improvements WATER MANAGEMENT | Water Improvements Crossroads East Water - (WF06) Est. Completion: 06/20 74th Street to Hayden Road, North of the Arizona State Route 101 Location: Project Type: Construction Related Description: Construct water lines within the area consistent with a development agreement and the Infrastructure Improvement Plan (IIP). The IIP is a written document per Arizona Revised Statute 9-463.05, identifying growth driven water and wastewater infrastructure needs that are funded with development fees. Advance construction of streets within the Core North and Core South area by the city that will require concurrent installation of water lines to provide service for future adjacent development. These lines are normally installed by the development community and will be reimbursed via reimbursement agreements. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs City Fees Construction Contingency Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) Water Development Fees Water Rates Total: 556.8 139.2 6,492.3 1,255.0 570.4 278.4 9,292.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 9,155.3 136.6 9,292.0 (1.0) (0.2) (1.3) 9,154.3 136.4 9,290.7 - - - - 9,154.3 136.4 9,290.7  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 187 - Table of Contents Water Improvements WATER MANAGEMENT | Water Improvements Deep Well Recharge/Recovery Projects - (WF08) Est. Completion: 06/25 Multiple locations Location: Project Type: Construction Related Description: Design and construct deep well water recharge and recovery facilities to ensure long term sustainability of the city’s drinking water aquifer. The city uses this aquifer for both the long- and short-term storage of water and needs improved capacity to store more water to meet ‘Safe Yield’ and enhance drought preparedness. This program will determine the best areas for this to occur and design and construct wells to best meet the city’s needs. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Design/Construction Admin Total: Funding Sources (In thousands of dollars) Water Rates Total: 317.6 10,217.6 669.1 11,204.3 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 11,204.3 11,204.3 (50.4) (50.4) 9,088.3 9,088.3 - 375.0 375.0 - 1,690.6 1,690.6 11,153.9 11,153.9 East Dynamite Area Transmission Main - (WD01) Est. Completion: 06/20 East Dynamite Corridor and 116th Street Location: Project Type: Construction Related Description: Design and construct backbone piping in the East Dynamite Area along 116th Street to support growth and maintain a looped system on a regional level. The work associated with this piping will be consistent with the Infrastructure Improvement Plan (IIP). The IIP is a written document per Arizona Revised Statute 9-463.05, identifying growth driven water and wastewater infrastructure needs that are funded with development fees. Funding Sources (In thousands of dollars) MPC Bonds Water Development Fees Water Rates Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 350.0 1,827.0 4,450.0 6,627.0 (350.0) (1,073.2) (4.3) (1,427.6) 753.8 4,445.7 5,199.4 - - - - 753.8 4,445.7 5,199.4  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 188 - Table of Contents Water Improvements WATER MANAGEMENT | Water Improvements Frank Lloyd Wright 24-inch Transmission Main & Booster Station 83B Modifications - (WC03) Est. Completion: 06/20 Frank Lloyd Wright corridor from the vicinity of the Arizona State Route 101 and Bell Road to Shea Boulevard Location: Project Type: Construction Related Description: Design and construct approximately four miles of large diameter water transmission main in the Frank Lloyd Wright corridor east of the Arizona State Route 101. The new transmission main will improve the pumping capacity at Booster Station 83B and address existing low operational capacities and pressures in the east Shea Boulevard portion of the service area during peak summer water demand periods. Funding Sources (In thousands of dollars) MPC Bonds Water Rates Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 9,886.6 5,513.4 15,400.0 (9,792.9) (72.2) (9,865.1) 93.7 5,441.2 5,534.9 - - - - 93.7 5,441.2 5,534.9 Irrigation Water Distribution System Improvements - (WB57) Est. Completion: 06/23 Citywide Location: Project Type: Construction Related Description: Improve the Irrigation Water Distribution System (IWDS) pipeline, pump stations, reservoirs and recharge wells. This project will be fully funded by the golf courses receiving Central Arizona Project (CAP) water from the Water Campus through the IWDS. Funding Sources (In thousands of dollars) Irrigation Water Distribution System Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 4,750.0 4,750.0 (1,499.0) (1,499.0) 3,251.0 3,251.0 - - - - 3,251.0 3,251.0  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 189 - Table of Contents Water Improvements WATER MANAGEMENT | Water Improvements IWDS / Harquahala Valley Irrigation District Property - Desert Mountain Golf Club - (WB69) Est. Completion: 06/20 Irrigation Water Distribution System / Harquahala Valley Irrigation District Property Location: Project Type: Construction Related Description: Design and construct groundwater supply wells and a transmission pipeline from the wells to the Central Arizona Project (CAP) canal in the Harquahala Valley. This project will be fully funded by the golf courses receiving water through the Irrigation Water Distribution System (IWDS). Funding Sources (In thousands of dollars) Irrigation Water Distribution Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 20,092.0 20,092.0 (4,855.8) (4,855.8) 15,236.2 15,236.2 - - - - 15,236.2 15,236.2 IWDS / Harquahala Valley Irrigation District Property - Scottsdale National Golf Club - (WB80) Est. Completion: 06/20 Irrigation Water Distribution System / Harquahala Valley Irrigation District Property Location: Project Type: Construction Related Description: Design and construct groundwater supply wells and a transmission pipeline from the wells to the Central Arizona Project (CAP) canal in the Harquahala Valley. This project will be fully funded by a golf course receiving water through the Irrigation Water Distribution System (IWDS). Funding Sources (In thousands of dollars) Irrigation Water Distribution Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 4,345.0 4,345.0 (151.1) (151.1) 4,193.9 4,193.9 - - - - 4,193.9 4,193.9 Master Plan - Water - (WB78) Est. Completion: 06/24 Citywide Location: Project Type: Construction Related Description: Update integrated master plan to determine water system management needs including federal regulatory impacts and capital project needs. Master planning activities include condition assessment analyses of existing pipelines, reservoirs, pump stations and treatment facilities, as well as updating operating manuals and standard operating procedures. Provides for facility planning, land use planning, and project cost estimating. Facilitates updates to the water Infrastructure Improvement Plan (IIP) needed to define water development fees associated with growth. Funding Sources (In thousands of dollars) Water Rates Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 1,477.6 1,477.6 (211.1) (211.1) 1,211.5 1,211.5 - - - 55.0 55.0 1,266.5 1,266.5  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 190 - Table of Contents Water Improvements WATER MANAGEMENT | Water Improvements Radio Telemetry Monitoring Automation Citywide - Water - (WB60) Est. Completion: 12/24 Citywide Location: Project Type: Construction Related Description: Construct radio telemetry facilities at new and existing water facilities to continue to improve operational efficiency through automation. Funding Sources (In thousands of dollars) Water Rates Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 7,359.4 7,359.4 (2,296.6) (2,296.6) 2,092.8 2,092.8 900.0 900.0 1,000.0 1,000.0 1,000.0 1,000.0 70.0 70.0 5,062.8 5,062.8 Regional Recharge Basins - (WB74) Est. Completion: 06/20 Various locations Location: Project Type: Construction Related Description: Recharge the city's unused allocation of Central Arizona Project (CAP) water in the Central Arizona Water Conservation District’s (CAWCD) established Tonopah Desert Recharge Project, the Superstition Mountain Recharge Project, the Granite Reef Underground Storage Project and the Salt River Project Groundwater Savings Facility. Recharge in these facilities is critical due to forecasted persistent drought conditions and projected rise of CAP rates. These facilities provide cost effective direct recharge which results in water storage credits that can be used to offset groundwater pumping needed to meet customer demand during peak summer months or extended periods of drought. Total Project Cost Funding Sources (In thousands of dollars) Water Rates Total: ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 12,190.0 (10,146.2) 12,190.0 (10,146.2) 2,043.8 2,043.8 - - - - 2,043.8 2,043.8  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 191 - Table of Contents Water Improvements WATER MANAGEMENT | Water Improvements Rio Verde/128th Street Transmission Mains - (WG01) Est. Completion: 12/22 Rio Verde Drive and 128th Street Location: Project Type: Construction Related Description: Design and construct transmission main infrastructure identified by the Infrastructure Improvement Plan (IIP). The IIP is a written document per Arizona Revised Statute 9-463.05, identifying growth driven water and wastewater infrastructure needs that are funded with development fees. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs City Fees Construction Contingency Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) Water Development Fees Water Rates Total: 447.5 84.4 3,458.3 760.8 345.8 168.8 5,265.7 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 5,155.7 110.0 5,265.7 - 5,155.7 110.0 5,265.7 - - - - 5,155.7 110.0 5,265.7  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 192 - Table of Contents Water Improvements WATER MANAGEMENT | Water Improvements Site 42 Reservoir Storage Expansion - (WF02) Est. Completion: 06/22 Jomax Road and Pima Road Location: Project Type: Construction Related Description: Rehabilitate existing 2.5 million gallon (MG) Tank and construction of a new 2.5 MG tank. The work associated with these tanks will be consistent with the Infrastructure Improvement Plan (IIP). The IIP is a written document per Arizona Revised Statute 9-463.05, identifying growth driven water and wastewater infrastructure needs that are funded with development fees. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs City Fees Construction Contingency Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) Water Development Fees Water Rates Total: 251.2 47.8 1,958.7 430.9 195.9 95.6 2,980.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 2,920.0 60.0 2,980.0 (93.4) (93.4) 2,826.6 60.0 2,886.6 - - - - 2,826.6 60.0 2,886.6  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 193 - Table of Contents WATER MANAGEMENT | Water Improvements Water Improvements State Land Near Legend Trails I - (WF03) Est. Completion: 06/22 Legend Trails Parkway and Pima Road Location: Project Type: Construction Related Description: Design and construct transmission main infrastructure identified by the Infrastructure Improvement Plan (IIP). The IIP is a written document per Arizona Revised Statute 9-463.05, identifying growth driven water and wastewater infrastructure needs that are funded with development fees. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs City Fees Construction Contingency Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) Water Development Fees Water Rates Total: 468.5 89.6 3,672.9 808.0 367.3 179.2 5,585.5 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 5,475.5 110.0 5,585.5 - 5,475.5 5,475.5 110.0 110.0 - - - 5,475.5 110.0 5,585.5  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 194 - Table of Contents WATER MANAGEMENT | Water Improvements Water Improvements State Land Near Legend Trails II - (WF04) Est. Completion: 12/24 Pima Road and Legend Trails Parkway Location: Project Type: Construction Related Description: Design and construct transmission main infrastructure identified by the Infrastructure Improvement Plan (IIP). The IIP is a written document per Arizona Revised Statute 9-463.05, identifying growth driven water and wastewater infrastructure needs that are funded with development fees. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs City Fees Construction Contingency Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) Water Development Fees Water Rates Total: 1,760.0 119.2 4,886.0 1,074.9 488.6 238.4 8,567.1 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 7,284.0 1,283.1 8,567.1 - 7,284.0 7,284.0 150.0 150.0 - - 1,133.1 1,133.1 7,284.0 1,283.1 8,567.1  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 195 - Table of Contents Water Improvements WATER MANAGEMENT | Water Improvements Technology Master Plan Identified Water Projects - (WE02) Est. Completion: 06/23 Citywide Location: Project Type: Technology Related Description: Design and implement capital improvements identified in the Technology Master Plan. Recommended improvements will focus on the areas of Supervisory Control and Data Acquisition (SCADA) systems, integration of asset management with work order systems and communications implementation. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Contingency Design/Construction Admin Information Technology Total: Funding Sources (In thousands of dollars) Water Rates Total: 154.0 105.0 15.0 3,626.0 2,300.0 6,200.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 6,200.0 6,200.0 (541.5) (541.5) 4,808.5 4,808.5 - - 850.0 850.0 - 5,658.5 5,658.5 Thomas Groundwater Treatment Facility - (WC07) Est. Completion: 06/21 8600 East Thomas Road Location: Project Type: Construction Related Description: Design and construct a new Reverse Osmosis (RO) treatment facility which will receive and treat a side stream of product water discharged from the adjacent Central Groundwater Treatment Facility (CGTF). The added water RO treatment will eliminate existing complex blending plans, enhance groundwater availability, and establish more robust technology needed to address potential future regulations. The naturally occurring water hardness in the groundwater will be reduced to levels similar to water in the city’s water distribution system. Funding Sources (In thousands of dollars) MPC Bonds Water Rates Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 12,938.4 18,484.2 31,422.6 (1,162.5) (2,210.5) (3,373.0) 11,775.9 16,273.8 28,049.6 - - - - 11,775.9 16,273.8 28,049.6  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 196 - Table of Contents Water Improvements WATER MANAGEMENT | Water Improvements Water and Sewer System Optimization - (WB55) Est. Completion: 06/20 Citywide Location: Project Type: Construction Related Description: Develop optimization tools and strategies to prioritize surface water usage over groundwater usage, blending requirements and strategies associated with water quality conditions and challenges, varying seasonal demands and reliability, redundancy and fire flows and energy usage and costs. Funding Sources (In thousands of dollars) Sewer Rates Water Rates Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 600.0 1,458.6 2,058.6 (600.0) (981.9) (1,581.9) 476.7 476.7 - - - - 476.7 476.7 Water Campus Vadose Well Construction - (TEMP2091-F) Est. Completion: 12/21 Scottsdale Water Campus Location: Project Type: Construction Related Description: Construct eight new Vadose wells in existing recharge well field consistent with the Infrastructure Improvement Plan (IIP). The IIP is a written document per Arizona Revised Statute 9-463.05, identifying growth driven water and wastewater infrastructure needs that are funded with development fees. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Design/Construction Admin Total: Funding Sources (In thousands of dollars) Water Development Fees Water Rates Total: 167.0 2,815.0 285.0 3,267.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 3,200.0 67.0 3,267.0 - - 3,200.0 67.0 3,267.0 - - - 3,200.0 67.0 3,267.0  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 197 - Table of Contents Water Improvements WATER MANAGEMENT | Water Improvements Water Campus Vadose Well Rehabilitation - (WB79) Est. Completion: 12/23 Scottsdale Water Campus Location: Project Type: Construction Related Description: Rehabilitate Vadose Zone recharge wells at the Water Campus to cost effectively extend the useful life of these aging assets. The Vadose Well complex at the Water Campus serves to recharge advanced treated water for the purposes of future groundwater withdrawals. Systematic rehabilitation of the existing recharge wells will reinforce this sustainable practice. Funding Sources (In thousands of dollars) Water Rates Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 715.0 715.0 (40.4) (40.4) 674.6 674.6 - - - - 674.6 674.6 Water Distribution System Improvements - (WB77) Est. Completion: 12/24 Citywide Location: Project Type: Construction Related Description: Improve the water distribution system due to system aging, and increasing demands including downtown revitalization. The project includes replacement of mains, pressure regulating valves, meters and other valves, as well as the design and construction of new water mains at various locations throughout the distribution system to improve service and to reduce operating cost. Replacement of existing small mains (4-inches and smaller) is required to meet fire flow requirements as set forth by city ordinance. This project will also include inspection, design, repair and replacement of water storage reservoirs and pump stations as driven by findings from the Asset Management Program. Total Project Cost Funding Sources (In thousands of dollars) Water Rates Total: ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 72,694.2 (32,908.3) 72,694.2 (32,908.3) 14,785.9 14,785.9 6,000.0 6,000.0 5,000.0 5,000.0 7,000.0 7,000.0 7,000.0 7,000.0 39,785.9 39,785.9  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 198 - Table of Contents Water Improvements WATER MANAGEMENT | Water Improvements Water Fund Contingency - (ZE02) Est. Completion: N/A Citywide Location: Project Type: Construction Related Description: Provide budgetary appropriation set aside for water system emergencies or unforeseen expenditures not otherwise budgeted. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Contingency Total: Funding Sources (In thousands of dollars) Water Rates Total: 15,000.0 15,000.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 15,000.0 15,000.0 - 3,000.0 3,000.0 3,000.0 3,000.0 3,000.0 3,000.0 3,000.0 3,000.0 3,000.0 3,000.0 15,000.0 15,000.0 Water Impact Fees - (WC01) Est. Completion: 12/20 Citywide Location: Project Type: Construction Related Description: Perform a water development fee study and audit requirements as required per Arizona Revised Statute 9463.05. Funding Sources (In thousands of dollars) Water Development Fees Water Rates Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 220.0 5.0 225.0 (77.7) (0.1) (77.8) 142.3 4.9 147.2 - - - - 142.3 4.9 147.2 Water Meter Replacement Program - (WB66) Est. Completion: N/A Citywide Location: Project Type: Construction Related Description: Purchase and install automated water meter equipment and input into workorder and billing system. The city is in the process of a multi-year transition from conventional-read water meters to automated metering devices for all customers. Total Project Cost Funding Sources (In thousands of dollars) Water Rates Total: ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 24,414.0 (10,129.4) 24,414.0 (10,129.4) 3,924.6 3,924.6 3,230.0 3,230.0 3,230.0 3,230.0 2,230.0 2,230.0 1,670.0 1,670.0 14,284.6 14,284.6  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 199 - Table of Contents Water Improvements WATER MANAGEMENT | Water Improvements Water Participation Program - (WB54) Est. Completion: 06/25 Citywide Location: Project Type: Construction Related Description: Facilitate the extension of water lines as required by City Code. The program allows the city to administer payback agreements to assist single-family residences connecting to the city's water distribution system. These paybacks are settled in the future, and the funding outlays made through this program will be re-paid to the city with interest. Funding Sources (In thousands of dollars) Water Rates Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 2,200.0 2,200.0 (868.3) (868.3) 1,131.7 1,131.7 - 200.0 200.0 - - 1,331.7 1,331.7 Water Quality Lab Equipment Replacement - (WG05) Est. Completion: 06/23 Scottsdale Water Campus Laboratory Location: Project Type: Technology Related Description: Replace and acquire new laboratory equipment and software that is used for the analysis of drinking water, reclaimed water and advanced treated reclaimed water in the Water Quality Laboratory. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Machinery and Equipment Total: Funding Sources (In thousands of dollars) Water Rates Total: 200.0 800.0 1,000.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 1,000.0 1,000.0 - 1,000.0 1,000.0 - - - - 1,000.0 1,000.0  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 200 - Table of Contents Water Improvements WATER MANAGEMENT | Water Improvements Water Resources Impact Fees - (WC02) Est. Completion: N/A Citywide Location: Project Type: Construction Related Description: Perform a water resources development fee study and audit requirements as required per Arizona Revised Statute 9-463.05. Funding Sources (In thousands of dollars) Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget Water Rates Water Resource Development Fees Total: 5.0 220.0 225.0 (0.1) (76.7) (76.7) 4.9 143.3 148.3 - - - - 4.9 143.3 148.3 Water System Oversizing - (WF07) Est. Completion: 06/25 Citywide Location: Project Type: Construction Related Description: Provides funds for the city to oversize lines and facilities to meet future capacity according to the Water Master Plan standards. Residential owners and developers are required by City Code to extend water lines (typically an 8-inch water line) at the resident/developer cost, and the city wishes to use that opportunity to upsize the line to accommodate regional flows. The city pays the cost difference between the upsized line and the price the resident/developer would have paid to extend the water line in-kind. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Total: Funding Sources (In thousands of dollars) Water Rates Total: 17.0 783.6 800.6 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 800.6 800.6 - 450.6 450.6 - 50.0 50.0 150.0 150.0 150.0 150.0 800.6 800.6  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 201 - Table of Contents Water Improvements WATER MANAGEMENT | Water Improvements Water System Security Enhancement Projects - (WE03) Est. Completion: 12/24 Citywide Location: Project Type: Construction Related Description: Provides for security enhancements at water facilities identified in the Water Resources Vulnerability Assessment. This includes upgrades of existing prevention, detection and response systems as needed. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Construction Design/Construction Admin Total: Funding Sources (In thousands of dollars) Water Rates Total: 147.0 2,218.0 210.0 2,575.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 2,575.0 2,575.0 (734.7) (734.7) 415.3 415.3 450.0 450.0 375.0 375.0 350.0 350.0 250.0 250.0 1,840.3 1,840.3 Water Technology Master Plan - (WB72) Est. Completion: 12/22 Citywide Location: Project Type: Technology Related Description: Develop a ten-year master plan to examine current capabilities and condition of communications systems. The master plan will involve the development of a roadmap to update, standardize and maintain integrated control systems including Supervisory Control and Data Acquisition/Telemetry infrastructure. The master plan effort will evaluate hardware/software, as well as study overall system resiliency. Funding Sources (In thousands of dollars) Water Rates Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 810.0 810.0 (309.9) (309.9) 200.1 200.1 - 300.0 300.0 - - 500.1 500.1  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 202 - Table of Contents Water Improvements WATER MANAGEMENT | Water Improvements Water Treatment Facility Improvements - (WD04) Est. Completion: 12/24 Water Treatment Facilities - Central Arizona Project (CAP) Plant, Chaparral Water Plant and Arsenic Treatment Location: Facility Project Type: Construction Related Description: Improve the water treatment facilities due to aging components. This project will include minor design, maintenance and construction modifications to various water treatment plant infrastructure. In addition, design and replace pump stations and storage tanks will be conducted as identified in the Asset Management Program. Total Project Cost Funding Sources (In thousands of dollars) Water Rates Total: ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 34,550.0 (11,987.9) 34,550.0 (11,987.9) 9,062.1 9,062.1 1,000.0 1,000.0 1,500.0 1,500.0 5,500.0 5,500.0 5,500.0 5,500.0 22,562.1 22,562.1 Water Treatment Plant Membranes - (WB71) Est. Completion: 12/24 Water Treatment Plant membranes Location: Project Type: Construction Related Description: Replace water treatment membranes at the Chaparral Water Treatment Plant, Central Arizona Project (CAP) Water Treatment Plant and Advanced Water Treatment Plant. Funding Sources (In thousands of dollars) Water Rates Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 7,376.3 7,376.3 (2,865.6) (2,865.6) 2,012.9 2,012.9 - 475.0 475.0 822.8 822.8 1,200.0 1,200.0 4,510.7 4,510.7  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 203 - Table of Contents Water Improvements WATER MANAGEMENT | Water Improvements Well Site - In Crossroads East - North of the Arizona State Route 101 - (WF05) Est. Completion: 12/21 Between Scottsdale Road and Hayden Road, north of the Arizona State Route 101 Location: Project Type: Construction Related Description: Design and construct a new wells north of the Arizona State Route 101 near Hayden Road for recharge and recovery consistent with the Infrastructure Improvement Plan (IIP). The IIP is a written document per Arizona Revised Statute 9-463.05, identifying growth driven water and wastewater infrastructure needs that are funded with development fees. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs City Fees Construction Contingency Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) Water Development Fees Water Rates Total: 338.6 64.7 2,649.6 582.9 265.0 129.3 4,030.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 3,950.0 80.0 4,030.0 - 3,950.0 80.0 4,030.0 - - - - 3,950.0 80.0 4,030.0 Well Sites - (WB75) Est. Completion: 06/24 Multiple locations Location: Project Type: Construction Related Description: Design and construct new wells and upgrade existing wells to meet anticipated demands at locations determined consistent with the Master Plan. The city will need to replace existing wells once the well has reached its useful life. Funding Sources (In thousands of dollars) Water Rates Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 2,915.4 2,915.4 (197.8) (197.8) 917.6 917.6 1,200.0 1,200.0 200.0 200.0 200.0 200.0 200.0 200.0 2,717.6 2,717.6  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 204 - Table of Contents Water Improvements WATER MANAGEMENT | Water Improvements Well Sites Rehabilitation - (WB51) Est. Completion: 12/20 Citywide Location: Project Type: Construction Related Description: Analyze, chemically or mechanically clean and rehabilitate wells and associated facilities as necessary. The wells in the city provide a critical water supply and need to be in proper working order to support peak summer and future water demands. Funding Sources (In thousands of dollars) Water Rates Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 4,000.0 4,000.0 (2,498.6) (2,498.6) 1,501.4 1,501.4 - - - - 1,501.4 1,501.4 WestWorld Improvements - (WB58) Est. Completion: 06/25 McDowell Mountain Location: Project Type: Construction Related Description: Improve the McDowell Mountain Golf recharge recovery pipeline, pump stations reservoirs, and recharge wells. This project will be fully funded by the golf courses and city facilities receiving Central Arizona Project (CAP) water from the CAP Canal and delivered through the improvements. Funding Sources (In thousands of dollars) WestWorld Golf Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 1,850.0 1,850.0 (305.7) (305.7) 944.3 944.3 150.0 150.0 150.0 150.0 150.0 150.0 150.0 150.0 1,544.3 1,544.3  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 205 - Table of Contents WATER MANAGEMENT | Water Improvements Water Improvements Zone 14/16 Water System Improvements Phase 2 - (WF09) Est. Completion: 06/20 Carefree Highway and Bartlett Road Location: Project Type: Construction Related Description: Design and construct two potable water booster stations and a 500,000-gallon storage reservoir to meet projected customer demand and fire flow in the water service area known as Wildcat Hill. This area is located south of Cave Creek Road and east of Pima Road in north Scottsdale. The work will be consistent with the Infrastructure Improvement Plan (IIP). The IIP is a written document per Arizona Revised Statute 9-463.05, identifying growth driven water and wastewater infrastructure needs that are funded with development fees. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs Art in Public Places City Fees Construction Contingency Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) 2018 MPC Bonds Water Development Funds Water Development Fees Water Rates Total: 390.0 37.8 72.5 3,746.8 653.8 297.2 145.0 5,343.1 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 5,195.2 (943.3) 4,252.0 - - - - 4,252.0 19.1 128.8 5,343.1 (11.6) (954.9) 19.1 117.2 4,388.2 - - - - 19.1 117.2 4,388.2  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 206 - Table of Contents Water Improvements WATER MANAGEMENT | Water Improvements Zone 2 Water System Improvements - (WC05) Est. Completion: 06/20 East Shea Boulevard area Location: Project Type: Construction Related Description: Perform Zone 2 Water System Improvements. Prepare Site 36 for abandonment. Water for the east Shea Boulevard area will now be delivered by Site 124 and Site 114. Retire Reservoir 36, Booster Pump Station 36 and Booster Pump Station 37. Replace the pumps at Booster Pump Station 124 to more effectively and efficiently supply the surrounding pressure zones. New pipelines and Pressure Reducing Valve (PRV) will be designed to optimally supply Zone 3E and 5E. Replace assets at Booster Station 124 including electrical gear, generator, service entrance section, variable drives and appurtenances. Funding Sources (In thousands of dollars) MPC Bonds Water Rates Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 4,000.0 5,330.0 9,330.0 (3,939.6) (1,981.6) (5,921.2) 60.4 3,348.4 3,408.8 - - - - 60.4 3,348.4 3,408.8 Zone 3W Water System Improvements - (WD03) Est. Completion: 06/20 Hayden Road and Frank Lloyd Wright Boulevard west of the Arizona State Route 101 Location: Project Type: Construction Related Description: Design and construct water system improvements in the Airpark area due to growth driven capacity demands including the installation of 12-inch, 20-inch and 30-inch transmission mains. The improvements will help meet growing water demands due to projected increased densities in the greater Airpark region. The work will be consistent with the Infrastructure Improvement Plan (IIP). The IIP is a written document per Arizona Revised Statute 9-463.05, identifying growth driven water and wastewater infrastructure needs that are funded with development fees. Funding Sources (In thousands of dollars) Water Rates Total: Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 4,775.0 4,775.0 - 4,775.0 4,775.0 - - - - 4,775.0 4,775.0  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 207 - Table of Contents Water Improvements WATER MANAGEMENT | Water Improvements Zone 8 Jomax Road Transmission Line - (WG03) Est. Completion: 12/21 Jomax Road Location: Project Type: Construction Related Description: Install water transmission line for future growth according to the 2015 Water Master Plan and the Infrastructure Improvement Plan (IIP). The IIP is a written document per Arizona Revised Statute 9-463.05, identifying growth driven water and wastewater infrastructure needs that are funded with development fees. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs City Fees Construction Contingency Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) Water Development Fees Water Rates Total: 62.5 11.9 486.3 107.0 48.6 23.7 740.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 725.0 15.0 740.0 - 725.0 15.0 740.0 - - - - 725.0 15.0 740.0  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 208 - Table of Contents Water Improvements WATER MANAGEMENT | Water Improvements Zone 8-D Jomax Road Transmission Line - (WG02) Est. Completion: 12/21 Jomax Road Location: Project Type: Construction Related Description: Install Water Transmission line for future growth according to the 2015 Water Master Plan and the Infrastructure Improvement Plan (IIP). The IIP is a written document per Arizona Revised Statute 9-463.05, identifying growth driven water and wastewater infrastructure needs that are funded with development fees. Total Project Cost Funding by Expenditure Category (In thousands of dollars) Administrative Costs City Fees Construction Contingency Design/Construction Admin Salaries Total: Funding Sources (In thousands of dollars) Water Development Fees Water Rates Total: 79.7 15.2 621.8 136.8 62.2 30.3 946.0 Total Project Cost ITD Expenditures (Thru 06/19) Adopted 2019/20 Forecast 2020/21 Forecast 2021/22 Forecast 2022/23 Forecast 2023/24 Total Remaining Budget 927.0 19.0 946.0 - 927.0 19.0 946.0 - - - - 927.0 19.0 946.0  Project was partially or wholly funded with reallocated bond proceeds from MPC Series 2013 per Resolution 10335 and MPC2016-01.  Recurring Capital Maintenance Projects. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 209 - FY 2019/20 Adopted Budget City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 210 - Table of Contents Capital Improvement Plan APPENDIX | Budget Adoption Ordinance Financial Summary & Five Year Financial Forecast City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 211 - Table of Contents Capital Improvement Plan APPENDIX | Budget Adoption Ordinance Financial Summary & Five Year Financial Forecast City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 212 - Table of Contents Capital Improvement Plan APPENDIX | Budget Adoption Ordinance Financial Summary & Five Year Financial Forecast CITY OF SCOTTSDALE Summary Schedule of Estimated Revenues and Expenditures/Expenses Fiscal Year 2019/2020 Schedule A Fiscal Year 2019 Adopted/Adjusted Budgeted Expenditures/Expenses* 2019 Actual Expenditures/Expenses** 2020 Fund Balance/Net Position at July 1 2020 Primary Property Tax Levy 2020 SCH E E General Fund $328,605,508 Special Revenue Fund Debt Service Fund $77,418,762 $102,728,807 FUNDS Capital Project Trust & Agency Funds Funds $585,559,743 $30,312 Enterprise Internal Service Funds Funds` Total All Funds $225,197,364 $47,220,321 $1,366,760,817 $276,137,944 $66,747,214 $89,695,127 $563,959,543 $30,312 $150,368,378 $7,551,698 $1,154,490,216 $77,744,842 $59,998,484 $7,352,482 $266,595,297 $34,661 $78,471,436 $44,781,936 $534,979,138 B $32,617,000 $0 $0 $0 $0 $0 $251,471 $32,868,471 Secondary Property Tax Levy B $0 $0 $32,971,795 $0 $0 $0 $0 $32,971,795 2020 Estimated Revenues Other than Property Taxes C $282,988,079 $149,042,306 $6,729,522 $573,839,474 $30,800 $197,226,959 $10,504,990 $1,220,362,130 2020 Other Financing Sources D $0 $0 $0 $0 $0 $0 $0 $0 2020 Other Financing (Uses) D $0 $0 $0 $0 $0 $0 $0 $0 2020 Interfund Transfers In D $10,592,588 $1,510,000 $64,737,554 $88,788,617 $0 $3,885,000 $143,319 $169,657,078 2020 Interfund Transfers (Out) D $27,598,592 $74,201,748 $7,309,448 $9,020,000 $0 $48,825,245 $2,702,045 $169,657,078 2020 Reduction for Amounts Not Available: LESS: Amounts for Future Debt Retirement: 2020 Total Financial Resources Available $393,349,921 $209,040,790 $47,053,799 $840,434,771 $65,461 $275,698,395 $55,538,397 $1,821,181,534 2020 Budgeted Expenditures/Expenses $375,843,917 $77,909,790 $104,481,905 $702,290,625 $36,800 $229,932,242 $51,325,563 $1,541,820,842 E Expenditure Limitation Comparison 1. Budgeted expenditures 2. Add/subtract : estimated net reconciling items 3. Budgeted expenditures adjusted for reconciling items 4. Less: estimated exclusions 5. Amount subject to the expenditure limitation 6. EEC or voter-approved alternative expenditure limitation 2018/2019 $1,366,760,817 - 2019/2020 $1,541,820,842 - 1,366,760,817 1,541,820,842 (924,607,098) (1,084,040,528) 442,153,719 457,780,314 $491,225,949 $509,102,292 *Includes expenditure adjustments approved in FY 2018/2019 from Schedule E. **Incudes actual amounts as of the date the proposed budget was prepared, adjusted for estimated activity for the remainder of the fiscal year. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 213 - Table of Contents Capital Improvement Plan APPENDIX | Budget Adoption Ordinance Financial Summary & Five Year Financial Forecast 1. 2. 3. 4. CITY OF SCOTTSDALE Summary of Property Tax Levy and Property Tax Rate Information Fiscal Year 2019/2020 Schedule B Fiscal Year 2018/2019 Maximum allowable primary property tax levy. A.R.S. §42-17051(A) 31,562,188 Amount received from primary property taxation in the current year in excess of the sum of that year's maximum allowable primary property tax levy. A.R.S. §42-17102(A)(18) 32,620,972 0 Property tax levy amounts A. Primary property taxes 31,878,855 32,868,471 B. Secondary property taxes 34,214,874 32,971,795 C. Total property tax levy amounts 66,093,729 65,840,266 Property taxes collected* A. Primary property taxes (1) 2018/2019 levy 29,575,046 (2) Prior years' levies 443,626 (3) Total primary property taxes B. 5. Fiscal Year 2019/2020 30,018,672 Secondary property taxes (1) 2018/2019 levy 32,323,259 (2) Prior years' levies 484,849 (3) Total secondary property taxes 32,808,108 C. 62,826,780 Total property taxes collected Property tax rates A. City tax rate (1) Primary property tax rate 0.5316 0.5198 (2) Secondary property tax rate 0.5705 0.5214 (3) Total city tax rate 1.1021 1.0412 B. Special assessment district tax rates Secondary property tax rates - As of the date the tentative budget was prepared, the city was operating 355 special assessment districts (streetlight improvement districts) for which secondary property taxes are levied. For information pertaining to these special assessment districtsand their tax rates, please contact the City of Scottsdale City Treasurer Division. *Includes actual property taxes collected as of the date the proposed budget was prepared, plus estimated property tax collections for the remainder of the fiscal year. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 214 - Table of Contents Capital Improvement Plan APPENDIX | Budget Adoption Ordinance Financial Summary & Five Year Financial Forecast CITY OF SCOTTSDALE Summary by Fund of Revenues Other than Property Taxes Fiscal Year 2019/2020 Schedule C Budgeted Revenues 2018/2019 Source of Revenues Actual Revenues 2018/2019* Adopted Revenues 2019/2020 GENERAL FUND TAXES - LOCAL AUTOMOTIVE $18,086,342 $18,086,342 $19,233,419 CONSTRUCTION $10,330,194 $10,330,194 $11,701,952 DINING/ENTERTNMNT $11,676,679 $11,676,679 $13,032,111 FOOD STORES $7,636,112 $7,636,112 $9,622,545 HOTEL/MOTEL $7,563,102 $7,563,102 $7,924,333 MAJOR DEPT STORES $10,629,787 $10,629,787 $10,668,543 MISC RETAIL STORES $23,512,367 $23,512,367 $24,602,143 OTHER ACTIVITY $12,825,161 $12,825,161 $14,493,297 RENTAL $18,703,089 $18,703,089 $20,360,644 UTILITIES $5,115,400 $5,115,400 $5,126,010 ELECTRIC & GAS FRANCHISE $8,541,000 $8,541,000 $8,615,610 CABLE TV LICENSE FEE $4,143,700 $4,143,700 $4,164,419 SALT RIVER PROJECT IN LIEU $217,952 $217,952 $231,986 STORMWATER FEE $933,234 $933,234 $942,896 STORMWATER FEE - CIP TOTAL TAXES - LOCAL $2,170,000 $2,170,000 $3,258,742 $142,084,119 $142,084,119 $153,978,650 STATE SHARED REVENUES STATE SHARED SALES TAX $24,479,293 $24,479,293 $26,266,732 STATE SHARED INCOME TAX $30,278,353 $30,278,353 $33,082,812 AUTO LIEU TAX $10,899,543 $10,899,543 $11,413,102 $65,657,189 $65,657,189 $70,762,646 $4,902,586 $4,902,586 $5,014,885 TOTAL STATE SHARED REVENUES CHARGES FOR SERVICE/OTHER WESTWORLD EQUESTRIAN FACILITY FEES INTERGOVERNMENTAL AGREEMENTS $1,819,929 $1,819,929 $4,253,555 MISCELLANEOUS $1,583,201 $1,583,201 $1,278,966 PROPERTY RENTAL TOTAL CHARGES FOR SERVICE/OTHER $3,372,747 $3,372,747 $3,432,574 $11,678,463 $11,678,463 $13,979,980 LICENSE PERMITS & FEES BUSINESS & LIQUOR LICENSES $1,885,121 $1,885,121 $1,785,341 FIRE CHARGES FOR SERVICES $1,512,900 $1,512,900 $1,602,829 RECREATION FEES $4,306,882 $4,306,882 $4,596,893 $7,704,903 $7,704,903 $7,985,063 TOTAL LICENSE PERMITS & FEES FINES FEES & FORFEITURES COURT FINES $4,851,286 $4,851,286 $5,062,977 LIBRARY $466,950 $466,950 $447,300 PARKING FINES $251,884 $251,884 $260,289 PHOTO RADAR $2,264,853 $2,264,853 $2,414,903 $7,834,973 $7,834,973 $8,185,469 TOTAL FINES FEES & FORFEITURES City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 215 - Table of Contents Capital Improvement Plan APPENDIX | Budget Adoption Ordinance Financial Summary & Five Year Financial Forecast CITY OF SCOTTSDALE Summary by Fund of Revenues Other than Property Taxes Fiscal Year 2019/2020 Schedule C Budgeted Revenues 2018/2019 Source of Revenues Actual Revenues 2018/2019* Adopted Revenues 2019/2020 INTEREST EARNINGS INTEREST EARNINGS $3,574,918 $3,574,918 $5,007,189 $3,574,918 $3,574,918 $5,007,189 BUILDING & RELATED PERMITS $15,565,523 $15,565,523 $15,834,143 TOTAL BUILDING PERMIT FEES & CHARGES $15,565,523 $15,565,523 $15,834,143 $6,091,427 $6,091,427 $6,841,159 TOTAL INTEREST EARNINGS BUILDING PERMIT FEES & CHARGES INDIRECT/DIRECT COST ALLOCATIONS INDIRECT COSTS DIRECT COST ALLOCATION (FIRE) $383,500 $383,500 $413,780 TOTAL INDIRECT/DIRECT COST ALLOCATIONS $6,474,927 $6,474,927 $7,254,939 $260,575,015 $260,575,015 $282,988,079 TOTAL GENERAL FUND SPECIAL REVENUE FUNDS PRESERVATION FUNDS AUTOMOTIVE $5,754,745 $5,754,745 $6,119,724 CONSTRUCTION $3,286,880 $3,286,880 $3,723,349 DINING/ENTERTNMNT $3,715,307 $3,715,307 $4,146,581 FOOD STORES $2,429,672 $2,429,672 $3,061,719 HOTEL/MOTEL $2,406,441 $2,406,441 $2,521,379 MAJOR DEPT STORES $3,382,205 $3,382,205 $3,394,536 MISC RETAIL STORES $7,481,208 $7,481,208 $7,827,955 OTHER ACTIVITY $3,402,222 $3,402,222 $3,904,647 RENTAL $5,950,983 $5,950,983 $6,478,386 UTILITIES $1,627,628 $1,627,628 $1,631,003 INTEREST EARNINGS $686,217 $686,217 $1,066,651 TOTAL PRESERVATION FUNDS $40,123,508 $40,123,508 $43,875,930 AUTOMOTIVE $3,170,256 $3,170,256 $5,119,814 TRANSPORTATION FUND CONSTRUCTION $1,810,723 $1,810,723 $2,937,118 DINING/ENTERTNMNT $2,046,741 $2,046,741 $3,469,065 FOOD STORES $1,338,492 $1,338,492 $2,561,460 HOTEL/MOTEL $1,325,695 $1,325,695 $2,109,407 MAJOR DEPT STORES $1,863,237 $1,863,237 $2,839,898 MISC RETAIL STORES $4,121,355 $4,121,355 $6,548,933 OTHER ACTIVITY $1,874,265 $1,874,265 $3,266,662 RENTAL $3,278,362 $3,278,362 $5,419,874 UTILITIES $896,651 $896,651 $1,364,511 $15,495,713 $15,495,713 $16,944,055 LOCAL TRANSPORTATION ASSISTANCE FUND $655,000 $655,000 $655,000 INTERGOVERNMENTAL AGREEMENTS $150,000 $150,000 $150,000 MISCELLANEOUS $190,000 $190,000 $130,240 INDIRECT/DIRECT COST ALLOCATIONS $424,355 $424,355 $438,493 $38,640,845 $38,640,845 $53,954,530 HIGHWAY USER TAX TOTAL TRANSPORTATION FUND City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 216 - Table of Contents Capital Improvement Plan APPENDIX | Budget Adoption Ordinance Financial Summary & Five Year Financial Forecast CITY OF SCOTTSDALE Summary by Fund of Revenues Other than Property Taxes Fiscal Year 2019/2020 Schedule C Budgeted Revenues 2018/2019 Source of Revenues Actual Revenues 2018/2019* Adopted Revenues 2019/2020 TOURISM DEVELOPMENT FUND TRANSIENT OCCUPANCY TAX $20,413,217 $20,413,217 MISCELLANEOUS $20,500 $20,500 $0 PROPERTY RENTAL $1,910,000 $1,910,000 $1,999,114 $22,343,717 $22,343,717 $23,529,342 ELECTRIC & GAS FRANCHISE $243,000 $243,000 $251,675 INTERGOVERNMENTAL AGREEMENTS $203,937 $203,937 $203,937 MISCELLANEOUS $1,338,462 $1,338,462 $1,890,229 PROPERTY RENTAL $365,191 $365,191 $2,285,755 CONTRIBUTIONS & DONATIONS $295,015 $295,015 $416,850 BUSINESS & LIQUOR LICENSES $57,000 $57,000 $58,000 RECREATION FEES $2,052,590 $2,052,590 $2,693,753 COURT FINES $1,892,644 $1,892,644 $2,058,063 POLICE FEES $427,950 $427,950 $290,250 TOTAL TOURISM DEVELOPMENT FUND $21,530,228 SPECIAL PROGRAMS FUND INTEREST EARNINGS $113,986 $113,986 $176,579 TOTAL SPECIAL PROGRAMS FUND $6,989,775 $6,989,775 $10,325,091 $609,553 $609,553 $646,718 $609,553 $609,553 $646,718 INTERGOVERNMENTAL AGREEMENTS $14,284 $14,284 $0 PROPERTY RENTAL $39,000 $39,000 $63,732 CONTRIBUTIONS & DONATIONS $4,296,122 $4,296,122 $2,624,029 FEDERAL GRANTS $12,034,615 $12,028,855 $13,299,269 STATE GRANTS $474,537 $474,537 $723,665 TOTAL GRANT FUNDS $16,858,558 $16,852,798 $16,710,695 $125,565,956 $125,560,196 $149,042,306 SPECIAL DISTRICTS STREETLIGHT DISTRICTS TOTAL SPECIAL DISTRICTS GRANT FUNDS TOTAL SPECIAL REVENUE FUNDS ENDOWMENT FUNDS ENDOWMENTS CONTRIBUTIONS & DONATIONS TOTAL ENDOWMENTS TOTAL ENDOWMENT FUNDS $22,000 $22,000 $30,800 $22,000 $22,000 $30,800 $22,000 $22,000 $30,800 $7,120,422 $7,120,422 $6,059,522 DEBT SERVICE FUNDS DEBT INTERGOVERNMENTAL AGREEMENTS CONTRIBUTIONS & DONATIONS PROPERTY RENTAL TOTAL DEBT TOTAL DEBT SERVICE FUNDS $0 $0 $510,000 $170,000 $170,000 $160,000 $7,290,422 $7,290,422 $6,729,522 $7,290,422 $7,290,422 $6,729,522 City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 217 - Table of Contents Capital Improvement Plan APPENDIX | Budget Adoption Ordinance Financial Summary & Five Year Financial Forecast CITY OF SCOTTSDALE Summary by Fund of Revenues Other than Property Taxes Fiscal Year 2019/2020 Schedule C Budgeted Revenues 2018/2019 Source of Revenues Actual Revenues 2018/2019* Adopted Revenues 2019/2020 CAPITAL PROJECT FUNDS CAPITAL IMPROVEMENT PROGRAM ESTIMATED UNEXPENDED PRIOR YEAR $340,735,097 $340,735,097 $469,619,525 $340,735,097 $340,735,097 $469,619,525 $340,735,097 $340,735,097 $469,619,525 OTHER WATER REVENUE $2,250,000 $2,250,000 $2,250,000 OTHER WATER RECLAMATION REVENUE $2,400,000 $2,400,000 $2,400,000 NON-POTABLE WATER SERVICE CHARGES $1,500,000 $1,500,000 $1,500,000 INTERGOVERNMENTAL AGREEMENTS $23,280,666 $23,280,666 $33,574,757 TOTAL CAPITAL IMPROVEMENT PROGRAM TOTAL CAPITAL PROJECT FUNDS CAPITAL IMPROVEMENT PROJECT FUNDS CONTRIBUTIONS & DONATIONS INTEREST EARNINGS BUILDING & RELATED PERMITS $254,800 $254,800 $5,134,800 $3,323,949 $3,323,949 $5,237,047 $5,000 $5,000 $340,000 $6,620,745 FEDERAL GRANTS $8,648,628 $8,648,628 MISCELLANEOUS $363,000 $363,000 $0 BOND PROCEEDS $0 $0 $47,162,600 $42,026,043 $42,026,043 $104,219,949 TOTAL CAPITAL IMPROVEMENT PROJECT FUNDS ENTERPRISE FUNDS AVIATION FUND JET FUEL AIRPORT FEES PROPERTY RENTAL INTEREST EARNINGS TOTAL AVIATION FUND $168,558 $168,558 $146,000 $4,716,822 $4,716,822 $4,893,177 $104,090 $104,090 $171,947 $179,816 $179,816 $157,916 $5,169,286 $5,169,286 $5,369,040 WATER & WATER RECLAMATION FUNDS STORMWATER FEE $300,000 $300,000 $332,750 WATER SERVICE FEES $96,931,020 $96,931,020 $104,247,290 SEWER SERVICE FEES $40,516,000 $40,516,000 $45,239,400 NON-POTABLE WATER SERVICE CHARGES $12,840,140 $12,840,140 $14,419,683 MISCELLANEOUS $843,140 $843,140 $875,543 PROPERTY RENTAL $250,000 $250,000 $255,800 $4,500 $4,500 $5,500 $1,886,612 $1,886,612 $2,576,903 $929,000 $929,000 $947,540 $154,500,412 $154,500,412 $168,900,409 CONTRIBUTIONS & DONATIONS INTEREST EARNINGS INDIRECT COSTS TOTAL WATER & WATER RECLAMATION FUNDS SOLID WASTE FUND SOLID WASTE SERVICE CHARGES - COMMERCIAL $3,779,732 $3,779,732 $3,314,484 SOLID WASTE SERVICE CHARGES - RESIDENTIAL $17,493,127 $17,493,127 $19,383,182 INTEREST EARNINGS $210,919 $210,919 $259,844 TOTAL SOLID WASTE FUND $21,483,778 $21,483,778 $22,957,510 $181,153,476 $181,153,476 $197,226,959 TOTAL ENTERPRISE FUNDS City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 218 - Table of Contents Capital Improvement Plan APPENDIX | Budget Adoption Ordinance Financial Summary & Five Year Financial Forecast CITY OF SCOTTSDALE Summary by Fund of Revenues Other than Property Taxes Fiscal Year 2019/2020 Schedule C Budgeted Revenues 2018/2019 Source of Revenues Actual Revenues 2018/2019* Adopted Revenues 2019/2020 INTERNAL SERVICE FUNDS FLEET MANAGEMENT FUND INTERNAL SERVICE OFFSETS ($21,279,228) ($21,279,228) ($22,702,085) FUEL $4,003,740 $4,003,740 $3,567,160 MAINTENANCE & OPERATIONS $8,990,892 $8,990,892 $9,400,504 VEHICLE ACQUISITIONS $8,284,596 $8,284,596 $9,734,421 MISCELLANEOUS $433,273 $433,273 $450,000 REIMBURSEMENTS FROM OUTSIDE SOURCES $490,000 $490,000 $500,000 $923,273 $923,273 $950,000 INTERNAL SERVICE OFFSETS ($1,027,240) ($1,027,240) ($1,069,023) PC REPLACEMENT $1,027,240 $1,027,240 $1,069,023 $0 $0 $0 TOTAL FLEET MANAGEMENT FUND PC REPLACEMENT FUND TOTAL PC REPLACEMENT FUND SELF INSURANCE FUNDS INTERNAL SERVICE OFFSETS ($33,632,358) ($33,632,358) ($35,878,713) ($33,632,358) ($33,632,358) ($35,878,713) DISABLED RETIREE CONTRIBUTIONS $282,832 $282,832 $282,972 EMPLOYEE CONTRIBUTIONS - DENTAL $763,455 $763,455 $786,359 EMPLOYEE CONTRIBUTIONS - MEDICAL $7,713,405 $7,713,405 $7,613,343 TOTAL SELF INSURANCE FUNDS SELF INSURANCE FUNDS - HEALTH EMPLOYER CONTRIBUTION - DENTAL $877,326 $877,326 $931,400 EMPLOYER CONTRIBUTION - MEDICAL $23,155,032 $23,155,032 $24,347,313 $317,297 $317,297 $322,316 $33,109,347 $33,109,347 $34,283,703 MISCELLANEOUS TOTAL SELF INSURANCE FUNDS - HEALTH SELF INSURANCE FUNDS - RISK SELF INSURANCE (PROPERTY AND WORKERS COMP) $9,500,000 $9,500,000 $10,500,000 UNEMPLOYMENT CLAIMS $100,000 $100,000 $100,000 MISCELLANEOUS $75,000 $75,000 $100,000 REIMBURSEMENTS FROM OUTSIDE SOURCES TOTAL SELF INSURANCE FUNDS - RISK TOTAL INTERNAL SERVICE FUNDS TOTAL ALL FUNDS $325,000 $325,000 $450,000 $10,000,000 $10,000,000 $11,150,000 $10,400,262 $10,400,262 $10,504,990 $967,768,271 $967,762,511 $1,220,362,130 *Includes actual revenues recognized on the modified accrual or accrual basis as of the date the proposed budget was prepared, plus estimated expenditures for the remainder of the fiscal year. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 219 - Table of Contents Capital Improvement Plan APPENDIX | Budget Adoption Ordinance Financial Summary & Five Year Financial Forecast CITY OF SCOTTSDALE Summary by Fund Type of Other Financing Sources/(Uses) and Interfund Transfers Fiscal Year 2019/2020 Schedule D Other Financing Sources/(Uses) Adopted Interfund Transfers 2019/2020 2019/2020 Fund IN OUT $0 $10,592,588 $27,598,592 $0 $10,592,588 $27,598,592 $0 $0 $6,463 GENERAL FUND GENERAL FUND TOTAL GENERAL FUND SPECIAL REVENUE FUNDS GRANT FUNDS PRESERVATION FUNDS $0 $0 $37,185,127 SPECIAL PROGRAMS FUND $0 $10,000 $2,942,800 TOURISM DEVELOPMENT FUND $0 $0 $7,567,250 TRANSPORTATION FUND $0 $1,500,000 $26,500,108 $0 $1,510,000 $74,201,748 $0 $64,737,554 $7,309,448 $0 $64,737,554 $7,309,448 $0 $88,788,617 $9,020,000 $0 $88,788,617 $9,020,000 $0 $0 $0 $0 $0 $0 AVIATION FUND $0 $0 $2,365,142 SOLID WASTE FUND $0 $0 $496,444 WATER & WATER RECLAMATION FUNDS $0 $3,885,000 $45,963,659 $0 $3,885,000 $48,825,245 FLEET MANAGEMENT FUND $0 $0 $2,120,204 SELF INSURANCE FUNDS - HEALTH $0 $143,319 $0 SELF INSURANCE FUNDS - RISK $0 $0 $581,841 $0 $143,319 $2,702,045 $0 $169,657,078 $169,657,078 TOTAL SPECIAL REVENUE FUNDS DEBT SERVICE FUNDS DEBT TOTAL DEBT SERVICE FUNDS CAPITAL IMPROVEMENT PROJECT FUNDS CAPITAL IMPROVEMENT PROGRAM TOTAL CAPITAL IMPROVEMENT PROJECT FUNDS CAPITAL PROJECT FUNDS CAPITAL PROJECT FUND TOTAL CAPITAL PROJECT FUNDS ENTERPRISE FUNDS TOTAL ENTERPRISE FUNDS INTERNAL SERVICE FUNDS TOTAL INTERNAL SERVICE FUNDS TOTAL ALL FUNDS City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 220 - Table of Contents Capital Improvement Plan APPENDIX | Budget Adoption Ordinance Financial Summary & Five Year Financial Forecast CITY OF SCOTTSDALE Summary by Division Expenditures/Expenses Within Each Fund Type Fiscal Year 2019/2020 Schedule E Adopted Budget Expenditures 2018/2019 Fund/Divisions Expenditure Adjustments Approved 2018/2019 Actual Expenditures 2018/2019* Adopted Budget Expenditures 2019/2020 GENERAL FUND MAYOR AND CITY COUNCIL $663,553 $15,102 $678,655 $775,112 $7,063,005 $404,614 $7,467,619 $7,087,156 CITY AUDITOR $960,417 $61,990 $1,022,407 $1,032,637 CITY CLERK $1,038,391 $46,910 $1,085,301 $828,072 CITY COURT $4,785,513 $149,524 $4,935,037 $5,070,798 CITY MANAGER $3,311,057 $215,671 $3,526,728 $3,980,309 CITY TREASURER $9,146,685 $93,868 $9,240,553 $9,981,707 $15,159,728 CITY ATTORNEY ADMINISTRATIVE SERVICES $14,056,227 $375,725 $14,431,952 COMMUNITY AND ECONOMIC DEVELOPMENT $20,413,122 $264,655 $20,677,777 $20,840,692 COMMUNITY SERVICES $41,205,770 $937,617 $42,143,387 $42,432,873 PUBLIC SAFETY - FIRE $40,311,276 $1,175,999 $41,487,275 $45,167,730 PUBLIC SAFETY - POLICE $101,727,372 $3,012,992 $104,740,364 $106,475,691 PUBLIC WORKS $12,417,500 $5,077,154 $17,494,654 $13,006,852 COMPENSATION OTHER $5,661,107 ($5,654,722) $6,385 $5,242,688 DEBT SERVICE $2,890,748 $0 $2,890,748 $2,907,851 ESTIMATED DIVISION SAVINGS ($4,846,100) $4,620,288 ($225,812) ($5,800,000) LEAVE ACCRUAL PAYMENTS $2,033,500 ($1,153,293) $880,207 $2,094,505 PAY PROGRAM $3,959,682 ($3,900,822) $58,860 $3,712,936 $0 $275,631 $275,631 $0 $8,421,780 ($5,275,917) $3,145,863 $8,508,271 $829,857 ($655,504) $174,353 $732,855 CONTINGENCY / RESERVE APPROPRIATION $52,555,046 ($120,000) $0 $86,605,454 TOTAL GENERAL FUND $328,605,508 ($32,518) $276,137,944 $375,843,917 $328,605,508 ($32,518) $276,137,944 $375,843,917 NON DIVISIONAL $609,553 $0 $609,553 $638,890 TOTAL SPECIAL DISTRICTS $609,553 $0 $609,553 $638,890 PERSONNEL - OTHER UTILITIES VACATION TRADE TOTAL GENERAL FUND SPECIAL REVENUE FUNDS SPECIAL DISTRICTS SPECIAL PROGRAMS FUND $7,500 $0 $7,500 $28,000 CITY COURT MAYOR AND CITY COUNCIL $1,319,912 $48,552 $1,368,464 $1,202,824 COMMUNITY AND ECONOMIC DEVELOPMENT $1,780,000 $0 $1,780,000 $400,783 COMMUNITY SERVICES $3,044,129 $64,288 $3,108,417 $3,321,659 PUBLIC SAFETY - FIRE PUBLIC SAFETY - POLICE $2,180 $0 $2,180 $10,300 $2,635,617 $17,378 $2,652,995 $2,294,843 PUBLIC WORKS $300,666 $0 $300,666 $445,087 COMPENSATION OTHER $78,484 ($78,339) $145 $62,593 PAY PROGRAM $45,712 ($45,666) $46 $57,367 VACATION TRADE $6,226 ($6,226) $0 $5,703 CONTINGENCY / RESERVE APPROPRIATION $1,500,000 $0 $0 $1,500,000 TOTAL SPECIAL PROGRAMS FUND $10,720,426 ($13) $9,220,413 $9,329,159 City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 221 - Table of Contents Capital Improvement Plan APPENDIX | Budget Adoption Ordinance Financial Summary & Five Year Financial Forecast Adopted Budget Expenditures 2018/2019 Fund/Divisions Expenditure Adjustments Approved 2018/2019 Actual Expenditures 2018/2019* Adopted Budget Expenditures 2019/2020 GRANT FUNDS CITY MANAGER $1,200,000 $79,760 $1,279,760 $1,000,000 COMMUNITY SERVICES $10,558,324 $258,510 $10,816,834 $10,265,922 PUBLIC SAFETY - FIRE $157,517 $420,201 $577,718 $376,362 PUBLIC SAFETY - POLICE $305,353 $292,855 $598,208 $304,561 COMPENSATION OTHER $28,524 ($28,504) $20 $40,808 PAY PROGRAM $24,782 ($18,616) $6,166 $40,941 VACATION TRADE $3,717 ($1,617) $2,100 $4,278 CONTINGENCY / RESERVE APPROPRIATION $4,433,141 ($996,053) $0 $4,671,360 TOTAL GRANT FUNDS $16,711,358 $6,536 $13,280,806 $16,704,232 $53,904 $2,911 $56,815 $56,739 TRANSPORTATION FUND CITY TREASURER COMMUNITY SERVICES $1,855,653 $0 $1,855,653 $1,892,446 PUBLIC WORKS $23,705,007 $1,042,236 $24,747,243 $23,904,007 COMPENSATION OTHER $201,905 ($201,802) $103 $197,371 ESTIMATED DIVISION SAVINGS ($418,218) $389,527 ($28,691) ($370,900) LEAVE ACCRUAL PAYMENTS $148,728 ($85,482) $63,246 $104,100 PAY PROGRAM $153,530 ($134,117) $19,413 $149,088 $1,493,068 ($994,429) $498,639 $1,561,822 $33,803 ($18,844) $14,959 $29,942 CONTINGENCY / RESERVE APPROPRIATION $3,222,738 $0 $0 $3,252,462 TOTAL TRANSPORTATION FUND $30,450,118 $0 $27,227,380 $30,777,077 UTILITIES VACATION TRADE TOURISM DEVELOPMENT FUND COMMUNITY AND ECONOMIC DEVELOPMENT $16,392,452 $9,427 $16,401,879 $15,575,803 COMPENSATION OTHER $19,776 ($17,365) $2,411 $10,181 PAY PROGRAM $11,501 ($8,929) $2,572 $7,347 VACATION TRADE $1,378 ($1,378) $0 $713 CONTINGENCY / RESERVE APPROPRIATION $2,500,000 $0 $0 $4,866,388 TOTAL TOURISM DEVELOPMENT FUND $18,925,107 ($18,245) $16,406,862 $20,460,432 PRESERVATION FUNDS DEBT SERVICE $2,200 $0 $2,200 $0 TOTAL PRESERVATION FUNDS $2,200 $0 $2,200 $0 $77,418,762 ($11,722) $66,747,214 $77,909,790 DEBT SERVICE $89,695,127 $0 $89,695,127 $98,219,349 CONTINGENCY / RESERVE APPROPRIATION $13,033,680 $0 $0 $6,262,556 TOTAL DEBT $102,728,807 $0 $89,695,127 $104,481,905 $102,728,807 $0 $89,695,127 $104,481,905 COMMUNITY SERVICES $30,312 $0 $30,312 $36,800 TOTAL ENDOWMENTS $30,312 $0 $30,312 $36,800 $30,312 $0 $30,312 $36,800 TOTAL SPECIAL REVENUE FUNDS DEBT SERVICE FUNDS DEBT TOTAL DEBT SERVICE FUNDS ENDOWMENT FUNDS ENDOWMENTS TOTAL ENDOWMENT FUNDS City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 222 - Table of Contents Capital Improvement Plan APPENDIX | Budget Adoption Ordinance Financial Summary & Five Year Financial Forecast Adopted Budget Expenditures 2018/2019 Fund/Divisions Expenditure Adjustments Approved 2018/2019 Actual Expenditures 2018/2019* Adopted Budget Expenditures 2019/2020 ENTERPRISE FUNDS SOLID WASTE FUND CITY TREASURER $976,258 PUBLIC WORKS $14,878 $991,136 $983,383 $20,619,318 $19,588,076 $70,382 $19,658,458 COMPENSATION OTHER $241,201 ($240,800) $401 $189,301 ESTIMATED DIVISION SAVINGS ($482,808) $347,856 ($134,952) ($320,000) INDIRECT/DIRECT COST ALLOCATION $1,673,850 $1,509,058 $0 $1,509,058 LEAVE ACCRUAL PAYMENTS $88,844 ($47,769) $41,075 $20,000 PAY PROGRAM $161,787 ($113,878) $47,909 $164,487 UTILITIES $28,333 ($15,695) $12,638 $27,663 VACATION TRADE $22,941 ($16,093) $6,848 $20,000 CONTINGENCY / RESERVE APPROPRIATION $5,457,622 $0 $0 $5,764,439 TOTAL SOLID WASTE FUND $27,591,312 ($1,119) $22,132,571 $29,142,441 WATER & WATER RECLAMATION FUNDS CITY TREASURER $2,284,377 $59,221 $2,343,598 $2,340,933 WATER RESOURCES $65,510,753 $552,986 $66,063,739 $68,072,568 COMPENSATION OTHER $737,955 ($737,194) $761 $754,097 DEBT SERVICE $33,015,479 $0 $33,015,479 $33,155,258 ESTIMATED DIVISION SAVINGS ($1,152,600) $724,393 ($428,207) ($1,177,100) INDIRECT/DIRECT COST ALLOCATION $5,729,678 $0 $5,729,678 $6,331,873 LEAVE ACCRUAL PAYMENTS $466,001 ($99,720) $366,281 $466,001 PAY PROGRAM $508,007 ($448,610) $59,397 $450,761 $16,270,200 $0 $16,270,200 $16,599,046 $69,402 ($49,823) $19,579 $63,448 CONTINGENCY / RESERVE APPROPRIATION $65,854,431 $0 $0 $67,381,993 TOTAL WATER & WATER RECLAMATION FUNDS $189,293,683 $1,253 $123,440,505 $194,438,878 $2,255,179 $102,141 $2,357,320 $2,354,614 $56,328 ($56,328) $0 $42,258 $1,720,994 $0 $1,720,994 $1,722,744 ESTIMATED DIVISION SAVINGS ($30,000) $29,671 ($329) ($30,000) INDIRECT/DIRECT COST ALLOCATION $589,546 $0 $589,546 $632,267 LEAVE ACCRUAL PAYMENTS $16,500 ($1,749) $14,751 $16,500 PAY PROGRAM $33,605 ($27,871) $5,734 $25,801 UTILITIES $149,340 ($42,054) $107,286 $122,296 UTILITIES VACATION TRADE AVIATION FUND COMMUNITY AND ECONOMIC DEVELOPMENT COMPENSATION OTHER DEBT SERVICE VACATION TRADE $3,944 ($3,944) $0 $3,564 CONTINGENCY / RESERVE APPROPRIATION $3,516,933 $0 $0 $1,460,879 TOTAL AVIATION FUND $8,312,369 ($134) $4,795,302 $6,350,923 $225,197,364 $0 $150,368,378 $229,932,242 TOTAL ENTERPRISE FUNDS INTERNAL SERVICE FUNDS SELF INSURANCE FUNDS - RISK CITY ATTORNEY $9,082,245 $62,214 $9,144,459 $10,475,018 COMPENSATION OTHER $34,455 ($34,437) $18 $39,506 PAY PROGRAM $23,387 ($26,050) ($2,663) $23,212 VACATION TRADE $1,727 ($1,727) $0 $2,139 CONTINGENCY / RESERVE APPROPRIATION $22,612,358 $0 $0 $22,956,017 TOTAL SELF INSURANCE FUNDS - RISK $31,754,172 $0 $9,141,814 $33,495,892 City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 223 - Table of Contents Capital Improvement Plan APPENDIX | Budget Adoption Ordinance Financial Summary & Five Year Financial Forecast Adopted Budget Expenditures 2018/2019 Fund/Divisions Expenditure Adjustments Approved 2018/2019 Actual Expenditures 2018/2019* Adopted Budget Expenditures 2019/2020 FLEET MANAGEMENT FUND PUBLIC WORKS $21,130,307 $156,719 $21,287,026 COMPENSATION OTHER $159,197 ($159,098) $99 $22,804,203 $123,596 ESTIMATED DIVISION SAVINGS ($204,790) $102,057 ($102,733) ($170,000) INTERNAL SERVICE OFFSETS ($21,279,228) $0 ($21,279,228) ($22,702,085) LEAVE ACCRUAL PAYMENTS $32,568 ($5,000) $27,568 $20,000 PAY PROGRAM $91,860 ($87,095) $4,765 $92,071 VACATION TRADE $11,844 ($7,583) $4,261 $12,832 CONTINGENCY / RESERVE APPROPRIATION $6,787,739 $0 $0 $7,660,195 TOTAL FLEET MANAGEMENT FUND $6,729,497 $0 ($58,242) $7,840,812 ADMINISTRATIVE SERVICES $1,034,300 $0 $1,034,300 $1,069,023 INTERNAL SERVICE OFFSETS ($1,027,240) $0 ($1,027,240) ($1,069,023) CONTINGENCY / RESERVE APPROPRIATION $500,000 $0 $0 $500,000 TOTAL PC REPLACEMENT FUND $507,060 $0 $7,060 $500,000 PC REPLACEMENT FUND SELF INSURANCE FUNDS - HEALTH ADMINISTRATIVE SERVICES $32,088,110 $5,881 $32,093,991 $34,133,925 COMPENSATION OTHER $2,624 ($2,607) $17 $2,306 PAY PROGRAM $2,690 ($3,274) ($584) $2,860 CONTINGENCY / RESERVE APPROPRIATION $9,768,526 $0 $0 $11,228,481 TOTAL SELF INSURANCE FUNDS - HEALTH $41,861,950 $0 $32,093,424 $45,367,572 SELF INSURANCE FUNDS INTERNAL SERVICE OFFSETS ($33,632,358) $0 ($33,632,358) ($35,878,713) TOTAL SELF INSURANCE FUNDS ($33,632,358) $0 ($33,632,358) ($35,878,713) $47,220,321 $0 $7,551,698 $51,325,563 $563,959,543 $0 $563,959,543 $659,690,525 TOTAL INTERNAL SERVICE FUNDS CAPITAL PROJECT FUNDS CAPITAL IMPROVEMENT PROGRAM CAPITAL PROJECTS CONTINGENCY / RESERVE APPROPRIATION $21,600,200 $0 $0 $42,600,100 TOTAL CAPITAL IMPROVEMENT PROGRAM $585,559,743 $0 $563,959,543 $702,290,625 $585,559,743 $0 $563,959,543 $702,290,625 $1,366,760,817 ($44,240) $1,154,490,216 $1,541,820,842 TOTAL CAPITAL PROJECT FUNDS TOTAL ALL FUNDS *Includes actual expenditures recognized on the modified accrual or accrual basis as of the date the proposed budget was prepared, plus estimated expenditures for the remainder of the fiscal year. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 224 - Table of Contents Capital Improvement Plan APPENDIX | Budget Adoption Ordinance Financial Summary & Five Year Financial Forecast CITY OF SCOTTSDALE Summary by Division of Expenditures/Expenses Fiscal Year 2019/2020 Schedule F Adopted Budget Expenditures 2018/2019 Division/Fund Expenditure Adjustments Approved 2018/2019 Actual Expenditures 2018/2019* Adopted Budget Expenditures 2019/2020 MAYOR AND CITY COUNCIL GENERAL FUND $663,553 $15,102 $678,655 $7,500 $0 $7,500 $28,000 $671,053 $15,102 $686,155 $803,112 GENERAL FUND $7,063,005 $404,614 $7,467,619 $7,087,156 INTERNAL SERVICE FUND - SELF INSURANCE - RISK $9,082,245 $62,214 $9,144,459 $10,475,018 $16,145,250 $466,828 $16,612,078 $17,562,174 $960,417 $61,990 $1,022,407 $1,032,637 $960,417 $61,990 $1,022,407 $1,032,637 $1,038,391 $46,910 $1,085,301 $828,072 $1,038,391 $46,910 $1,085,301 $828,072 GENERAL FUND $4,785,513 $149,524 $4,935,037 $5,070,798 SPECIAL REVENUE FUND - SPECIAL PROGRAMS $1,319,912 $48,552 $1,368,464 $1,202,824 $6,105,425 $198,076 $6,303,501 $6,273,622 GENERAL FUND $3,311,057 $215,671 $3,526,728 $3,980,309 SPECIAL REVENUE FUND - GRANT $1,200,000 $79,760 $1,279,760 $1,000,000 $4,511,057 $295,431 $4,806,488 $4,980,309 $9,981,707 SPECIAL REVENUE FUND - SPECIAL PROGRAMS TOTAL MAYOR AND CITY COUNCIL $775,112 CITY ATTORNEY TOTAL CITY ATTORNEY CITY AUDITOR GENERAL FUND TOTAL CITY AUDITOR CITY CLERK GENERAL FUND TOTAL CITY CLERK CITY COURT TOTAL CITY COURT CITY MANAGER TOTAL CITY MANAGER CITY TREASURER GENERAL FUND $9,146,685 $93,868 $9,240,553 SPECIAL REVENUE FUND - TRANSPORTATION $53,904 $2,911 $56,815 $56,739 ENTERPRISE FUND - SOLID WASTE $976,258 $14,878 $991,136 $983,383 ENTERPRISE FUND - WATER & WATER RECLAMATION TOTAL CITY TREASURER $2,284,377 $59,221 $2,343,598 $2,340,933 $12,461,224 $170,878 $12,632,102 $13,362,762 $15,159,728 ADMINISTRATIVE SERVICES GENERAL FUND $14,056,227 $375,725 $14,431,952 INTERNAL SERVICE FUND - PC REPLACEMENT $1,034,300 $0 $1,034,300 $1,069,023 INTERNAL SERVICE FUND - SELF INSURANCE - HEALTH $32,088,110 $5,881 $32,093,991 $34,133,925 $47,178,637 $381,606 $47,560,243 $50,362,676 $20,840,692 TOTAL ADMINISTRATIVE SERVICES COMMUNITY AND ECONOMIC DEVELOPMENT GENERAL FUND $20,413,122 $264,655 $20,677,777 SPECIAL REVENUE FUND - SPECIAL PROGRAMS $1,780,000 $0 $1,780,000 $400,783 SPECIAL REVENUE FUND - TOURISM DEVELOPMENT $16,392,452 $9,427 $16,401,879 $15,575,803 ENTERPRISE FUND - AVIATION TOTAL COMMUNITY AND ECONOMIC DEVELOPMENT $2,255,179 $102,141 $2,357,320 $2,354,614 $40,840,753 $376,223 $41,216,976 $39,171,892 City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 225 - Table of Contents Capital Improvement Plan APPENDIX | Budget Adoption Ordinance Financial Summary & Five Year Financial Forecast Adopted Budget Expenditures 2018/2019 Division/Fund Expenditure Adjustments Approved 2018/2019 Actual Expenditures 2018/2019* Adopted Budget Expenditures 2019/2020 COMMUNITY SERVICES GENERAL FUND $41,205,770 $937,617 $42,143,387 $42,432,873 SPECIAL REVENUE FUND - GRANT $10,558,324 $258,510 $10,816,834 $10,265,922 SPECIAL REVENUE FUND - SPECIAL PROGRAMS $3,044,129 $64,288 $3,108,417 $3,321,659 SPECIAL REVENUE FUND - TRANSPORTATION $1,855,653 $0 $1,855,653 $1,892,446 ENDOWMENT FUND - ENDOWMENTS TOTAL COMMUNITY SERVICES $30,312 $0 $30,312 $36,800 $56,694,188 $1,260,415 $57,954,603 $57,949,700 $40,311,276 $1,175,999 $41,487,275 $45,167,730 $157,517 $420,201 $577,718 $376,362 $2,180 $0 $2,180 $10,300 $40,470,973 $1,596,200 $42,067,173 $45,554,392 $101,727,372 $3,012,992 $104,740,364 $106,475,691 $305,353 $292,855 $598,208 $304,561 $2,635,617 $17,378 $2,652,995 $2,294,843 $104,668,342 $3,323,225 $107,991,567 $109,075,095 $12,417,500 $5,077,154 $17,494,654 $13,006,852 $300,666 $0 $300,666 $445,087 $23,705,007 $1,042,236 $24,747,243 $23,904,007 $20,619,318 PUBLIC SAFETY - FIRE GENERAL FUND SPECIAL REVENUE FUND - GRANT SPECIAL REVENUE FUND - SPECIAL PROGRAMS TOTAL PUBLIC SAFETY - FIRE PUBLIC SAFETY - POLICE GENERAL FUND SPECIAL REVENUE FUND - GRANT SPECIAL REVENUE FUND - SPECIAL PROGRAMS TOTAL PUBLIC SAFETY - POLICE PUBLIC WORKS GENERAL FUND SPECIAL REVENUE FUND - SPECIAL PROGRAMS SPECIAL REVENUE FUND - TRANSPORTATION ENTERPRISE FUND - SOLID WASTE $19,588,076 $70,382 $19,658,458 INTERNAL SERVICE FUND - FLEET MANAGEMENT $21,130,307 $156,719 $21,287,026 $22,804,203 $77,141,556 $6,346,491 $83,488,047 $80,779,467 TOTAL PUBLIC WORKS WATER RESOURCES ENTERPRISE FUND - WATER & WATER RECLAMATION $65,510,753 $552,986 $66,063,739 $68,072,568 $65,510,753 $552,986 $66,063,739 $68,072,568 $563,959,543 $0 $563,959,543 $659,690,525 $7,221,556 ($7,211,196) $10,360 $6,704,705 CONTINGENCY / RESERVE APPROPRIATION $213,342,414 ($1,116,053) $0 $266,710,324 TOTAL WATER RESOURCES OTHER CAPITAL PROJECTS COMPENSATION OTHER DEBT SERVICE $127,324,548 $0 $127,324,548 $136,005,202 ESTIMATED DIVISION SAVINGS ($7,134,516) $6,213,792 ($920,724) ($7,868,000) INDIRECT/DIRECT COST ALLOCATION $7,828,282 $0 $7,828,282 $8,637,990 INTERNAL SERVICE OFFSETS ($55,938,826) $0 ($55,938,826) ($59,649,821) LEAVE ACCRUAL PAYMENTS $2,786,141 ($1,393,013) $1,393,128 $2,721,106 $609,553 $0 $609,553 $638,890 $5,016,543 ($4,814,928) $201,615 $4,726,871 $0 $275,631 $275,631 $0 $26,362,721 ($6,328,095) $20,034,626 $26,819,098 SPECIAL REVENUE FUND - SPECIAL DISTRICTS PAY PROGRAM PERSONNEL - OTHER UTILITIES VACATION TRADE TOTAL OTHER TOTAL ALL FUNDS $984,839 ($762,739) $222,100 $875,474 $892,362,798 ($15,136,601) $664,999,836 $1,046,012,364 $1,366,760,817 ($44,240) $1,154,490,216 $1,541,820,842 *Includes actual expenditures recognized on the modified accrual or accrual basis as of the date the proposed budget was prepared, plus estimated expenditures for the remainder of the fiscal year. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 226 - Table of Contents Capital Improvement Plan APPENDIX | Budget Adoption Ordinance Financial Summary & Five Year Financial Forecast CITY OF SCOTTSDALE Full-Time Employees and Personnel Compensation Fiscal Year 2019/2020 Schedule G Fund Total Adopted Personnel Compensation 2019/2020 Full-Time Equivalent (FTE) 2019/2020 Employee Salaries and Hourly Costs 2019/2020 1,982.63 $148,944,456 $33,719,252 $19,679,172 $10,514,840 $212,857,720 1,982.63 $148,944,456 $33,719,252 $19,679,172 $10,514,840 $212,857,720 Other Benefit Costs 2019/2020 Healthcare Costs 2019/2020 Retirement Costs 2019/2020 GENERAL FUND GENERAL FUND TOTAL GENERAL FUND SPECIAL REVENUE FUNDS GRANT FUNDS 21.00 $1,294,569 $168,932 $187,200 $86,660 $1,737,361 SPECIAL PROGRAMS FUND 37.05 $1,810,510 $184,291 $208,680 $134,401 $2,337,882 TOURISM DEVELOPMENT FUND 2.00 $228,192 $19,438 $29,496 $12,596 $289,722 TRANSPORTATION FUND 84.98 $5,840,583 $684,573 $968,832 $458,129 $7,952,117 145.03 $9,173,854 $1,057,234 $1,394,208 $691,786 $12,317,082 TOTAL SPECIAL REVENUE FUNDS ENTERPRISE FUNDS AVIATION FUND 15.47 $1,097,649 $123,350 $109,572 $82,097 $1,412,668 SOLID WASTE FUND 96.42 $6,043,366 $646,935 $1,019,040 $435,747 $8,145,088 WATER & WATER RECLAMATION FUNDS TOTAL ENTERPRISE FUNDS 229.90 $17,611,502 $1,982,938 $2,612,730 $1,314,852 $23,522,022 341.79 $24,752,517 $2,753,223 $3,741,342 $1,832,696 $33,079,778 $4,615,656 INTERNAL SERVICE FUNDS FLEET MANAGEMENT FUND 53.00 $3,339,712 $393,121 $620,400 $262,423 SELF INSURANCE FUNDS - HEALTH 0.00 $291,687 $0 $0 $0 $291,687 SELF INSURANCE FUNDS - RISK 9.00 $741,559 $81,876 $68,328 $55,098 $946,861 62.00 $4,372,958 $474,997 $688,728 $317,521 $5,854,204 2,531.45 $187,243,785 $38,004,706 $25,503,450 $13,356,843 $264,108,784 TOTAL INTERNAL SERVICE FUNDS TOTAL ALL FUNDS City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 227 - FY 2019/20 Adopted Budget City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 228 - Table of Contents Capital Improvement Plan APPENDIX Property Tax Levy Ordinance Financial | Summary & Five Year Financial Forecast ORDINANCE NO. 4408 AN ORDINANCE OF THE CITY OF SCOTTSDALE, MARICOPA COUNTY, ARIZONA, LEVYING UPON THE ASSESSED VALUATION OF THE PROPERTY WITHIN THE CITY OF SCOTTSDALE SUBJECT TO TAXATION, A CERTAIN SUM UPON EACH ONE HUNDRED DOLLARS ($100.00) OF ASSESSED VALUATION SUFFICIENT TO RAISE THE AMOUNT ESTIMATED TO BE REQUIRED IN THE ANNUAL BUDGET, LESS THE AMOUNT ESTIMATED TO BE RECEIVED FROM OTHER SOURCES OF REVENUE; FIXING THE PRIMARY PROPERTY TAX RATE AND SECONDARY PROPERTY TAX RATE; PROVIDING FUNDS FOR THE VARIOUS BOND REDEMPTIONS FOR THE PURPOSE OF PAYING PRINCIPAL OF AND INTEREST UPON BONDED INDEBTEDNESS; AND PROVIDING FUNDS FOR GENERAL MUNICIPAL EXPENSES; ALL FOR THE FISCAL YEAR ENDING THE 30TH DAY OF JUNE, 2020. WHEREAS, by the provisions of the City Charter and State statutes, an ordinance is required to set the property tax levy for the fiscal year beginning July 1, 2019, and ending June 30, 2020; WHEREAS, the County of Maricopa is the assessing and collecting authority for the City of Scottsdale; WHEREAS, the required public hearing was held on June 11, 2019, and the City Council made the following policy decisions relating to the primary property taxes: a. Accepted increasing the levy by the two percent (2%) maximum legal amount for fiscal year 2019/20; and b. Increased the levy amount to account for two hundred fifty-one thousand four hundred and seventy-one dollars ($251,471) for tort claim payments for calendar year 2018; and now, therefore, BE IT ORDAINED by the Council of the City of Scottsdale as follows: Section 1. The foregoing recitals are incorporated as if fully set forth herein. Section 2. There is hereby levied on each one hundred and no/100 dollars ($100.00) of assessed valuation of all property, both real and personal, within the corporate limits of the City of Scottsdale, except such property as may be by law exempt from taxation, a primary property tax levy not to exceed the maximum levy allowed by law for the fiscal year ending June 30, 2020, and allowable tort liability claims. The total primary levy is thirty-two million eight hundred sixty­ eight thousand four hundred forty-three dollars ($32,868,443), resulting in a tax rate of $0.5198 per one hundred and no/100 dollars ($100.00) of assessed value. Said figure is subject to change only if a court decision were to reduce the net assessed valuation in a significant manner. Ordinance No. 4408 Page 1 of 2 City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 229 - Table of Contents Capital Improvement Plan APPENDIX Property Tax Levy Ordinance Financial | Summary & Five Year Financial Forecast Section 3. In addition to the rate set in Section 2 above, there is hereby levied on each one hundred and no/100 dollars ($100.00) of assessed valuation of all property, both real and personal, within the corporate limits of the City of Scottsdale, except such property as may be, by law, exempt from taxation, a secondary property tax rate of $0.5214 per one hundred and no/100 dollars ($100.00) of assessed value, which is a rate sufficient to raise the sum of thirty­ two million nine hundred seventy-one thousand seven hundred and ninety-five dollars ($32,971,795) for the purpose of providing a bond interest and redemption fund for General Obligation debt service for the fiscal year ending June 30, 2020. Section 4. Failure by the county officials of Maricopa County, Arizona, to properly return the delinquent list, any irregularity in assessments or omission in the same, or any irregularity in any proceedings shall not invalidate such proceedings or invalidate any title conveyed by any tax deed; failure or neglect of any officer(s) to timely perform any of the assigned duties shall not invalidate any proceedings or any deed or sale pursuant thereto; the validity of the assessment or levy of taxes or of the judgment of sale by which the collection of the same may be enforced shall not affect the lien of the City of Scottsdale upon such property for the delinquent taxes unpaid thereon, and no overcharge as to part of the taxes or of costs shall invalidate any proceedings for the collection of taxes or the foreclosure; and all acts of officers de facto shall be valid as if performed by officers de jure. Section 5. The City Clerk or designee is hereby authorized and directed to transmit a certified copy of this ordinance to the Maricopa County Assessor and the Maricopa County Board of Supervisors. Section 6. repealed. All ordinances and parts of ordinances in conflict herewith are hereby PASSED AND ADOPTED by the Council of the City of Scottsdale, Maricopa County, Arizona, this 25th day of June, 2019. rk APPROVED AS O FORM: C{hrJ(_£QQ_sL__ Bruce Washburn, City Attorney By: Kimberly Campbell, Assistant City Attorney Ordinance No. 4408 Page 2 of2 City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 230 - Appendix ACJC ADA ADEQ ADMIN ADOR ADOT ADWR AFG AIPP ALCP AMI/AMR APS ARS ASRS ASST ASU ASUF AWT AZPOST AZSTA BOR C&ED CAD CAFR CAO CAP CAWCD CBT CCTV CDBG CDL CE CEF CEO CFD CGTF CII CIP CMOM CMRC CNG COBRA COP COR COS CPM CPR Table of Contents Capital Improvement Plan APPENDIX | Acronyms Financial Summary & Five Year Financial Forecast Acronyms/Abbreviations Arizona Criminal Justice Commission Americans with Disabilities Act Arizona Department of Environmental Quality Administrator/Administration Arizona Department of Revenue Arizona Department of Transportation Arizona Department of Water Resources Assistance to Firefighters Grant Art in Public Places Arterial Life Cycle Program Advanced Metering Infrastructure/Automatic Meter Reading Arizona Public Service Arizona Revised Statutes Arizona State Retirement System Assistant Arizona State University Arizona State University Foundation Advanced Water Treatment Arizona Peace Officer Standards and Training Board Arizona Sports and Tourism Authority Bureau of Reclamation Community & Economic Development Computer Aided Dispatch Comprehensive Annual Financial Report Community Assistance Office Central Arizona Project Central Arizona Water Conservation District Computer Based Training Closed Circuit Television Community Development Block Grant Commercial Driver’s License Continuing Education Court Enhancement Fund Chief Executive Officer Community Facility District Central Groundwater Treatment Facility Commercial, Industrial and Institutional Capital Improvement Plan Capacity, Management, Operations and Maintenance Capital Management Review Committee Compressed Natural Gas Consolidated Omnibus Budget Reconciliation Act Certificate of Participation Cost of Risk City of Scottsdale Capital Project Management Cardiopulmonary Resuscitation City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 231 - Appendix CY DIR DNA DUI DV EMS EMT EOC EPA EEC ESL EXEC FAA FCV FEMA FRC FT FTE FTG FY GAAP GAIN GASB GF GFOA GIS GO GOHS HB HEAT HMO HR HRIS HUD HURF HVAC HVID IBNR ICMA ID IDA IFR IGA IIP I/LEADS ISO IT Table of Contents Capital Improvement Plan APPENDIX | Acronyms Financial Summary & Five Year Financial Forecast Acronyms/Abbreviations Calendar Year Director Deoxyribonucleic Acid Driving Under the Influence Domestic Violence Emergency Medical Services Emergency Medical Technician Emergency Operations Center Environmental Protection Agency Economic Estimates Commission English as a Second Language Executive Federal Aviation Administration Full Cash Value Federal Emergency Management Agency Family Resource Center Full Time Full Time Equivalents Fill the Gap Fiscal Year Generally Accepted Accounting Principles Getting Arizona Involved in Neighborhoods Governmental Accounting Standards Board General Fund Government Finance Officers Association Geographic Information System General Obligation Governor’s Office of Highway Safety House Bill High Enforcement Arrest Team Health Maintenance Organization Human Resources Human Resources Information System U.S. Department of Housing and Urban Development Highway User Revenue Fund Heating, Ventilation, and Air Conditioning Harquahala Valley Irrigation District Incurred but Not Reported International City/County Management Association Improvement District Industrial Development Authority Instrument Flight Rules Intergovernmental Agreement Infrastructure Improvement Plan Intergraph/Law Enforcement Automated Defense Systems Insurance Service Organization Information Technology City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 232 - Appendix ITD ITS IWDS IWMS JAAB JCEF LED LIMS LUA MAG MCFCD MCSD MG MGR MISC MPC MPS MS4 MVD NACSLB NCHIP NFPA NPDES OOJC OP OPS OSB OSHA PAYGO PC PCI PGM/PROG PPO PRR PRV PSPRS PT Q1/2/3/4 REACT REC REP REV RFID RICO RO RMS RPTA Table of Contents Capital Improvement Plan APPENDIX | Acronyms Financial Summary & Five Year Financial Forecast Acronyms/Abbreviations Inception to Date Intelligent Transportation System Irrigation Water Distribution System Integrated Workplace Management System Judicial Appointments Advisory Board Judicial Collections Enhancement Fund Light-Emitting Diode Laboratory Information Management System Land Use Assumptions Maricopa Association of Governments Maricopa County Flood Control District Maricopa County Stadium District Million Gallon Manager Miscellaneous Municipal Property Corporation Mobile for Public Safety Municipal Separate Storm Sewer System Motor Vehicle Division National Advisory Council on State and Local Budgeting National Criminal Historic Improvement Program National Fire Protection Association National Pollution Discharge Elimination System Out of Jurisdiction Confinement Operator Operations Operations Services Bureau Occupational Safety and Health Administration Pay-As-You-Go Personal Computer Pavement Condition Index Program Preferred Provider Organization Public Records Request Pressure Reducing Valve Public Safety Personnel Retirement System Part Time Quarters 1, 2, 3 and/or 4 Regional Emergency Action Coordinating Team Recreation Representative Revenue Radio Frequency Identification Device Racketeering Influenced Corrupt Organizations Reverse Osmosis Records Management System Regional Public Transit Authority City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 233 - Appendix ROSC RV RWDS SAI SB SCADA SFD SHC SOD SPA SPD SPEC SR SRO SROG SRP SRPMIC STEAM SUPV SVC SW TECH TEFAP TGTF TMC TNEC TPC UCR WAN WIIP WTP YTD Table of Contents Capital Improvement Plan APPENDIX | Acronyms Financial Summary & Five Year Financial Forecast Acronyms/Abbreviations Return of Spontaneous Circulation Recreation Vehicle Reclaimed Water Distribution System Southern Avenue Interceptor Senate Bill Supervisory Control and Data Acquisition Scottsdale Fire Department Scottsdale Heritage Connection Special Operations Division Scottsdale Preserve Authority Scottsdale Police Department Specialist Senior Salt River Outfall Sub Regional Operating Group Salt River Project Salt River Pima-Maricopa Indian Community Science, Technology, Art and Math Supervisor Service Software Technician The Emergency Food Assistance Program Thomas Groundwater Treatment Facility Traffic Management Center Tony Nelssen Equestrian Center Tournament Players Club Uniform Crime Reporting Wide Area Network Water Infrastructure Improvement Plan Water Treatment Plant Year to Date City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 234 - Appendix Table of Contents Capital Improvement Plan |Glossary Glossary Financial SummaryAPPENDIX & Five Year Financial Forecast Accrual Basis – A basis of accounting whereby transactions are recognized when they are incurred, as opposed to when cash is received or paid. Actual – As used in the fund summaries and division summaries within the budget document, represents the actual cost results of operations. This category is presented on a modified accrual basis, with the exception that depreciation and amortization are not budgeted and principal payments on debt in the enterprise funds are budgeted as expenses. Adopted – As used in the fund summaries and division summaries within the budget document, represents the budget as approved by formal action of the City Council. Appropriation – An authorization made by the City Council, which permits the city to incur obligations and to expend resources for specific purposes. Assessed Valuation – A value that is established annually by the county assessor for real and personal property as a basis for levying taxes. Balanced Budget – Arizona State law requires a “balanced” budget, which is “all-inclusive”. Arizona State Revised Statute (42-17151) defines a “balanced” budget as follow: “Fix, levy and assess the amount to be raised from primary property taxation and secondary property taxation. This amount, plus all other sources of revenue, as estimated, and unencumbered balances from the preceding fiscal year, shall equal the total of amounts proposed to be spent in the budget for the current fiscal year.” Under Arizona State law “all-inclusive” means if an item is not budgeted (i.e. does not have an appropriation), it cannot legally be spent during the fiscal year. Therefore, the budget must include sufficient appropriation provisions for expenditures related to revenues (e.g., possible future grants) that cannot be accurately determined or even anticipated when the budget is adopted in June. This budgetary flexibility allows the city to comply with the Arizona state law and to pro-actively pursue emerging revenue sources as the budget year unfolds. The contingent expenditure appropriations associated with items such as possible future grants/revenues may not be spent without prior City Council approval during a public meeting. Base Budget – Cost of continuing the existing levels of service in the current budget year. Beginning Balance – The residual funds brought forward from the previous fiscal year (ending balance). Bond 2000 – General Obligation Bonds that were authorized by voters in calendar year 2000 and are secured by the full faith and credit of the issuer. General Obligation Bonds issued by local units of government are secured by a pledge of the issuer’s property taxing power and must be authorized by the electorate. Bond 2015 – General Obligation Bonds that were authorized by voters in calendar year 2015 and are secured by the full faith and credit of the issuer. General Obligation Bonds issued by local units of government are secured by a pledge of the issuer’s property taxing power and must be authorized by the electorate. Bond Funds – Established to account for bond proceeds to be used only for approved bond projects. Bonds – Debt instruments, which require repayment of a specified principal amount on a certain date (maturity date), together with interest at a stated rate or according to a formula for determining the interest rate. Bond Rating – The measure of the quality and safety of a bond. It indicates the likelihood that a debt issuer will be able to meet scheduled repayments and dictates the interest rate paid. Budget – A plan of financial operation embodying an estimate of proposed expenditures and the means of financing them. Used without any modifier, the term usually indicates a financial plan for a single fiscal year. In practice, the term budget is used in two ways. Sometimes it designates the financial plan presented for adoption and other times it designates the plan finally approved. It is usually necessary to specify whether the budget under consideration is preliminary and tentative, or whether the appropriating body has approved it. Budget Calendar – The schedule of key dates, which a government follows in the preparation and adoption of the budget. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 235 - Appendix Table of Contents Capital Improvement Plan |Glossary Glossary Financial SummaryAPPENDIX & Five Year Financial Forecast Budgetary Basis – Budgets are adopted on a basis consistent with generally accepted accounting principles (GAAP), with the exception that (1) no depreciation is budgeted for proprietary funds; and (2) bond principal in the enterprise funds is subject to appropriation. The budgetary basis of accounting is used to present all proposed budget and forecast amounts in the budget document to facilitate meaningful comparisons. Capital Expenditures – The city defines a capital expenditure as using the following three criteria: (1) relatively high monetary values (equal to or greater than $25,000), (2) long asset life (equal to or greater than five years of useful life, and (3) results in the creation of a capital asset, or the revitalization of a capital asset. Capital Improvement Funds – Established to account for financial resources to be used for the acquisition or construction of major capital facilities. The city maintains several capital project funds to ensure appropriate legal compliance and financial management for various restricted revenues. Capital Improvement Plan (CIP) – A comprehensive plan that annually forecasts the capital needs of the City of Scottsdale for a period of five years. The CIP is essential to the city’s comprehensive financial planning process and fundamental in upholding the city’s sound infrastructure. The annual adopted capital budget is derived from the CIP five-year forecast. Capital Outlay – Includes the purchase of land, the purchase or construction of buildings, structures, and facilities of all types, and the acquisition of machinery and equipment. It includes expenditures that result in the acquisition or addition of a fixed asset or increase the capacity, efficiency, span of life, or economy of operating an existing fixed asset. For an item to qualify as a capital outlay expenditure it must meet all of the following requirements: (1) have an estimated useful life of more than two years; (2) typically have a unit cost of $10,000 or more; and (3) be a betterment or improvement. Replacement of a capital item is classified as a capital outlay under the same code as the original purchase. Replacement or repair parts are classified under commodities. Capital Project – Any project having assets of significant value and having a useful life of five years or more. Capital projects include the purchase of land, design, engineering and construction of buildings, and infrastructure items such as streets, bridges, drainage, street lighting, and water systems. Commodities – Expendable items purchased through the city-approved centralized purchasing process. Examples of commodities include supplies, repair and replacement parts, and small tools. Community Facilities Districts (CFD) – CFDs are special purpose public improvement districts. By utilizing a variety of public funding options such as bonds, special assessments, taxes and user fees, CFDs provide a mechanism to finance public infrastructure, the operation and maintenance of public infrastructure, and enhanced municipal services in qualifying areas. Contingency – A budgetary reserve set aside for emergencies or unforeseen expenditures not otherwise budgeted. Contracts Payable – A liability reflecting amounts due on contracts of goods or services furnished to the city. Contractual Services – Expenditures for services performed by non-city firms or individuals, or by other city divisions. Cost Center – An organizational budget/operating unit within each city division. Court Enhancement Fund – A fund to accumulate fees imposed by the City Court on fines, sanctions, penalties and assessments for the purpose of enhancing the technological, operational and security capabilities of the City Court. Debt Service – Payment of principal, interest, and related service charges on obligations resulting from the issuance of bonds. Debt Service Funds – Funds established to account for the accumulation of resources and for the payment of general long-term debt principal and interest that are not serviced by the General, Special Revenue, or Enterprise Funds. They do not include contractual obligations accounted for in the individual funds. Department – A functional unit within a division consisting of one or more cost centers engaged in activities supporting the unit’s mission and objectives. Division – The combination of departments and programs of the city with a specific and unique set of goals and objectives (i.e., Public Works, Community Services, etc.). City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 236 - Appendix Table of Contents Capital Improvement Plan |Glossary Glossary Financial SummaryAPPENDIX & Five Year Financial Forecast Ending Balance – The residual funds that are spendable or available for appropriation at the end of the fiscal year. Enterprise Capital Funds – Funds used to account for utility rates and development fees for specific projects. Enterprise Funds – Funds established to account for operations, including debt service that are financed and operated similarly to private businesses - where the intent is the service is self-sufficient, with all costs supported predominantly by user charges. The city maintains three Enterprise Funds to account for Water & Water Reclamation, Solid Waste, and Aviation activities. Estimate – Represents the original adopted budget plus any contingency transfers, approved changes, and anticipated year-end savings. Excise Debt – Debt that is repaid by excise taxes. In this case, the excise taxes used to fund the debt service payments are a portion of the sales tax and transient occupancy tax. Expenditure – Outlay of funds for obtaining assets or goods and services. Expenditures represent decreases in net financial resources. Expenditure Limitation – An amendment to the Arizona State Constitution limiting annual expenditures for all municipalities. The Arizona Economic Estimates Commission sets the limit based on population growth and inflation. Fees – Charges for specific services. Financial Policy – A government’s directive with respect to operating, capital and reserve management and financial reporting related to services provided, programs and capital investment. Financial policy provides an agreed upon set of principles for the planning and programming of government budgets and their funding. Fiscal Year – A twelve-month period designated as the operating year for accounting and budgeting purposes in an organization. The City of Scottsdale’s fiscal year is July 1 through June 30. Five-Year Financial Plan – An estimation of sources and uses required by the city to operate for the next five–year period. Fleet Charges – Fees charged to other areas of the city for the maintenance, repair, and replacement of city vehicles. The fee for these charges is returned to the fleet management internal service fund as revenue. Forecast – A prediction of a future outcome based on known and unknown factors. Franchise Fee – Annual fees paid by utilities (electricity, cable TV and natural gas) for the use of city public rights of way. Franchise fees are also paid by the city’s Water & Water Reclamation Funds, as a reimbursement to the General Fund for the utility’s use of city streets and right of ways. Franchise fees are typically a set percentage of gross revenue within the city. Fringe Benefits – Contributions made by a government to meet commitments or obligations for employee-related expenses. Included is the government’s share of costs for social security and the various pension, medical, and life insurance plans. Full-Time Equivalent (FTE) – A calculation used to convert part-time hours to equivalent full-time positions. Full-time employee salaries are based on 2,080 hours per year. The full-time equivalent of a part-time employee is calculated by dividing the number of hours budgeted by 2,080. Full Cash Value – Arizona Revised Statutes defines Full Cash Value (FCV) as being synonymous with market value. For assessment purposes, full cash value approximates market value. Also see secondary assessed valuation. Fund – A fiscal and accounting entity with a self–balancing set of accounts. Records cash and other financial resources together with all related liabilities and residual equities or balances and changes therein. Funds are segregated for the purpose of carrying on specific activities or attaining certain objectives in accordance with special regulations, restrictions, or limitations. Fund Balance – The balance of net financial resources that are spendable or available for appropriation. As used in the budget, the excess of sources (revenues and cash transfers-in) over uses (expenditures, debt service, and cash transfers-out). The beginning fund balance is the residual funds brought forward from the previous fiscal year. The fund balance is comprised of a reserved fund balance and an undesignated, unreserved fund balance. The reserved fund balance is restricted for specific purposes, while the unreserved fund balance is not restricted for a specific purpose and is available for general appropriation. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 237 - Appendix Table of Contents Capital Improvement Plan |Glossary Glossary Financial SummaryAPPENDIX & Five Year Financial Forecast Fund Summary – A combined statement of sources, uses, and changes in fund balance showing the prior year’s actual, adopted, estimated budgets, and the current year’s adopted budgets. GAAP Adjustments – Differences arising from the use of a basis of accounting for budgetary purposes that differ from Generally Accepted Accounting Principles (GAAP). For example, depreciation and amortization in Enterprise Funds are not considered expenses on the budget basis of accounting but are considered expenses on the GAAP basis. General Fund – Primary operating fund of the city. It exists to account for the resources devoted to finance the services traditionally associated with local government. Included in these services are police and fire protection, parks and recreation, planning and economic development, general administration of the city, and any other activity for which a special fund has not been created. General Long-Term Debt – Represents any unmatured debt not considered to be a fund liability. General Obligation Bonds (GO Bonds) – Bonds secured by the full faith and credit of the issuer. GO bonds issued by local units of government are secured by a pledge of the issuer’s property taxing power (secondary portion). They are usually issued to pay for general capital improvements such as parks and roads. Generally Accepted Accounting Principles (GAAP) – The uniform minimum standards and guidelines to financial accounting and reporting, which govern the form and content of the basic financial statements of an entity. GAAP encompass the conventions, rules, and procedures necessary to define the accepted accounting practices at a particular time. They include both broad guidelines of general application and detailed practices and procedures. In addition, GAAP provides standards by which to measure financial presentations. Goal – A statement of broad direction, purpose or intent based on the needs of the community. A goal is general and timeless. Grant – A contribution by one government unit or funding source to another. The contribution is usually made to aid in the support of a specified function (i.e., education or drug enforcement), but it is sometimes for general purposes. Grant Capital Funds – Used to account for the proceeds of capital grants. House Bill 2111 (HB 2111) – The Arizona Department of Revenue (ADOR) simplified the transaction privilege tax, by centralizing the administration and collection of local business sales tax. Once revenue is received, ADOR will distribute the sales tax to the appropriate cities. Highway User Fuel Tax (HURF) – Gasoline tax shared with municipalities; a portion is distributed based upon the population of the city and a portion is distributed based upon the origin of the sales of the fuel. The Arizona State Constitution requires that this revenue be used solely for street and highway purposes. Improvement Districts – Consists of property owners desiring improvements to their property. Bonds are issued to finance these improvements, which are repaid by assessments on affected property. Improvement District debt is paid for by a compulsory levy (special assessment) made against certain properties to defray all or part of the cost of a specific capital improvement or service deemed to benefit primarily those properties. Indirect Cost Allocation – Funding transferred to the General Fund from Enterprise Funds for specific central administrative functions, which benefit those funds (i.e., City Manager, Information Technology, Human Resources, City Attorney, etc.). Intergovernmental Revenues – Revenues levied by one government but shared on a predetermined basis with another government or class of governments. Internal Service Fund – Established to account for the financing, on a cost-reimbursement basis, of commodities or services provided by one service area for the benefit of other service areas within the city. The city maintains Internal Service Funds to account for fleet, PC replacement and self-insurance activities. Limited Property Value – The limited property value is calculated according to a statutory formula mandated by the Arizona State Legislation and cannot exceed the full cash value (also known as secondary assessed valuation). Also see primary assessed valuation. Mission – Defines the primary purpose of the city and is intended to guide all organizational decisions, policies, and activities (internal and external) on a daily basis. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 238 - Appendix Table of Contents Capital Improvement Plan |Glossary Glossary Financial SummaryAPPENDIX & Five Year Financial Forecast Municipal Property Corporation (MPC) – A non-profit corporation established to issue bonds to fund City capital improvements projects. Needs Assessment – The foundation for determining what city customers feel is needed. Market surveys, public hearings, and boards and commission surveys are conducted to obtain this information. Objective – Something to be accomplished in specific, well-defined, and measurable terms, and that is achievable within a specific time frame. Operating Budget – The plan for current expenditures and the proposed means of financing them. The annual operating budget is the primary means by which most of the financing, acquisition, spending, and service delivery activities of a government are controlled. The use of annual operating budgets is required by law in Arizona and is a requirement of Scottsdale’s City Charter. Operating Revenue – Funds that the government receives as income to pay for ongoing operations. It includes such items as taxes, fees from specific services, interest earnings, and grant revenues. Operating revenues are used to pay for day–to–day services. Ordinance – A formal legislative enactment by the governing body of a municipality. If it is not in conflict with any higher form of law, such as a state statute or a constitutional provision, it has the full force and effect of law within the boundaries of the municipality to which it applies. Other Fiscal Activity – Refers to various trust and agency funds used to account for assets held by the city in a trustee capacity or as an agent for individuals, other governmental units, and other funds. Outstanding Debt – The balance due at any given time resulting from the borrowing of money or from the purchase of goods and services. Pay-As-You-Go Capital Improvement Projects (PAYGO) – Capital projects whose funding source is derived from city revenue sources other than through the sale of voter–approved bonds. Performance Measure – Data collected to determine how effective or efficient a service area is in achieving its objectives. Personnel Services – Includes the compensation paid periodically to employees plus employee fringe benefit costs, such as the city’s contributions to retirement, social security, health and life insurance. It also includes fees paid to elected officials, election judges, and clerks. Preserve Bonds – A category of excise tax revenue bonds and GO bonds. The bonds are special revenue obligations of the Scottsdale Preserve Authority (SPA) payable solely from and secured by either a 0.20 percent sales tax approved by city voters in 1995 and issued for the purpose of acquiring land for the Scottsdale McDowell Sonoran Preserve or a 0.15 percent sales tax approved by city voters in 2004 and issued for the purpose of acquiring land and construction of essential preserve related necessities such as proposed trailheads for the Preserve. Primary Assessed Valuation (Limited Property Value) – In Arizona, the primary assessed valuation is used to compute primary taxes for the maintenance and operation of school districts, community college districts, municipalities, counties, and the state. The limited property value is calculated according to a statutory formula mandated by the Arizona state legislation and cannot exceed the full cash value (also known as secondary assessed valuation). Primary Assessment – The amount of tax calculated according to a statutory formula based on the primary assessed valuation. Primary Property Tax – Tax levied for the purpose of funding general government operations. Annual increases are limited to two percent of the previous year’s maximum allowable primary property tax levy plus allowances for new construction and annexation of new property and tort litigation settlements. Program – A group of related activities performed by one or more organizational units for the purpose of accomplishing a function for which the city is responsible. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 239 - Appendix Table of Contents Capital Improvement Plan |Glossary Glossary Financial SummaryAPPENDIX & Five Year Financial Forecast Property Tax – Tax calculated according to value of property and used as the source of monies to support the General Fund (primary property tax) and to pay general obligation debt (secondary property tax). Each year the Maricopa County Assessor’s Office determines the value of all property, commercially and privately owned, within the county. These assessment values are then used on a pro-rata basis for levying property taxes. Property taxes are paid twice a year. The first half is due on October 1st and the second half is due on the following March 1st. Proposition 400 (Regional Sales Tax) – Tax representing revenues received from the 2004 voter approved 20-year extension of a half-cent transportation sales tax in Maricopa County that was first approved in 1985 to fund freeway construction. Racketeered Influenced Corrupt Organizations (RICO) Funds – Funds obtained from an anti–racketeering revolving fund maintained by either the federal or state government as a result of asset forfeitures from criminal enterprises. These monies are allocated to municipalities for approved non–recurring public safety expenditures. Refunding – A procedure whereby an issuer refinances an outstanding bond issue by issuing new bonds. There are generally two major reasons for refunding: (1) to reduce the issuer’s interest costs or (2) to remove a burdensome or restrictive covenant imposed by the terms of the bonds being refinanced. The proceeds of the new bonds are either deposited into escrow to pay the debt service on the outstanding obligations when due, or they are used to immediately retire the outstanding obligations. The new obligations are referred to as the refunding bonds and the outstanding obligations being refinanced are referred to as the refunded bonds or the prior issue. Regional Sales Tax (Proposition 400) – Tax representing revenues received from the 2004 voter approved 20-year extension of a half-cent transportation sales tax in Maricopa County that was first approved in 1985 to fund freeway construction. Reserve – An account which records a portion of the fund balance segregated for some future use and which is, therefore, not available for further appropriation or expenditure. Revenue Bonds – Bonds payable from a specific source of revenue, which do not pledge the full faith, and credit of the issuer. Revenue bonds are payable from identified sources of revenue and do not affect the property tax rate. Pledged revenues may be derived from operation of the financed project, grants, excise, or other specified non–property tax. Sales Tax – A tax on goods and services. Scottsdale levies a 1.1 percent sales tax, of which 0.10 percent is dedicated to public safety. The remaining 1.0 percent of the sales tax is available to fund basic municipal services such as police, fire, libraries, and parks. Sales tax receipts received in the current month are based on prior month activity. Secondary Assessed Valuation (Full Cash Value) – In Arizona, the secondary assessed valuation is used to compute secondary taxes, which may consist of those related to bonds, budget overrides, and special districts such as fire, flood control, and other limited purpose districts. Full cash value is a reflection of the market value of property. Secondary Assessment – The amount of tax calculated according to a statutory formula based on the secondary assessed valuation. Secondary Property Tax – Tax levied for the purpose of funding the principal, interest, and redemption charges on general obligation bonds of the city. The amount of this tax is determined by the annual debt service requirements on the city’s general obligation bonds. Self Insurance – The retention by an entity of a risk of loss arising out of the ownership of property or from some other cause instead of transferring that risk through the purchase of an insurance policy. Service Levels – Describes the present services provided by a city division. Sinking Fund – An account into which a debt issuer makes periodic deposits to ensure the timely availability of sufficient monies for the payment of debt service requirements. The revenues to be deposited into the sinking fund and payments from there are determined by the terms of the bond contract. Special Assessment – A compulsory levy made against certain properties to defray all or part of the cost of a specific capital improvement or service deemed to benefit primarily those properties. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 240 - Appendix Table of Contents Capital Improvement Plan |Glossary Glossary Financial SummaryAPPENDIX & Five Year Financial Forecast Special Revenue Funds – Funds established to account for the proceeds of specific revenue sources that are legally restricted to expenditures for specified purposes. The city maintains funds to support the following four special revenue sources: Transportation, Preservation, Special Programs and Tourism Development. Stakeholder – Refers to anyone affected by or who has a stake in government. This includes, but is not limited to: citizens, customers, elected officials, board and commission members, management, employees, and their representatives (whether unions or other agents), businesses, vendors, other governments, and the media. Street Light Improvement Districts – Districts formed to provide a means for properties within a district to maintain streetlights within their boundaries. A street light tax is levied against the property owner to cover the cost of electrical billings received and paid by the city. Tax Levy – The total amount of revenue to be raised by general property taxes for purposes specified in the tax levy ordinance. Tax Rate – The amount of tax levied for each $100 of assessed valuation. Taxes – Compulsory charges levied by a government for the purpose of financing services performed for common benefit. This term does not include specific charges made against particular persons or property for current or permanent benefits such as special assessments. Neither does the term include charges for services rendered only to those paying such charges, such as water service. Transfers – The authorized exchanges of cash or other resources between funds, divisions, and/or capital projects. Transportation Privilege Tax Capital Fund – Fund established to account solely for transportation projects. Transportation Sales Tax – Sales Tax of 0.1 percent which was approved by city voters in 2018 for a period of 10 years to fund transportation projects. Trend Analysis – Examination of changes over time, which provides useful management information such as the city’s current financial situation and its future financial capacity to sustain service levels. Trust Funds – Funds established to administer resources received and held by the city as the trustee or agent for others. Use of these funds facilitates the discharge of responsibility placed upon the city by virtue of law or other similar authority. Undesignated, Unreserved Fund Balance – The portion of a fund’s balance that is not restricted for a specific purpose and is available for general appropriation. Unrestricted General Capital Fund – Fund established to account for transfers-in from the General Fund and for any other activity for which a special capital fund has not been created. User Fee – The fee charged for services to a party or parties who directly benefits from the service. Work-Order Credits - Allocation of a portion of a budgeted amount to different funds or divisions based on where the work was completed. City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 241 - FY 2019/20 Adopted Budget City of Scottsdale FY 2019/20 Adopted Budget - Volume Three - 242 -